5544 W 82ND ST 90045

Certificate Information: 5544 W 82ND ST 90045

Application / Permit
22010-10000-00922
Plan Check / Job No.
B22LA03297
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of an (E) detached garage and storage into an ADU per state law GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 6/3/2022
Issuing Office
Current Status
CofO Issued on 1/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/24/2022 APPLICANT
Assigned to Plan Check Engineer 2/25/2022 HELEN NGUYEN
Corrections Issued 2/25/2022 HELEN NGUYEN
Applicant returned to address corrections 4/5/2022 HELEN NGUYEN
Applicant returned to address corrections 4/7/2022 HELEN NGUYEN
Plan Check Approved 5/1/2022 JOE VO
Issued 6/3/2022 APPLICANT
CofO in Progress 1/19/2023 BOBBY KEY
Permit Finaled 1/23/2023 DANIEL ORRANTE
CofO Issued 1/23/2023 DANIEL ORRANTE
Permit Finaled 1/23/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/4/2022 JOSE RODRIGUEZ
Sewer availability Cleared 3/4/2022 JOSE RODRIGUEZ
Eng Process Fee Ord 176,300 Cleared 3/18/2022 ANTHONY MAINEZ
Specific Plan Cleared 3/24/2022 MIGUEL GAMBOA
ZA Case Cleared 3/24/2022 MIGUEL GAMBOA
Construction within easement Cleared 4/15/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Saiyadian, Sarnaghi, Tomik; Lic. No.: C89129 1171 JUSTIN AVE APT 3      GLENDALE, CA 91201

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/10/2022 Corrections Issued BOBBY KEY
Pre-Inspection 6/10/2022 Partial Inspection BOBBY KEY
Sewer 6/17/2022 Approved STEPHANIE SWANSON
Footing/Foundation/Slab 7/12/2022 Approved BOBBY KEY
ELECTRICAL-Rough 8/5/2022 Approved BOBBY KEY
HVAC-Rough 8/5/2022 Approved BOBBY KEY
PLUMBING-Rough 8/5/2022 Approved BOBBY KEY
Underground Mechanical 8/5/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 8/17/2022 Corrections Issued BOBBY KEY
Underground Mechanical 8/17/2022 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 9/1/2022 Approved BOBBY KEY
Green Building Rough 9/20/2022 Approved BOBBY KEY
Interior/Exterior Lathing 9/20/2022 Partial Approval BOBBY KEY
PLUMBING-Rough 9/20/2022 Approved BOBBY KEY
Insulation 10/3/2022 Approved BOBBY KEY
Drywall Nailing 10/11/2022 Approved BOBBY KEY
ELECTRICAL-Final 11/17/2022 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Final 1/13/2023 Corrections Issued HERBERT GIRON
Final 1/13/2023 Corrections Issued HERBERT GIRON
Gas Test 1/13/2023 Approved HERBERT GIRON
Green Building Final 1/13/2023 Corrections Issued HERBERT GIRON
HVAC-Final 1/13/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 1/13/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 1/13/2023 SGSOV Approved HERBERT GIRON
Smoke Detectors 1/13/2023 Approved HERBERT GIRON
ELECTRICAL-Final 1/18/2023 Not Ready for Inspection BOBBY KEY
Final 1/18/2023 Not Ready for Inspection BOBBY KEY
Green Building Final 1/18/2023 Approved BOBBY KEY
HVAC-Final 1/18/2023 Approved BOBBY KEY
Final 1/19/2023 OK to Issue CofO BOBBY KEY