*EPLAN* NEW 1-STORY DETACHED ADU (484 SF) WITH ATTACHED 1-CAR GARAGE (242 SF) PER LAMC 12.22A.33(c)(-(d).
Permit Issued
Issued on 2/28/2023
Issuing Office
Current Status
Issued on 2/28/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/22/2022 APPLICANT
Assigned to Plan Check Engineer 2/23/2022 VIVIAN LAO
Corrections Issued 2/24/2022 VIVIAN LAO
Applicant returned to address corrections 1/18/2023 JOSEPH RAFOLS
Applicant returned to address corrections 2/13/2023 JOSEPH RAFOLS
Plan Check Approved 2/22/2023 JOSEPH RAFOLS
Issued 2/28/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/9/2022 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 6/9/2022 JOSE HERNANDEZ
Sewer availability Cleared 6/9/2022 JOSE HERNANDEZ
Low Impact Development Cleared 12/28/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 1/17/2023 ANA SORIANO

Contact Information

Contractor Owner-Builder       ,
Engineer Tiongco,, John Lazarraga; Lic. No.: C70915 17715 CANEHILL AVE      BELLFLOWER, CA 90706

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/23/2023 Partial Approval EUGENE CASSIDY
METHANE-Barrier 5/23/2023 Not Ready for Inspection EUGENE CASSIDY
METHANE-Subgrade 5/23/2023 Not Ready for Inspection EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 6/5/2023 Partial Approval EUGENE CASSIDY
METHANE-Barrier 6/5/2023 Not Ready for Inspection EUGENE CASSIDY
METHANE-Subgrade 6/5/2023 Not Ready for Inspection EUGENE CASSIDY
Deputy Methane Barrier 6/7/2023 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 6/8/2023 Corrections Issued EUGENE CASSIDY
METHANE-Barrier 6/8/2023 Approved EUGENE CASSIDY
METHANE-Subgrade 6/8/2023 Approved EUGENE CASSIDY
Footing/Foundation/Slab 6/12/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 7/5/2023 Corrections Issued EUGENE CASSIDY
Green Building Rough 7/5/2023 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 7/5/2023 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 7/5/2023 Approved EUGENE CASSIDY
ELECTRICAL-Rough 7/7/2023 Approved JOHN KLARIN
PLUMBING-Rough 7/7/2023 Approved JOHN KLARIN
Insulation 7/13/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 7/13/2023 Partial Approval EUGENE CASSIDY
Drywall Nailing 7/17/2023 Approved EUGENE CASSIDY
Green Building Rough 7/17/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 7/27/2023 Approved EUGENE CASSIDY
Shower Pan 7/27/2023 Approved EUGENE CASSIDY
ELECTRICAL-Rough 8/15/2023 Approved EUGENE CASSIDY
PLUMBING-Rough 8/15/2023 Approved EUGENE CASSIDY
Sewer 8/15/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 10/19/2023 Approved EUGENE CASSIDY
Final 10/19/2023 Corrections Issued EUGENE CASSIDY
Green Building Final 10/19/2023 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 10/19/2023 SGSOV Approved EUGENE CASSIDY
Service/Power Release 10/19/2023 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 10/19/2023 Approved EUGENE CASSIDY
Final 4/7/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 4/7/2025 Approved EUGENE CASSIDY
Service/Power Release 4/7/2025 Not Required EUGENE CASSIDY