1445 E 43RD PL 90011

Certificate Information: 1445 E 43RD PL 90011

Application / Permit
22010-10000-00874
Plan Check / Job No.
B22LA03095
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Proposed 1-Story Accessory Dwelling Unit (ADU) 875 SF at Rear Per Ordinance.
Permit Issued
Issued on 1/24/2025
Issuing Office
Metro
Current Status
CofO Issued on 2/24/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/7/2022 APPLICANT
Assigned to Plan Check Engineer 3/8/2022 MINA HABILI
Corrections Issued 3/8/2022 MINA HABILI
Building Plans Picked Up 3/24/2022 APPLICANT
Plan Check Approved 6/22/2022 KHUONG TRUONG
Issued 1/24/2025 APPLICANT
CofO in Progress 2/23/2026 ALEJANDRO DE ARTOLA
Permit Finaled 2/24/2026 DEROLD HAUFF
CofO Issued 2/24/2026 DEROLD HAUFF
Permit Finaled 2/24/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/8/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 4/12/2022 WALLIE JONG
Sewer availability Cleared 4/12/2022 WALLIE JONG
Low Impact Development Cleared 6/16/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 6/21/2022 TREVOR QUAN

Contact Information

Contractor Napoles Builders Inc; Lic. No.: 1013480-B 294 EAST 47TH PLACE      LOS ANGELES, CA 90011

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/4/2025 Corrections Issued BARRY HACHE
PLUMBING-Rough 8/4/2025 Not Ready for Inspection BARRY HACHE
Excavation/Setback/Form/Re-Bar 8/11/2025 Approved LUIS CASTRO
Footing/Foundation/Slab 8/11/2025 Corrections Issued LUIS CASTRO
PLUMBING-Rough 8/11/2025 Partial Approval LUIS CASTRO
BUILDING-Rough-Frame 9/12/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 9/12/2025 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 9/12/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 9/12/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 9/12/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 9/12/2025 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 9/12/2025 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 9/30/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 9/30/2025 Approved ALEJANDRO DE ARTOLA
Green Building Rough 9/30/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 9/30/2025 Approved ALEJANDRO DE ARTOLA
Insulation 9/30/2025 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 9/30/2025 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 9/30/2025 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 10/17/2025 Approved ANTHONY RAMOS
Insulation 10/17/2025 Approved ANTHONY RAMOS
Sewer 12/1/2025 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 12/1/2025 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 12/2/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 1/30/2026 Corrections Issued ALEJANDRO DE ARTOLA
Final 1/30/2026 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 1/30/2026 Approved ALEJANDRO DE ARTOLA
Green Building Final 1/30/2026 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 1/30/2026 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 1/30/2026 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 2/20/2026 Approved ALEJANDRO DE ARTOLA
Final 2/20/2026 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 2/20/2026 Approved ALEJANDRO DE ARTOLA
Green Building Final 2/20/2026 Approved ALEJANDRO DE ARTOLA
HVAC-Final 2/20/2026 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 2/20/2026 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 2/20/2026 SGSOV Approved ALEJANDRO DE ARTOLA
Smoke Detectors 2/20/2026 Approved ALEJANDRO DE ARTOLA
Final 2/23/2026 OK to Issue CofO ALEJANDRO DE ARTOLA