16410 S ORCHARD AVE 90247
Certificate Information: 16410 S ORCHARD AVE 90247
- Application / Permit
- 22010-10000-00971
- Plan Check / Job No.
- B22LA03553
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. NEW DETACHED FACTORY BUILT ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 4/13/2022
- Issuing Office
- Current Status
- CofO Issued on 4/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/1/2022 | KEVIN MORALES |
| Corrections Issued | 3/1/2022 | KEVIN MORALES |
| Applicant returned to address corrections | 4/4/2022 | KEVIN MORALES |
| Applicant returned to address corrections | 4/6/2022 | KEVIN MORALES |
| Plan Check Approved | 4/9/2022 | KEVIN MORALES |
| Issued | 4/13/2022 | APPLICANT |
| CofO in Progress | 4/5/2023 | JAMES CHAVEZ |
| Permit Finaled | 4/12/2023 | ANSON MAGLASANG |
| CofO Issued | 4/12/2023 | ANSON MAGLASANG |
| Permit Finaled | 4/12/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 3/7/2022 | HUGO LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2022 | HUGO LOPEZ |
| Sewer availability | Cleared | 3/16/2022 | HUGO LOPEZ |
| Low Impact Development | Cleared | 3/29/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 3/31/2022 | HUGO LOPEZ |
Contact Information
| Contractor | United Dwelling Construction Inc; Lic. No.: 1066382-B | 150 E 57TH ST LOS ANGELES, CA 90011 |
| Engineer | Sveiven,, Shane; Lic. No.: C89133 | 1909 S ALMA STREET SAN PEDRO, CA 90731 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/20/2022 | Corrections Issued | EUGENE CASSIDY |
| Sewer | 5/20/2022 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 5/20/2022 | Approved | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 5/25/2022 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 6/13/2022 | Partial Approval | EUGENE CASSIDY |
| MERV13>=Rough | 6/13/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 6/13/2022 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 6/29/2022 | Approved | JOHN KLARIN |
| HVAC-Rough | 7/5/2022 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 10/6/2022 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 10/6/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 10/6/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 10/6/2022 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 10/6/2022 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 10/6/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| MERV13>=Final | 10/6/2022 | Approved | ALEJANDRO DE ARTOLA |
| MERV13>=Rough | 10/6/2022 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 10/6/2022 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 10/6/2022 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/7/2022 | No Access for Inspection | JAMES CHAVEZ |
| PLUMBING-Final | 12/7/2022 | No Access for Inspection | JAMES CHAVEZ |
| Service/Power Release | 12/7/2022 | No Access for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Final | 1/13/2023 | Corrections Issued | JAMES CHAVEZ |
| PLUMBING-Final | 1/13/2023 | Approved | JAMES CHAVEZ |
| Service/Power Release | 1/13/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Final | 2/24/2023 | OK to Issue CofO | JAMES CHAVEZ |
| Service/Power Release | 2/24/2023 | Approved | JAMES CHAVEZ |