3738 W 59TH ST 90043

Certificate Information: 3738 W 59TH ST 90043

Application / Permit
22010-10000-00719
Plan Check / Job No.
B22LA02668
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached ADU per LAMC 12.22 A.33(c) & (d). To comply with WFPP.
Permit Issued
Issued on 7/28/2022
Issuing Office
Metro
Current Status
CofO Issued on 5/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/15/2022 APPLICANT
Assigned to Plan Check Engineer 2/22/2022 TSE MING HUANG
Corrections Issued 7/11/2022 RICARDO RAMIREZ
Plan Check Approved 7/15/2022 RICARDO RAMIREZ
Issued 7/28/2022 APPLICANT
CofO in Progress 5/19/2023 ENRIQUE MIRELES
CofO in Progress 5/19/2023 ENRIQUE MIRELES
Permit Finaled 5/25/2023 DEROLD HAUFF
CofO Issued 5/25/2023 DEROLD HAUFF
Permit Finaled 5/25/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/5/2022 AMAAN MALIK
Low Impact Development Cleared 7/5/2022 CHRIS VONG
Eng Process Fee Ord 176,300 Cleared 7/13/2022 AMAAN MALIK
Roof/Waste drainage to street Cleared 7/13/2022 AMAAN MALIK
Sewer availability Cleared 7/13/2022 AMAAN MALIK

Contact Information

Contractor Goldweight Construction Inc; Lic. No.: 1077042-B 3236 W 113 ST      INGLEWOOD, CA 90303

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/16/2022 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 8/16/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 8/29/2022 Partial Approval ENRIQUE MIRELES
ELECTRICAL-Rough 9/27/2022 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 9/27/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 9/27/2022 Approved ENRIQUE MIRELES
Insulation 10/11/2022 Approved ENRIQUE MIRELES
Wood Frame 10/11/2022 Approved ENRIQUE MIRELES
Drywall Nailing 10/26/2022 Partial Approval RYAN SALAZAR
Green Building Rough 10/26/2022 Approved RYAN SALAZAR
HVAC-Rough 10/26/2022 Partial Approval RYAN SALAZAR
Interior/Exterior Lathing 10/26/2022 Partial Approval RYAN SALAZAR
Interior/Exterior Lathing 11/22/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 1/30/2023 Approved ENRIQUE MIRELES
Drywall Nailing 1/30/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Final 1/30/2023 Approved ENRIQUE MIRELES
Final 1/30/2023 Corrections Issued ENRIQUE MIRELES
Green Building Final 1/30/2023 Approved ENRIQUE MIRELES
HVAC-Final 1/30/2023 Approved ENRIQUE MIRELES
PLUMBING-Final 1/30/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 1/30/2023 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 1/30/2023 Approved ENRIQUE MIRELES
Smoke Detectors 1/30/2023 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 1/30/2023 Approved ENRIQUE MIRELES
Final 2/9/2023 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Final 3/29/2023 Approved ENRIQUE MIRELES
Final 3/29/2023 OK to Issue CofO ENRIQUE MIRELES
HVAC-Final 3/29/2023 Approved ENRIQUE MIRELES
PLUMBING-Final 3/29/2023 Approved ENRIQUE MIRELES
Service/Power Release 3/29/2023 Approved ENRIQUE MIRELES