2940 3/4 S 9TH AVE 90018
Certificate Information: 2940 3/4 S 9TH AVE 90018
- Application / Permit
- 22010-10000-00764
- Plan Check / Job No.
- B22LA02797
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Install one two-bedroom RADCO Approved Factory Built Housing Accessory Dwelling Unit over a raised floor foundation. LADBS ADU Standard Plan ADU30. FBH Per: RAD-31-1029. Optional Pre-Cast Foundation per RAD-31-1034.
- Permit Issued
- Issued on 4/13/2022
- Issuing Office
- Current Status
- CofO Issued on 10/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2022 | JOE VO |
| Corrections Issued | 2/21/2022 | JOE VO |
| Applicant returned to address corrections | 3/7/2022 | JOE VO |
| Plan Check Approved | 4/11/2022 | JOE VO |
| Issued | 4/13/2022 | APPLICANT |
| CofO in Progress | 10/2/2023 | CALEB MEISTER |
| Permit Finaled | 10/24/2023 | DEROLD HAUFF |
| CofO Issued | 10/24/2023 | DEROLD HAUFF |
| Permit Finaled | 10/24/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 2/22/2022 | MICHAEL SOTO |
| Address approval | Cleared | 2/25/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/1/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 3/1/2022 | JEANETTE VONG |
| Low Impact Development | Cleared | 3/29/2022 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 3/30/2022 | JEANETTE VONG |
| Construction near power lines | Cleared | 4/1/2022 | RIDWAN HARDY |
Contact Information
| Contractor | United Dwelling Construction Inc; Lic. No.: 1066382-B | 150 E 57TH ST LOS ANGELES, CA 90011 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/24/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Footing/Foundation/Slab | 4/24/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 5/2/2023 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 5/17/2023 | Partial Approval | CALEB MEISTER |
| Green Building Rough | 5/17/2023 | Not Ready for Inspection | CALEB MEISTER |
| Underground Mechanical | 5/17/2023 | Partial Approval | CALEB MEISTER |
| Verify Sprinkler Sign Off | 5/17/2023 | Not Ready for Inspection | CALEB MEISTER |
| Underground Mechanical | 6/7/2023 | Approved | CALEB MEISTER |
| Wood Frame | 6/15/2023 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Final | 8/9/2023 | Not Ready for Inspection | CALEB MEISTER |
| HVAC-Final | 8/9/2023 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Final | 8/9/2023 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 9/28/2023 | Approved | CALEB MEISTER |
| Final | 9/28/2023 | OK to Issue CofO | CALEB MEISTER |
| Footing/Foundation/Slab | 9/28/2023 | Approved | CALEB MEISTER |
| Green Building Final | 9/28/2023 | Approved | CALEB MEISTER |
| Green Building Rough | 9/28/2023 | Approved | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 9/28/2023 | SGSOV Approved | CALEB MEISTER |
| Service/Power Release | 9/28/2023 | Approved | CALEB MEISTER |
| Smoke Detectors | 9/28/2023 | Approved | CALEB MEISTER |
| Verify Sprinkler Sign Off | 9/28/2023 | Approved | CALEB MEISTER |