1519 W RUTGERS PL 90710

Certificate Information: 1519 W RUTGERS PL 90710

Application / Permit
22010-10000-00662
Plan Check / Job No.
B22LA02427
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER ORDINANCE. WFPP (1-STORY)
Permit Issued
Issued on 10/17/2022
Issuing Office
Current Status
CofO Issued on 8/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2022 APPLICANT
Assigned to Plan Check Engineer 3/3/2022 CARLOS MONTES
Corrections Issued 3/4/2022 CARLOS MONTES
Applicant returned to address corrections 8/2/2022 DANIEL YIP
Plan Check Approved 8/7/2022 DANIEL YIP
Issued 10/17/2022 APPLICANT
CofO in Progress 8/28/2023 EUGENE CASSIDY
Permit Finaled 8/29/2023 ANSON MAGLASANG
CofO Issued 8/29/2023 ANSON MAGLASANG
Permit Finaled 8/29/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 3/8/2022 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 3/9/2022 JOSE HERNANDEZ
Sewer availability Cleared 3/16/2022 JOSE HERNANDEZ
Low Impact Development Cleared 7/22/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 7/27/2022 JOSE HERNANDEZ

Contact Information

Contractor Next Generation Builders; Lic. No.: 1069728-B       ,
Contractor Polymath Development Group Inc; Lic. No.: 1069728-B       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/25/2022 Approved JOHN KLARIN
METHANE-Subgrade 12/20/2022 Partial Approval EUGENE CASSIDY
Underground Mechanical 12/20/2022 Corrections Issued EUGENE CASSIDY
Underground Mechanical 12/21/2022 Approved EUGENE CASSIDY
ELECTRICAL-Final 7/12/2023 Corrections Issued EUGENE CASSIDY
Gas Test 7/12/2023 Approved EUGENE CASSIDY
HVAC-Final 7/12/2023 Approved EUGENE CASSIDY
PLUMBING-Final 7/12/2023 Approved EUGENE CASSIDY
Service/Power Release 7/12/2023 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 7/31/2023 Corrections Issued EUGENE CASSIDY
HVAC-Final 7/31/2023 Approved EUGENE CASSIDY
PLUMBING-Final 7/31/2023 Approved EUGENE CASSIDY
Service/Power Release 7/31/2023 Not Ready for Inspection EUGENE CASSIDY
Drywall Nailing 8/3/2023 Approved EUGENE CASSIDY
ELECTRICAL-Final 8/3/2023 Approved EUGENE CASSIDY
Final 8/3/2023 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 8/3/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 8/25/2023 Approved EUGENE CASSIDY
Final 8/25/2023 OK to Issue CofO EUGENE CASSIDY
Footing/Foundation/Slab 8/25/2023 Approved EUGENE CASSIDY
Green Building Final 8/25/2023 Approved EUGENE CASSIDY
METHANE-Barrier 8/25/2023 Approved EUGENE CASSIDY
METHANE-Final 8/25/2023 Approved EUGENE CASSIDY
METHANE-Subgrade 8/25/2023 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 8/25/2023 SGSOV Approved EUGENE CASSIDY
Service/Power Release 8/25/2023 Approved EUGENE CASSIDY
Smoke Detectors 8/25/2023 Approved EUGENE CASSIDY