1035 W 80TH ST 90044

Certificate Information: 1035 W 80TH ST 90044

Application / Permit
22010-10000-00731
Plan Check / Job No.
B22LA02692
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER STATE LAW GCS65852.2(e)(1)(B) WITH ATTACHED PATIO COVER
Permit Issued
Issued on 7/10/2023
Issuing Office
Current Status
CofO Issued on 9/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/28/2022 APPLICANT
Assigned to Plan Check Engineer 3/24/2022 VU NGUYEN
Corrections Issued 3/31/2022 VU NGUYEN
Quality Review Completed 4/1/2022 EUGENE BARBEAU
Plan Check Approved 8/15/2022 VU NGUYEN
Issued 7/10/2023 APPLICANT
CofO in Progress 8/1/2024 MICHAEL LEWIS
CofO Issued 9/3/2024 RUBEN SALAS
Permit Finaled 9/3/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/4/2022 CELINA MORENO
Sewer availability Cleared 4/4/2022 CELINA MORENO
Community Plan Implem. Overlay Cleared 4/20/2022 RAFAEL FONTES
Community Plan Implem. Overlay Cleared 4/21/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 6/7/2022 CELINA MORENO
Low Impact Development Cleared 8/5/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 8/10/2022 TREVOR QUAN

Contact Information

Contractor La Green Development Inc; Lic. No.: 1061369-B       ,
Contractor Socal Energy Power; Lic. No.: 1061369-B       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/18/2023 Approved MICHAEL LEWIS
Sewer 8/28/2023 Approved MICHAEL LEWIS
Underground Mechanical 8/28/2023 Approved MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 9/18/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 9/18/2023 Approved MICHAEL LEWIS
ELECTRICAL-Rough 11/6/2023 Approved MICHAEL LEWIS
HVAC-Rough 11/6/2023 Corrections Issued MICHAEL LEWIS
PLUMBING-Rough 11/6/2023 Approved MICHAEL LEWIS
Underground Mechanical 11/6/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 11/13/2023 Partial Approval CRAIG DAVIS
Green Building Rough 11/13/2023 Not Ready for Inspection CRAIG DAVIS
HVAC-Rough 11/13/2023 Not Ready for Inspection CRAIG DAVIS
Verify Sprinkler Sign Off 11/13/2023 Not Ready for Inspection CRAIG DAVIS
Interior/Exterior Lathing 11/20/2023 Approved MICHAEL LEWIS
Insulation 11/27/2023 Conditional Approval RONNIE MINDANAO
BUILDING-Rough-Frame 1/10/2024 Approved MICHAEL LEWIS
Green Building Rough 1/10/2024 Approved MICHAEL LEWIS
HVAC-Rough 1/10/2024 Approved MICHAEL LEWIS
Insulation 1/10/2024 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 1/10/2024 Approved MICHAEL LEWIS
Drywall Nailing 1/16/2024 Approved MICHAEL LEWIS
Interior/Exterior Lathing 1/16/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 2/23/2024 SGSOV Not Ready MICHAEL LEWIS
ELECTRICAL-Final 3/7/2024 Corrections Issued MICHAEL LEWIS
Final 3/7/2024 Corrections Issued MICHAEL LEWIS
Green Building Final 3/7/2024 Corrections Issued MICHAEL LEWIS
HVAC-Final 3/7/2024 Corrections Issued MICHAEL LEWIS
PLUMBING-Final 3/7/2024 Corrections Issued MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 3/7/2024 SGSOV Not Ready MICHAEL LEWIS
Service/Power Release 3/7/2024 Not Ready for Inspection MICHAEL LEWIS
Smoke Detectors 3/7/2024 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Final 3/19/2024 Corrections Issued MICHAEL LEWIS
PLUMBING-Final 3/19/2024 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Final 7/15/2024 Corrections Issued MICHAEL LEWIS
Final 7/15/2024 Corrections Issued MICHAEL LEWIS
Green Building Final 7/15/2024 Approved MICHAEL LEWIS
HVAC-Final 7/15/2024 Approved MICHAEL LEWIS
PLUMBING-Final 7/15/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 7/15/2024 SGSOV Not Ready MICHAEL LEWIS
Service/Power Release 7/15/2024 Not Ready for Inspection MICHAEL LEWIS
Smoke Detectors 7/15/2024 Approved MICHAEL LEWIS
ELECTRICAL-Final 7/24/2024 No Access for Inspection MICHAEL LEWIS
Final 7/24/2024 No Access for Inspection MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 7/24/2024 SGSOV Not Ready MICHAEL LEWIS
Service/Power Release 7/24/2024 No Access for Inspection MICHAEL LEWIS
ELECTRICAL-Final 7/29/2024 No Access for Inspection JOSE MACIAS
ELECTRICAL-Final 7/31/2024 Approved MICHAEL LEWIS
Final 7/31/2024 OK to Issue CofO MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 7/31/2024 SGSOV Approved MICHAEL LEWIS
Service/Power Release 7/31/2024 Approved MICHAEL LEWIS