12906-12908 W RUBENS AVE 90066
Certificate Information: 12906-12908 W RUBENS AVE 90066
- Application / Permit
- 22010-10000-00875
- Plan Check / Job No.
- B22LA03101
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (E) 1-STORY SFD WITH ATTACHED 1-CAR GARAGE. PROPOSED GROUND FLOOR AND 2ND FLOOR ADDITION TO MAKE 2-STORY SFD WITH ATTACHED 2-CAR GARAGE AND ATTACHED ADU PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 9/27/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2022 | KHEDER ALRAZAA |
| Corrections Issued | 4/1/2022 | KHEDER ALRAZAA |
| Quality Review Completed | 4/7/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 4/12/2022 | APPLICANT |
| Applicant returned to address corrections | 7/27/2022 | KHEDER ALRAZAA |
| Plan Check Approved | 8/4/2022 | KHEDER ALRAZAA |
| Issued | 9/27/2022 | APPLICANT |
| CofO in Progress | 2/29/2024 | TEMISTOCLES CAAL |
| Permit Finaled | 3/6/2024 | DANIEL ORRANTE |
| CofO Issued | 3/6/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/6/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 6/21/2022 | SARAH YOUSSEF |
| Specific Plan | Cleared | 6/30/2022 | VALERIA CEJA |
| Hydrant and Access approval | Cleared | 7/5/2022 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2022 | JENSON LEE |
| Miscellaneous | Cleared | 7/7/2022 | JENSON LEE |
| Roof/Waste drainage to street | Cleared | 7/7/2022 | JENSON LEE |
| Sewer availability | Cleared | 7/7/2022 | JENSON LEE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mallak,, Nabil Michel; Lic. No.: S5351 | 3679 MOTOR AVE SUITE 201 LOS ANGELES, CA 90034 |
| Geologist | Minas,, Shant; Lic. No.: EG2607 | 566 RIVERDALE DRIVE GLENDALE, CA 91204 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/13/2022 | Partial Approval | HERBERT GIRON |
| Sewer | 12/13/2022 | Partial Approval | HERBERT GIRON |
| Deputy Drilled-In Anchors | 12/27/2022 | Conditional Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 2/8/2023 | Approved | HERBERT GIRON |
| Footing/Foundation/Slab | 2/8/2023 | Approved | HERBERT GIRON |
| METHANE-Barrier | 2/8/2023 | Approved | HERBERT GIRON |
| METHANE-Subgrade | 2/8/2023 | Approved | HERBERT GIRON |
| Sewer | 2/10/2023 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2023 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2023 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2023 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2023 | Conditional Approval | HERBERT GIRON |
| ELECTRICAL-Rough | 5/11/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 5/11/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 5/11/2023 | Partial Approval | HERBERT GIRON |
| MERV13>=Rough | 5/11/2023 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 5/11/2023 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 5/15/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 5/15/2023 | Approved | HERBERT GIRON |
| Green Building Rough | 5/15/2023 | Approved | HERBERT GIRON |
| METHANE-Rough | 5/15/2023 | Approved | HERBERT GIRON |
| Verify Sprinkler Sign Off | 5/15/2023 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 5/18/2023 | Approved | HERBERT GIRON |
| Insulation | 6/6/2023 | Approved | HERBERT GIRON |
| Shower Pan | 6/6/2023 | Partial Approval | HERBERT GIRON |
| Drywall Nailing | 6/26/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 7/3/2023 | Approved | RICHARD STEINBACH |
| Shower Pan | 7/25/2023 | Approved | HERBERT GIRON |
| Gas Test | 11/2/2023 | Approved | HERBERT GIRON |
| Underground Mechanical | 11/13/2023 | Approved | TEMISTOCLES CAAL |
| Underground Mechanical | 11/22/2023 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 12/28/2023 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Final | 12/28/2023 | Not Ready for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Final | 12/28/2023 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Service/Power Release | 12/28/2023 | Not Ready for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Final | 1/3/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Final | 1/10/2024 | Approved | BOBBY KEY |
| Special/Order Compliance | 1/10/2024 | Partial Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 1/12/2024 | Approved | TEMISTOCLES CAAL |
| Final | 1/12/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Green Building Final | 1/12/2024 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Final | 1/12/2024 | Approved | TEMISTOCLES CAAL |
| MERV13>=Final | 1/12/2024 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 1/12/2024 | SGSOV Approved | TEMISTOCLES CAAL |
| Service/Power Release | 1/12/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Smoke Detectors | 1/12/2024 | Approved | TEMISTOCLES CAAL |
| Final | 2/28/2024 | OK to Issue CofO | TEMISTOCLES CAAL |
| Green Building Final | 2/28/2024 | Approved | TEMISTOCLES CAAL |
| Service/Power Release | 2/28/2024 | Approved | TEMISTOCLES CAAL |