4844-4844 1/2 E MALTA ST 90042

Certificate Information: 4844-4844 1/2 E MALTA ST 90042

Application / Permit
22010-10000-00794
Plan Check / Job No.
B22LA02847
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: CONVERT (E) GARAGE IN SINGLE FAMILY DWELLING TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 8/4/2024
Issuing Office
Current Status
Issued on 8/4/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/23/2022 APPLICANT
Assigned to Plan Check Engineer 2/24/2022 DANIEL YIP
Corrections Issued 2/24/2022 CARLOS MONTES
Applicant returned to address corrections 9/13/2022 DANIEL YIP
Applicant returned to address corrections 9/23/2022 JESSE ARELLANO
Applicant returned to address corrections 11/1/2022 SUNMIN LEE
Applicant returned to address corrections 3/23/2023 SUNMIN LEE
Plan Check Approved 5/18/2023 DANIEL YIP
Issued 8/4/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/17/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 3/17/2022 JEANETTE VONG
Sewer availability Cleared 3/17/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 4/6/2022 JEANETTE VONG
Hydrant and Access approval Cleared 4/22/2022 DWAYNE LAURENT
Specific Plan Cleared 4/28/2022 NASHYA JENSEN
Low Impact Development Cleared 9/8/2022 ROGELIO CORTES
GPI Written Notices Cleared 9/13/2022 CARLOS MONTES
Grading Pre-Inspection Cleared 9/13/2022 CARLOS MONTES
Tenant Habitability Plan Cleared 10/4/2022 MICHAEL SOTO

Contact Information

Contractor Espino Roberto; Lic. No.: 924261-B       ,
Contractor Marb Construction Management; Lic. No.: 924261-B       ,
Engineer Baraty,, Patrick; Lic. No.: S5900 1819 SUNSHINE COURT      GLENDALE, CA 91208

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/8/2024 Partial Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 9/6/2024 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 9/6/2024 Approved ALIZAH MAYAGOITIA
Footing/Foundation/Slab 9/13/2024 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 9/20/2024 Corrections Issued ALIZAH MAYAGOITIA
Wood Frame 9/20/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 9/24/2024 Not Ready for Inspection OSVALDO PARAMO
Wood Frame 9/24/2024 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 9/27/2024 Partial Inspection OSVALDO PARAMO
Wood Frame 9/27/2024 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 9/30/2024 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 10/8/2024 Partial Approval ALIZAH MAYAGOITIA
Wood Frame 10/8/2024 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Rough 10/22/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Rough 10/22/2024 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 10/22/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Wood Frame 10/22/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 10/24/2024 Partial Approval ALIZAH MAYAGOITIA
HVAC-Rough 10/24/2024 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 10/24/2024 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Rough 11/21/2024 Approved ALIZAH MAYAGOITIA
Gas Test 11/21/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Rough 11/21/2024 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 11/21/2024 Partial Approval ALIZAH MAYAGOITIA
Underground Mechanical 11/21/2024 Corrections Issued ALIZAH MAYAGOITIA
Wood Frame 11/21/2024 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Rough 12/5/2024 Approved ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 12/5/2024 Corrections Issued ROY SPAULDING
HVAC-Rough 12/5/2024 Approved ROY SPAULDING
PLUMBING-Rough 12/5/2024 Partial Approval ROY SPAULDING
BUILDING-Rough-Frame 12/9/2024 Corrections Issued OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 12/9/2024 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 12/13/2024 Approved OSVALDO PARAMO
Interior/Exterior Lathing 12/13/2024 Partial Approval OSVALDO PARAMO
Insulation 12/17/2024 Corrections Issued ALEX COLIN
Interior/Exterior Lathing 12/17/2024 Approved ALEX COLIN
Shower Pan 12/17/2024 Approved ALEX COLIN
Drywall Nailing 1/21/2025 Approved JOSH MEISTER
Pre-Inspection 9/17/2025 Partial Inspection LILIANA PORTILLO
Final 5/20/2026 Not Ready for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 5/20/2026 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 5/20/2026 Not Ready for Inspection OSVALDO PARAMO