4640 W 5TH ST 90020
Certificate Information: 4640 W 5TH ST 90020
- Application / Permit
- 22010-10000-00786
- Plan Check / Job No.
- B21LA24533
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. New 2-story accessory building. 2-Car Garage & Pool bath at 1st floor. Accessory Dwelling Unit on 2nd floor.
- Permit Issued
- Issued on 2/6/2023
- Issuing Office
- Current Status
- CofO Issued on 9/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2022 | PRANITA SHAH |
| Corrections Issued | 3/29/2022 | PRANITA SHAH |
| Quality Review Completed | 4/3/2022 | HERNAN ARREOLA |
| Applicant returned to address corrections | 10/26/2022 | PRANITA SHAH |
| Applicant returned to address corrections | 12/13/2022 | PRANITA SHAH |
| Plan Check Approved | 1/9/2023 | PRANITA SHAH |
| Issued | 2/6/2023 | APPLICANT |
| CofO in Progress | 9/24/2025 | JEFFREY MEAD |
| Permit Finaled | 9/27/2025 | DEROLD HAUFF |
| Permit Finaled | 9/27/2025 | DEROLD HAUFF |
| CofO Issued | 9/27/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/16/2022 | JEANETTE VONG |
| Permit | Cleared | 4/16/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 4/18/2022 | JEANETTE VONG |
| Trees in Parkway | Cleared | 7/13/2022 | ADALBERTO VERA |
| HPOZ | Cleared | 7/18/2022 | LYDIA CHAPMAN |
| Low Impact Development | Cleared | 9/15/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 9/20/2022 | JEANETTE VONG |
Contact Information
| Contractor | C C Noble Inc; Lic. No.: 894239-B | , |
| Contractor | Noble Construction Co; Lic. No.: 894239-B | , |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
| Engineer | Ruan,, Federico R; Lic. No.: S6689 | 553 S OAK KNOLL AVE PASADENA, CA 91101 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/19/2023 | Approved | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 7/24/2023 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 8/18/2023 | Partial Approval | JEFFREY MEAD |
| METHANE-Subgrade | 8/18/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 8/18/2023 | Partial Approval | JEFFREY MEAD |
| Footing/Foundation/Slab | 9/14/2023 | Approved | JEFFREY MEAD |
| METHANE-Barrier | 9/14/2023 | Approved | JEFFREY MEAD |
| Deputy Wood Construction | 2/28/2024 | Partial Approval | JEFFREY MEAD |
| ELECTRICAL-Rough | 3/11/2024 | Approved | JEFFREY MEAD |
| HVAC-Rough | 3/11/2024 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 3/11/2024 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 4/11/2024 | Corrections Issued | JEFFREY MEAD |
| Green Building Rough | 4/11/2024 | Approved | JEFFREY MEAD |
| METHANE-Rough | 4/11/2024 | Partial Approval | JEFFREY MEAD |
| Shower Pan | 4/11/2024 | Approved | JEFFREY MEAD |
| Insulation | 4/24/2024 | Partial Approval | JEFFREY MEAD |
| Drywall Nailing | 5/24/2024 | Partial Approval | JEFFREY MEAD |
| Interior/Exterior Lathing | 6/6/2024 | Partial Approval | JEFFREY MEAD |
| Interior/Exterior Lathing | 6/27/2024 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 7/30/2024 | Approved | JEFFREY MEAD |
| Underground Mechanical | 8/7/2024 | Corrections Issued | JEFFREY MEAD |
| ELECTRICAL-Final | 5/8/2025 | Approved | JEFFREY MEAD |
| Final | 5/8/2025 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 5/8/2025 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 5/8/2025 | Approved | JEFFREY MEAD |
| Smoke Detectors | 5/8/2025 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 7/22/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 8/4/2025 | Approved | JEFFREY MEAD |
| Drywall Nailing | 8/4/2025 | Approved | JEFFREY MEAD |
| Final | 8/4/2025 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 8/4/2025 | Approved | JEFFREY MEAD |
| METHANE-Final | 8/4/2025 | Approved | JEFFREY MEAD |
| METHANE-Rough | 8/4/2025 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 8/4/2025 | SGSOV Approved | JEFFREY MEAD |
| Service/Power Release | 8/4/2025 | Not Required | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 8/4/2025 | Approved | JEFFREY MEAD |
| Final | 8/26/2025 | Partial Approval | JEFFREY MEAD |
| Final | 9/19/2025 | Partial Approval | JEFFREY MEAD |
| Final | 9/23/2025 | OK to Issue CofO | JEFFREY MEAD |