9033 N LEDGE AVE 91352

Certificate Information: 9033 N LEDGE AVE 91352

Application / Permit
22010-10000-00680
Plan Check / Job No.
B22LA02488
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER ORDINANCE. The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
Permit Issued
Issued on 6/21/2023
Issuing Office
Metro
Current Status
CofO Issued on 8/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/14/2022 APPLICANT
Assigned to Plan Check Engineer 2/18/2022 FARSHAD ALIMOHAMADI
Corrections Issued 2/21/2022 FARSHAD ALIMOHAMADI
Building Plans Picked Up 2/24/2022 APPLICANT
Applicant returned to address corrections 5/9/2023 KHUONG TRUONG
Plan Check Approved 6/21/2023 GEORGE ALVAREZ
Issued 6/21/2023 APPLICANT
CofO in Progress 7/10/2024 DAVID ANDERSON
Permit Finaled 8/12/2024 DANIEL ORRANTE
CofO Issued 8/12/2024 DANIEL ORRANTE
Permit Finaled 8/12/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/9/2022 JOSE DUARTE-DIAZ
Grading Pre-Inspection Cleared 3/16/2022 BRIAN MILLER
Miscellaneous Cleared 3/18/2022 NELSON RODRIGUEZ
Specific Plan Cleared 3/28/2022 SARAH HOUNSELL
Eng Process Fee Ord 176,300 Cleared 3/29/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 4/21/2022 ROSE MARIE SMITH
Hydrant and Access approval Cleared 4/25/2022 DWIGHT SANKEY
GPI Written Notices Cleared 5/9/2023 FARSHAD ALIMOHAMADI
Roof/Waste drainage to street Cleared 5/10/2023 CARLOS AGUILERA
Hold Cleared 7/31/2023 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/2/2023 Partial Inspection THOMAS FINNILA
Footing/Foundation/Slab 8/9/2023 Not Ready for Inspection DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 8/16/2023 Not Ready for Inspection DAVID ANDERSON
Footing/Foundation/Slab 8/16/2023 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Rough 8/16/2023 Partial Approval DAVID ANDERSON
Footing/Foundation/Slab 8/22/2023 Not Ready for Inspection DAVID ANDERSON
Footing/Foundation/Slab 8/24/2023 Approved DAVID ANDERSON
BUILDING-Rough-Frame 10/17/2023 Not Ready for Inspection DAVID ANDERSON
ELECTRICAL-Rough 10/17/2023 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 10/17/2023 Approved DAVID ANDERSON
Green Building Rough 10/17/2023 Approved DAVID ANDERSON
HVAC-Rough 10/17/2023 Corrections Issued DAVID ANDERSON
PLUMBING-Rough 10/17/2023 Corrections Issued DAVID ANDERSON
Verify Sprinkler Sign Off 10/17/2023 Approved DAVID ANDERSON
BUILDING-Rough-Frame 10/26/2023 Approved DAVID ANDERSON
HVAC-Rough 10/26/2023 Approved DAVID ANDERSON
PLUMBING-Rough 10/26/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 11/14/2023 Approved DAVID ANDERSON
Insulation 11/21/2023 Approved DAVID ANDERSON
Drywall Nailing 11/27/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 12/11/2023 Approved DAVID ANDERSON
Shower Pan 12/11/2023 Approved DAVID ANDERSON
Underground Mechanical 2/20/2024 Partial Approval DAVID ANDERSON
Service/Power Release 2/29/2024 Not Ready for Inspection DAVID ANDERSON
Underground Mechanical 2/29/2024 Approved DAVID ANDERSON
Final 4/9/2024 Corrections Issued DAVID ANDERSON
Green Building Final 4/9/2024 Not Ready for Inspection DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 4/9/2024 SGSOV Not Ready DAVID ANDERSON
Service/Power Release 4/9/2024 Not Ready for Inspection DAVID ANDERSON
Smoke Detectors 4/9/2024 Approved DAVID ANDERSON
Green Building Final 4/16/2024 Approved SALVADOR MARTINEZ
Grounding or Bonding 4/16/2024 Approved SALVADOR MARTINEZ
Final 4/22/2024 Not Ready for Inspection DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 4/22/2024 SGSOV Approved DAVID ANDERSON
Service/Power Release 4/22/2024 Not Ready for Inspection DAVID ANDERSON
Final 5/1/2024 Not Ready for Inspection DAVID ANDERSON
Service/Power Release 5/1/2024 Not Ready for Inspection DAVID ANDERSON
Final 7/9/2024 OK to Issue CofO DAVID ANDERSON
Service/Power Release 7/9/2024 Approved DAVID ANDERSON