829 W 66TH ST 90044
Certificate Information: 829 W 66TH ST 90044
- Application / Permit
- 22010-10000-00969
- Plan Check / Job No.
- B22LA03515
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 35'-4"X35' 2-STORY SFD 1762 SF WITH ATTACHED 2-CAR GARAGE 591 SF (FRONT BUILDIING). 1 OF 2
- Permit Issued
- Issued on 12/1/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2022 | CHUNG-WEN CHUANG |
| Corrections Issued | 3/30/2022 | CHUNG-WEN CHUANG |
| Quality Review Completed | 4/6/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 4/8/2022 | APPLICANT |
| Plan Check Approved | 8/2/2022 | CHUNG-WEN CHUANG |
| Issued | 12/1/2022 | APPLICANT |
| CofO in Progress | 5/25/2023 | MICHAEL LEWIS |
| Permit Finaled | 6/1/2023 | DEROLD HAUFF |
| CofO Issued | 6/1/2023 | DEROLD HAUFF |
| Permit Finaled | 6/1/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/16/2022 | JEANETTE VONG |
| Permit | Cleared | 4/16/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 4/18/2022 | JEANETTE VONG |
| SB8 RUD | Cleared | 4/20/2022 | JESSICA WANG |
| Hydrant and Access approval | Cleared | 5/12/2022 | MICHAEL GILLISSIE |
| Low Impact Development | Cleared | 7/8/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 7/11/2022 | JEANETTE VONG |
| Frnt yard landscape/Water mgmt | Cleared | 7/20/2022 | MAXFIELD VERMY |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/3/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 1/23/2023 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 1/23/2023 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2023 | Partial Approval | LILIANA PORTILLO |
| Insulation | 1/24/2023 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2023 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2023 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Rough | 3/2/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 3/2/2023 | Approved | LILIANA PORTILLO |
| Sewer | 3/2/2023 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 3/2/2023 | Partial Approval | LILIANA PORTILLO |
| HVAC-Rough | 3/3/2023 | Corrections Issued | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 3/3/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 3/7/2023 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 3/7/2023 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 3/7/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 3/17/2023 | Conditional Approval | LILIANA PORTILLO |
| Green Building Rough | 3/17/2023 | Approved | LILIANA PORTILLO |
| Insulation | 3/17/2023 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 3/31/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 3/31/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 4/3/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 5/4/2023 | Partial Approval | MICHAEL LEWIS |
| ELECTRICAL-Final | 5/18/2023 | Approved | MICHAEL LEWIS |
| Green Building Final | 5/18/2023 | Approved | MICHAEL LEWIS |
| HVAC-Final | 5/18/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 5/19/2023 | Approved | MICHAEL LEWIS |
| Final | 5/19/2023 | OK to Issue CofO | MICHAEL LEWIS |
| PLUMBING-Final | 5/19/2023 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 5/19/2023 | SGSOV Approved | MICHAEL LEWIS |
| Service/Power Release | 5/19/2023 | Approved | MICHAEL LEWIS |
| Service/Power Release | 5/24/2023 | Approved | MICHAEL LEWIS |