3320 N LUGANO PL 90068

Certificate Information: 3320 N LUGANO PL 90068

Application / Permit
22010-10000-00684
Plan Check / Job No.
B22LA02514
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFR
Permit Issued
Issued on 5/2/2024
Issuing Office
Metro
Current Status
CofO Issued on 4/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/15/2022 APPLICANT
Assigned to Plan Check Engineer 3/10/2022 HERNAN ARREOLA
Corrections Issued 3/25/2022 HERNAN ARREOLA
Quality Review Completed 3/29/2022 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 1/17/2023 HERNAN ARREOLA
Issued 5/2/2024 APPLICANT
CofO in Progress 4/13/2026 CRAIG VAUGHAN
Permit Finaled 4/13/2026 DEROLD HAUFF
CofO Issued 4/13/2026 DEROLD HAUFF
Permit Finaled 4/13/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/1/2022 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 8/1/2022 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 8/1/2022 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 8/1/2022 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 8/1/2022 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 8/1/2022 LEE GUILBEAUX
Miscellaneous Cleared 8/1/2022 LEE GUILBEAUX
Work Adjacent to Public Way Cleared 8/1/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/2/2022 LEE GUILBEAUX
Permit Cleared 8/2/2022 LEE GUILBEAUX
Sewer availability Cleared 8/2/2022 LEE GUILBEAUX
Hydrant and Access approval Cleared 9/18/2022 JOHN CONNEALLY
Low Impact Development Cleared 10/17/2022 LUIS LUVANO
Roof/Waste drainage to street Cleared 10/20/2022 CELINA MORENO
Specific Plan Cleared 12/6/2022 JAZMIN ROQUE
Miscellaneous Cleared 12/7/2022 JAZMIN ROQUE
GPI Written Notices Cleared 1/17/2023 HERNAN ARREOLA
Grading Pre-Inspection Cleared 1/17/2023 HERNAN ARREOLA
Excavation more than 5-ft deep Cleared 3/22/2024 CALOSHA APPROVED

Contact Information

Contractor Owner-Builder       ,
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107
Engineer Lee,, Sang Youck; Lic. No.: S3821 3531 BROOKHILL ST      GLENDALE, CA 91214

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/6/2024 Partial Inspection ROY SPAULDING
Footing/Foundation/Slab 5/29/2024 Partial Approval ROY SPAULDING
PLUMBING-Rough 5/29/2024 Partial Approval ROY SPAULDING
Deputy Reinf. Concrete 5/30/2024 Conditional Approval ROY SPAULDING
Excavation/Setback/Form/Re-Bar 6/12/2024 Partial Approval ROY SPAULDING
Footing/Foundation/Slab 6/12/2024 Partial Approval ROY SPAULDING
Deputy Reinf. Concrete 6/14/2024 Conditional Approval ROY SPAULDING
Deputy Shotcrete 6/14/2024 Conditional Approval ROY SPAULDING
Deputy Reinf. Concrete 7/10/2024 Conditional Approval ROY SPAULDING
Excavation/Setback/Form/Re-Bar 7/11/2024 Not Ready for Inspection ROY SPAULDING
Piling/Pier/Caisson 7/11/2024 Not Ready for Inspection ROY SPAULDING
Deputy Reinf. Concrete 7/16/2024 Conditional Approval ROY SPAULDING
Deputy Reinf. Concrete 8/1/2024 Approved BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 8/1/2024 Partial Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 8/5/2024 Conditional Approval ROY SPAULDING
Deputy Other (see comments) 8/19/2024 Conditional Approval ROY SPAULDING
Excavation/Setback/Form/Re-Bar 8/20/2024 Approved ROY SPAULDING
Piling/Pier/Caisson 8/20/2024 Approved ROY SPAULDING
Deputy Drilled-In Anchors 8/22/2024 Conditional Approval ROY SPAULDING
Excavation/Setback/Form/Re-Bar 9/4/2024 Partial Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 9/5/2024 Conditional Approval BRIAN SULLIVAN
Deputy Shotcrete 9/5/2024 Conditional Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 9/20/2024 Approved CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 9/20/2024 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 9/20/2024 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 9/25/2024 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 10/9/2024 Partial Approval BRENDAN MORELLI
ELECTRICAL-Rough 10/16/2024 Partial Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 10/16/2024 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 10/16/2024 Partial Approval CRAIG VAUGHAN
Deputy Steel/Welding 12/11/2024 Conditional Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 12/19/2024 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 12/19/2024 Partial Approval CRAIG VAUGHAN
Green Building Rough 12/19/2024 Not Ready for Inspection CRAIG VAUGHAN
Structural Steel Frame 12/19/2024 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 12/19/2024 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 1/22/2025 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 2/5/2025 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 2/7/2025 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 2/10/2025 Partial Approval CRAIG VAUGHAN
Deputy Wood Construction 3/3/2025 Conditional Approval CRAIG VAUGHAN
PLUMBING-Rough 3/14/2025 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 3/17/2025 Not Ready for Inspection CRAIG VAUGHAN
Wood Frame 3/17/2025 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 3/18/2025 Corrections Issued CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 4/1/2025 Partial Approval CRAIG VAUGHAN
Wood Frame 4/1/2025 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 4/25/2025 Corrections Issued CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 4/25/2025 Partial Approval CRAIG VAUGHAN
HVAC-Rough 4/30/2025 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 5/12/2025 Approved CRAIG VAUGHAN
Green Building Rough 5/12/2025 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 5/12/2025 Approved CRAIG VAUGHAN
Insulation 5/28/2025 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 5/28/2025 Partial Approval CRAIG VAUGHAN
Drywall Nailing 6/9/2025 Approved CRAIG VAUGHAN
Underground Mechanical 8/11/2025 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 8/19/2025 Approved JOSH MEISTER
Sewer 8/25/2025 Approved CRAIG VAUGHAN
PLUMBING-Rough 9/8/2025 Approved CRAIG VAUGHAN
Underground Mechanical 9/8/2025 Partial Approval CRAIG VAUGHAN
PLUMBING-Final 10/1/2025 Approved CRAIG VAUGHAN
ELECTRICAL-Final 10/28/2025 Corrections Issued CRAIG VAUGHAN
Service/Power Release 12/11/2025 Approved CRAIG VAUGHAN
Service/Power Release 12/17/2025 Approved CRAIG VAUGHAN
HVAC-Final 3/10/2026 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Final 4/1/2026 Approved CRAIG VAUGHAN
Final 4/1/2026 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 4/1/2026 Approved CRAIG VAUGHAN
Green Building Final 4/1/2026 Approved CRAIG VAUGHAN
HVAC-Final 4/1/2026 Approved CRAIG VAUGHAN
Reinforced Masonry Frame 4/1/2026 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 4/1/2026 SGSOV Not Required CRAIG VAUGHAN
Smoke Detectors 4/1/2026 Approved CRAIG VAUGHAN
Structural Steel Frame 4/1/2026 Approved CRAIG VAUGHAN
ELECTRICAL-Final 4/6/2026 Approved CRAIG VAUGHAN
Final 4/6/2026 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 4/6/2026 Approved CRAIG VAUGHAN