6016 S KENISTON AVE 90043

Certificate Information: 6016 S KENISTON AVE 90043

Application / Permit
22010-10000-00973
Plan Check / Job No.
B22LA03555
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Permit to Install one two-bedroom RADCO Approved Factory Built Housing Accessory Dwelling Unit over a raised floor foundation. LADBS ADU Standard Plan ADU30. FBH Per: RAD-31-1029. Optional Pre-Cast Foundation per RAD-31-1034. * LID PLAN APPROVAL REQUIRED PRIOR TO C FO O *
Permit Issued
Issued on 4/25/2022
Issuing Office
Current Status
CofO Issued on 4/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2022 APPLICANT
Assigned to Plan Check Engineer 3/1/2022 JOE VO
Corrections Issued 3/2/2022 JOE VO
Applicant returned to address corrections 3/29/2022 JOE VO
Plan Check Approved 4/20/2022 JOE VO
Issued 4/25/2022 APPLICANT
CofO in Progress 3/29/2023 ENRIQUE MIRELES
CofO in Progress 3/29/2023 ENRIQUE MIRELES
Permit Finaled 4/2/2023 DEROLD HAUFF
Permit Finaled 4/2/2023 DEROLD HAUFF
CofO Issued 4/2/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/7/2022 STEVE MELGAR
Roof/Waste drainage to street Cleared 3/7/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 3/8/2022 STEVE MELGAR
Sewer availability Cleared 3/8/2022 STEVE MELGAR
Low Impact Development Cleared 4/13/2022 KHAING AYE
Construction near power lines Cleared 4/15/2022 RIDWAN HARDY

Contact Information

Contractor United Dwelling Construction Inc; Lic. No.: 1066382-B 150 E 57TH ST      LOS ANGELES, CA 90011
Engineer Sveiven,, Shane; Lic. No.: C89133 1909 S ALMA STREET      SAN PEDRO, CA 90731

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 7/22/2022 Approved ENRIQUE MIRELES
Underground Mechanical 7/22/2022 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 8/12/2022 Approved ENRIQUE MIRELES
Wood Frame 9/2/2022 Approved ENRIQUE MIRELES
HVAC-Rough 10/14/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 2/2/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Final 2/2/2023 Approved ENRIQUE MIRELES
Final 2/2/2023 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 2/2/2023 Approved ENRIQUE MIRELES
Green Building Final 2/2/2023 Approved ENRIQUE MIRELES
Green Building Rough 2/2/2023 Approved ENRIQUE MIRELES
HVAC-Final 2/2/2023 Approved ENRIQUE MIRELES
PLUMBING-Final 2/2/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 2/2/2023 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 2/2/2023 Approved ENRIQUE MIRELES
Smoke Detectors 2/2/2023 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 2/2/2023 Approved ENRIQUE MIRELES
Final 3/24/2023 OK to Issue CofO ENRIQUE MIRELES