1519 W 58TH ST 90062
Certificate Information: 1519 W 58TH ST 90062
- Application / Permit
- 22010-10000-00797
- Plan Check / Job No.
- B22LA02851
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan CONVERT EXISTING DETACHED 2-CAR GARAGE TO A NEW ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) [306 SQ.FT]
- Permit Issued
- Issued on 3/24/2022
- Issuing Office
- Current Status
- CofO Issued on 6/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2022 | CARLOS MONTES |
| Corrections Issued | 2/18/2022 | CARLOS MONTES |
| Plan Check Approved | 3/23/2022 | CARLOS MONTES |
| Issued | 3/24/2022 | APPLICANT |
| CofO in Progress | 6/5/2024 | CRAIG DAVIS |
| CofO Issued | 6/10/2024 | DEROLD HAUFF |
| Permit Finaled | 6/10/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/4/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 3/4/2022 | JEANETTE VONG |
| CPC | Cleared | 3/9/2022 | STEVEN WECHSLER |
Contact Information
| Architect | Di, Zitti, Fernando; Lic. No.: C24587 | 21243 VENTURA BLVD #115 WOODLAND HILLS, CA 91364 |
| Architect | Di, Zitti, Fernando; Lic. No.: NA24587 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/26/2022 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 5/12/2022 | Partial Approval | SABAS ALONSO |
| Sewer | 5/12/2022 | Approved | SABAS ALONSO |
| Underground Mechanical | 5/12/2022 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 5/19/2022 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 7/28/2022 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 7/28/2022 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Rough | 7/28/2022 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Rough | 7/28/2022 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 7/28/2022 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 8/2/2022 | No Access for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/3/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 8/3/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 8/3/2022 | Approved | SABAS ALONSO |
| HVAC-Rough | 8/3/2022 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 8/3/2022 | Approved | SABAS ALONSO |
| Insulation | 8/4/2022 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2022 | Partial Approval | SABAS ALONSO |
| Drywall Nailing | 9/1/2022 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 10/20/2023 | SGSOV Not Ready | JUSTIN HAWLEY |
| Final | 11/1/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 11/1/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 11/1/2023 | SGSOV Not Ready | ENRIQUE MIRELES |
| Smoke Detectors | 11/1/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 12/1/2023 | Corrections Issued | CRAIG DAVIS |
| Green Building Final | 12/1/2023 | Approved | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 12/1/2023 | SGSOV Approved | CRAIG DAVIS |
| Smoke Detectors | 12/1/2023 | Approved | CRAIG DAVIS |
| Final | 1/26/2024 | Corrections Issued | RONNIE MINDANAO |
| Final | 4/12/2024 | No Access for Inspection | CRAIG DAVIS |
| Final | 5/22/2024 | Partial Inspection | CRAIG DAVIS |
| Service/Power Release | 5/23/2024 | No Access for Inspection | CRAIG DAVIS |
| Final | 6/4/2024 | OK to Issue CofO | CRAIG DAVIS |
| Service/Power Release | 6/4/2024 | Approved | CRAIG DAVIS |