4420 1/2 W 63RD ST 90043
Certificate Information: 4420 1/2 W 63RD ST 90043
- Application / Permit
- 22010-10000-00848
- Plan Check / Job No.
- B22LA03031
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 3/11/2022
- Issuing Office
- Current Status
- CofO Corrected on 4/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2022 | DANIEL YIP |
| Corrections Issued | 2/23/2022 | DANIEL YIP |
| Applicant returned to address corrections | 3/4/2022 | DANIEL YIP |
| Applicant returned to address corrections | 3/7/2022 | DANIEL YIP |
| Plan Check Approved | 3/11/2022 | DANIEL YIP |
| Issued | 3/11/2022 | APPLICANT |
| CofO in Progress | 10/26/2022 | MICHAEL LEWIS |
| CofO Issued-Status Void | 12/28/2022 | DEROLD HAUFF |
| Permit Finaled-Status Void | 12/28/2022 | DEROLD HAUFF |
| Re-Activate Permit | 4/3/2024 | DEROLD HAUFF |
| Permit Finaled | 4/16/2024 | DEROLD HAUFF |
| CofO Corrected | 4/16/2024 | DEROLD HAUFF |
| Permit Finaled | 4/16/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/4/2022 | CINDY QI |
| Sewer availability | Cleared | 3/4/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2022 | CINDY QI |
Contact Information
| Contractor | Kvm Homes Llc; Lic. No.: 911466-B | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/31/2022 | Approved | ENRIQUE MIRELES |
| Pre-Inspection | 4/15/2022 | Approved | HORACE FULTZ |
| Sewer | 4/19/2022 | Approved | ENRIQUE MIRELES |
| Pre-Inspection | 4/25/2022 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 4/25/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 5/5/2022 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 5/9/2022 | Approved | HORACE FULTZ |
| Footing/Foundation/Slab | 5/12/2022 | Corrections Issued | ENRIQUE MIRELES |
| Underground Mechanical | 5/16/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 5/23/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 7/1/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 7/6/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 7/7/2022 | Corrections Issued | ENRIQUE MIRELES |
| Pre-Inspection | 7/12/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 7/18/2022 | Approved | ENRIQUE MIRELES |
| Insulation | 7/22/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 7/26/2022 | Approved | ADAM ESCOTO |
| Pre-Inspection | 7/28/2022 | Approved | ENRIQUE MIRELES |
| Pre-Inspection | 8/10/2022 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 8/18/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 8/18/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 9/20/2022 | Approved | ENRIQUE MIRELES |
| Final | 9/20/2022 | Corrections Issued | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 9/20/2022 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 9/20/2022 | Approved | ENRIQUE MIRELES |
| Final | 10/13/2022 | Corrections Issued | ENRIQUE MIRELES |
| Final | 10/25/2022 | OK to Issue CofO | MICHAEL LEWIS |