117 W 110TH ST 90061
Certificate Information: 117 W 110TH ST 90061
- Application / Permit
- 22010-10000-00929
- Plan Check / Job No.
- B22LA03346
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY ADU PER LAMC 12.22 A.33 (c)-(d) WITH ATTACHED GARAGE (REAR BUILDING)
- Permit Issued
- Issued on 1/26/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/20/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 3/16/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 3/25/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 3/30/2022 | APPLICANT |
| Plan Check Approved | 8/3/2022 | MAHNAZ NOURHASHEMI |
| Issued | 1/26/2023 | APPLICANT |
| CofO in Progress | 10/14/2023 | JAMES CHAVEZ |
| CofO Issued | 10/20/2023 | ANSON MAGLASANG |
| Permit Finaled | 10/20/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 4/6/2022 | CHRISTOPHER ROCHA |
| Permit | Cleared | 4/6/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 4/26/2022 | CHRISTOPHER ROCHA |
| Hydrant and Access approval | Cleared | 5/3/2022 | CINDY JOSSELYN |
| SB8 RUD | Cleared | 5/24/2022 | JESSICA WANG |
| Low Impact Development | Cleared | 6/3/2022 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 6/9/2022 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/13/2023 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2023 | Partial Approval | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2023 | Approved | JAMES CHAVEZ |
| HVAC-Rough | 5/18/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Rough | 5/18/2023 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 5/19/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Rough | 5/19/2023 | Approved | JAMES CHAVEZ |
| Green Building Rough | 5/19/2023 | Approved | JAMES CHAVEZ |
| Verify Sprinkler Sign Off | 5/19/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Insulation | 6/1/2023 | Approved | JAMES CHAVEZ |
| Drywall Nailing | 6/6/2023 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 6/6/2023 | Approved | JAMES CHAVEZ |
| Sewer | 7/6/2023 | Approved | JAMES CHAVEZ |
| Underground Mechanical | 7/6/2023 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Final | 7/19/2023 | Partial Approval | JAMES CHAVEZ |
| HVAC-Final | 10/12/2023 | Approved | JOHN KLARIN |
| PLUMBING-Final | 10/12/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 10/13/2023 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Final | 10/13/2023 | Approved | JAMES CHAVEZ |
| Final | 10/13/2023 | OK to Issue CofO | JAMES CHAVEZ |
| Green Building Final | 10/13/2023 | Approved | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 10/13/2023 | SGSOV Approved | JAMES CHAVEZ |
| Service/Power Release | 10/13/2023 | Approved | JAMES CHAVEZ |
| Smoke Detectors | 10/13/2023 | Approved | JAMES CHAVEZ |
| Verify Sprinkler Sign Off | 10/13/2023 | Approved | JAMES CHAVEZ |
| Service/Power Release | 10/16/2023 | Approved | JAMES CHAVEZ |