3738 W 59TH ST 90043
Certificate Information: 3738 W 59TH ST 90043
- Application / Permit
- 22010-10000-00719
- Plan Check / Job No.
- B22LA02668
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached ADU per LAMC 12.22 A.33(c) & (d). To comply with WFPP.
- Permit Issued
- Issued on 7/28/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/22/2022 | TSE MING HUANG |
| Corrections Issued | 7/11/2022 | RICARDO RAMIREZ |
| Plan Check Approved | 7/15/2022 | RICARDO RAMIREZ |
| Issued | 7/28/2022 | APPLICANT |
| CofO in Progress | 5/19/2023 | ENRIQUE MIRELES |
| CofO in Progress | 5/19/2023 | ENRIQUE MIRELES |
| Permit Finaled | 5/25/2023 | DEROLD HAUFF |
| CofO Issued | 5/25/2023 | DEROLD HAUFF |
| Permit Finaled | 5/25/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/5/2022 | AMAAN MALIK |
| Low Impact Development | Cleared | 7/5/2022 | CHRIS VONG |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2022 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 7/13/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 7/13/2022 | AMAAN MALIK |
Contact Information
| Contractor | Goldweight Construction Inc; Lic. No.: 1077042-B | 3236 W 113 ST INGLEWOOD, CA 90303 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/16/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 8/16/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 8/29/2022 | Partial Approval | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 9/27/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 9/27/2022 | Approved | ENRIQUE MIRELES |
| Insulation | 10/11/2022 | Approved | ENRIQUE MIRELES |
| Wood Frame | 10/11/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 10/26/2022 | Partial Approval | RYAN SALAZAR |
| Green Building Rough | 10/26/2022 | Approved | RYAN SALAZAR |
| HVAC-Rough | 10/26/2022 | Partial Approval | RYAN SALAZAR |
| Interior/Exterior Lathing | 10/26/2022 | Partial Approval | RYAN SALAZAR |
| Interior/Exterior Lathing | 11/22/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 1/30/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 1/30/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 1/30/2023 | Approved | ENRIQUE MIRELES |
| Final | 1/30/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 1/30/2023 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 1/30/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 1/30/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 1/30/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 1/30/2023 | Approved | ENRIQUE MIRELES |
| Smoke Detectors | 1/30/2023 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 1/30/2023 | Approved | ENRIQUE MIRELES |
| Final | 2/9/2023 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Final | 3/29/2023 | Approved | ENRIQUE MIRELES |
| Final | 3/29/2023 | OK to Issue CofO | ENRIQUE MIRELES |
| HVAC-Final | 3/29/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 3/29/2023 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 3/29/2023 | Approved | ENRIQUE MIRELES |