2009 S PENMAR AVE 90291

Certificate Information: 2009 S PENMAR AVE 90291

Application / Permit
22010-10000-00835
Plan Check / Job No.
B22LA02996
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY DETACHED ADU
Permit Issued
Issued on 2/14/2024
Issuing Office
Current Status
CofO Corrected on 6/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2022 APPLICANT
Disabled Access Plans Picked Up 3/14/2022 APPLICANT
Assigned to Plan Check Engineer 3/17/2022 HERNAN ARREOLA
Green Plans Picked Up 3/21/2022 APPLICANT
Corrections Issued 3/31/2022 HERNAN ARREOLA
Quality Review Completed 4/6/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 4/8/2022 APPLICANT
Applicant returned to address corrections 2/9/2023 HERNAN ARREOLA
Plan Check Approved 2/8/2024 HERNAN ARREOLA
Issued 2/14/2024 APPLICANT
CofO Issued-Status Void 6/20/2025 RICHARD STEINBACH
Permit Finaled-Status Void 6/20/2025 RICHARD STEINBACH
Re-Activate Permit 6/26/2025 RICHARD STEINBACH
Permit Finaled 6/26/2025 RICHARD STEINBACH
CofO Corrected 6/26/2025 RICHARD STEINBACH
Permit Finaled 6/26/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 8/4/2023 DARIN LAM
"Q" conditions Cleared 8/14/2023 JAZMIN ROQUE
Tenant Habitability Plan Cleared 8/15/2023 ISMAEL HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 8/22/2023 DARIN LAM
Sewer availability Cleared 8/22/2023 DARIN LAM
Specific Plan Cleared 8/29/2023 PEDRO AYALA
Hydrant and Access approval Cleared 9/9/2023 JOHN CONNEALLY
Green Code Cleared 11/29/2023 MICHAEL AYERS
Roof/Waste drainage to street Cleared 2/1/2024 DARIN LAM

Contact Information

Architect Uriu,, Giovanni; Lic. No.: C7487 830 SO GLENDALE AVENUE      GLENDALE, CA 91205
Contractor Concord Construction Inc; Lic. No.: 1077056-B 449 SOUTH BEVERLY DRIVE   1ST FLOOR    BEVERLY HILLS, CA 90212

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 8/8/2024 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 8/28/2024 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 9/6/2024 Not Ready for Inspection HERBERT GIRON
Footing/Foundation/Slab 9/10/2024 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/24/2024 Corrections Issued TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 10/30/2024 Partial Approval BOBBY KEY
Green Building Rough 1/2/2025 Approved KENNETH NAGLE
Insulation 1/2/2025 Approved KENNETH NAGLE
Wood Frame 1/2/2025 Approved KENNETH NAGLE
Drywall Nailing 6/4/2025 Approved JESUS RODRIGUEZ
Final 6/4/2025 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 6/4/2025 Approved JESUS RODRIGUEZ
Green Building Final 6/4/2025 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 6/4/2025 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 6/4/2025 Approved JESUS RODRIGUEZ
Final 6/16/2025 Partial Approval JESUS RODRIGUEZ
Final 6/20/2025 Conditional Approval DAVID FEILER