8851 S KITTYHAWK AVE 90045
Certificate Information: 8851 S KITTYHAWK AVE 90045
- Application / Permit
- 22010-10000-00675
- Plan Check / Job No.
- B22LA02458
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSORY DWELLING UNIT 560 SF IN THE REAR OF EXISTING HOUSES PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c)(d)(g) ALL WORK PER WFPP
- Permit Issued
- Issued on 8/25/2022
- Issuing Office
- Current Status
- CofO Issued on 5/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2022 | KHUONG TRUONG |
| Corrections Issued | 4/14/2022 | KHUONG TRUONG |
| Building Plans Picked Up | 4/18/2022 | APPLICANT |
| Applicant returned to address corrections | 5/2/2022 | FERNANDO FLORES |
| Applicant returned to address corrections | 8/18/2022 | AUNG SOE |
| Plan Check Approved | 8/25/2022 | DANIEL SANJUAN |
| Issued | 8/25/2022 | APPLICANT |
| CofO in Progress | 5/4/2023 | JESUS RODRIGUEZ |
| Permit Finaled | 5/5/2023 | DANIEL ORRANTE |
| CofO Issued | 5/5/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/5/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/2/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2022 | CINDY QI |
| Sewer availability | Cleared | 5/2/2022 | CINDY QI |
| ZA Case | Cleared | 5/2/2022 | RICHARD REASER |
| Specific Plan | Cleared | 6/3/2022 | EDUARDO HERMOSO |
| Low Impact Development | Cleared | 8/12/2022 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 8/12/2022 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/30/2022 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 9/6/2022 | Conditional Approval | BOBBY KEY |
| PLUMBING-Rough | 9/6/2022 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 9/12/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 10/12/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2022 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 10/17/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 10/17/2022 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 10/19/2022 | Approved | BOBBY KEY |
| Green Building Rough | 10/19/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 10/19/2022 | Partial Approval | BOBBY KEY |
| MERV13>=Rough | 10/19/2022 | Approved | BOBBY KEY |
| PLUMBING-Rough | 10/19/2022 | Approved | BOBBY KEY |
| Verify Sprinkler Sign Off | 10/19/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 10/21/2022 | Approved | BOBBY KEY |
| Insulation | 10/21/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 10/27/2022 | Approved | BOBBY KEY |
| Final | 10/27/2022 | Corrections Issued | BOBBY KEY |
| Special/Order Compliance | 11/23/2022 | Partial Inspection | BOBBY KEY |
| Underground Mechanical | 11/23/2022 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Final | 2/16/2023 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 2/16/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 2/16/2023 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Final | 3/3/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Final | 3/3/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Green Building Final | 3/3/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 3/3/2023 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Service/Power Release | 3/3/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Smoke Detectors | 3/3/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 4/3/2023 | Corrections Issued | BOBBY KEY |
| Final | 4/3/2023 | Corrections Issued | BOBBY KEY |
| Green Building Final | 4/3/2023 | Approved | BOBBY KEY |
| HVAC-Final | 4/3/2023 | Approved | BOBBY KEY |
| PLUMBING-Final | 4/3/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 4/3/2023 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 4/3/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 5/3/2023 | Approved | JESUS RODRIGUEZ |
| Final | 5/3/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Service/Power Release | 5/3/2023 | Approved | JESUS RODRIGUEZ |