1711 E 15TH ST 90021
Certificate Information: 1711 E 15TH ST 90021
- Application / Permit
- 22010-10000-00640
- Plan Check / Job No.
- B22LA02338
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (22) Storage Building for Household Goods
- Work Description
- NEW 4 STORY TYPE IIB SELF STORAGE FACILITY OVER 1 LEVEL TYPE IA BASEMENT. AB 2097 ZERO PARKING REQUIRED.
- Permit Issued
- Issued on 8/19/2025
- Issuing Office
- South Los Angeles
- Current Status
- Issued on 8/19/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | SERGIO GUTIERREZ |
| Corrections Issued | 4/1/2022 | SERGIO GUTIERREZ |
| Quality Review Completed | 4/5/2022 | FARUK SEZER |
| Building Plans Picked Up | 4/7/2022 | APPLICANT |
| Applicant returned to address corrections | 5/12/2022 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 9/8/2023 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 7/17/2024 | SERGIO GUTIERREZ |
| Plan Check Approved | 12/6/2024 | SERGIO GUTIERREZ |
| Issued | 8/19/2025 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 7/12/2022 | KURT CORRAL |
| Historic Resource Verification | Cleared | 3/22/2023 | MAX LODER |
| CPC | Cleared | 4/4/2023 | YINGSHI HUANG |
| Frnt yard landscape/Water mgmt | Cleared | 4/4/2023 | YINGSHI HUANG |
| Miscellaneous | Cleared | 4/4/2023 | YINGSHI HUANG |
| Miscellaneous | Cleared | 4/4/2023 | YINGSHI HUANG |
| Permit | Cleared | 5/12/2023 | JEREMY CHOK |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2023 | JEREMY CHOK |
| Sewer availability | Cleared | 5/20/2023 | JEREMY CHOK |
| Trees in Parkway | Cleared | 7/17/2023 | ADALBERTO VERA |
| Building over 36-ft | Cleared | 8/15/2023 | CALOSHA APPROVED |
| Bicycle Parking | Cleared | 8/23/2023 | COLLINS ALLAN |
| Driveway location | Cleared | 8/23/2023 | COLLINS ALLAN |
| Driveway location | Cleared | 8/23/2023 | COLLINS ALLAN |
| Internal circulation | Cleared | 8/23/2023 | COLLINS ALLAN |
| Transportation Demand Ord. | Cleared | 8/23/2023 | COLLINS ALLAN |
| Stormwater Pollution Mitigatn | Cleared | 12/15/2023 | JORGE MEJIA LEMUS |
| Work Adjacent to Public Way | Cleared | 1/12/2024 | JOSE RODRIGUEZ |
| Roof/Waste drainage to street | Cleared | 1/16/2024 | JEANIE LAM |
| ZA Case | Cleared | 1/18/2024 | RYAN LY |
| Redevelopment Project Area | Cleared | 2/1/2024 | ELIZABETH GALLARDO |
| Construction near power lines | Cleared | 2/14/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 2/14/2024 | RIDWAN HARDY |
| Miscellaneous | Cleared | 7/12/2024 | DANIEL CORONADO |
| Prkng lot landscape/Water mgmt | Cleared | 7/12/2024 | DANIEL CORONADO |
| Site Plan review | Cleared | 7/12/2024 | DANIEL CORONADO |
| ZA Case | Cleared | 7/12/2024 | DANIEL CORONADO |
| Low Impact Development | Cleared | 7/14/2024 | MARTIN FRAGOSO |
| DAS Clearance | Cleared | 7/28/2024 | ELIZABETH TOMS |
| Green Code | Cleared | 8/27/2024 | AARON COSTA |
| Highway dedication | Cleared | 10/8/2024 | WALLIE JONG |
Contact Information
| Contractor | P B Brown Llc; Lic. No.: 989446-B | 428 S DILLARD STREET WINTER GARDEN, FL 34787 |
| Engineer | Cullumber,, Wesley Steven; Lic. No.: C80675 | 6930 DESTINY DRIVE SUITE 300 ROCKLIN, CA 95677 |
| Engineer | Kim,, Carl C; Lic. No.: GE2620 | 945 BAILEYANA ROAD HILLSBOROUGH, CA 94010 |
| Engineer | Salter,, David R; Lic. No.: C69911 | 3445 CEDAR ST SANTA YNEZ, CA 93460 |
| Geologist | Hillstrand,, Andrew Robert; Lic. No.: EG2366 | 553 S VENTU PARK RD NEWBURY PARK, CA 91320 |
Inspector Information
| NICK DANERI, (213) 202-5615 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/14/2026 | Approved | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 3/11/2026 | Not Ready for Inspection | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 3/23/2026 | Partial Approval | JOEY BUCHANAN |
| Footing/Foundation/Slab | 3/23/2026 | Partial Approval | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 4/1/2026 | Not Ready for Inspection | JOEY BUCHANAN |
| Footing/Foundation/Slab | 4/1/2026 | Not Ready for Inspection | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 4/2/2026 | Not Ready for Inspection | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 4/3/2026 | Conditional Approval | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 4/3/2026 | Partial Approval | JOEY BUCHANAN |
| Footing/Foundation/Slab | 4/3/2026 | Partial Approval | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 4/6/2026 | Partial Approval | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 4/8/2026 | Not Ready for Inspection | JOEY BUCHANAN |
| Footing/Foundation/Slab | 4/8/2026 | Not Ready for Inspection | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 4/9/2026 | Partial Approval | JOEY BUCHANAN |
| Masonry Wall/Backfill | 4/14/2026 | Partial Approval | JOEY BUCHANAN |
| Deputy Shotcrete | 4/17/2026 | No Result Entered | NICK DANERI |
| Masonry Wall/Backfill | 4/17/2026 | Partial Approval | JOEY BUCHANAN |
| Deputy Shotcrete | 4/21/2026 | No Result Entered | NICK DANERI |
| Deputy Shotcrete | 4/22/2026 | No Result Entered | NICK DANERI |
| Excavation/Setback/Form/Re-Bar | 4/22/2026 | Partial Approval | JOEY BUCHANAN |
| Masonry Wall/Backfill | 4/22/2026 | Not Ready for Inspection | JOEY BUCHANAN |
| Deputy Shotcrete | 4/23/2026 | No Result Entered | NICK DANERI |
| Deputy Reinf. Concrete | 4/24/2026 | No Result Entered | NICK DANERI |
| Excavation/Setback/Form/Re-Bar | 4/24/2026 | Not Ready for Inspection | JOEY BUCHANAN |
| Deputy Shotcrete | 4/27/2026 | No Result Entered | NICK DANERI |
| Excavation/Setback/Form/Re-Bar | 4/27/2026 | Partial Approval | JOEY BUCHANAN |
| Deputy Shotcrete | 4/28/2026 | No Result Entered | NICK DANERI |
| Masonry Wall/Backfill | 4/28/2026 | Partial Approval | ALFREDO LOPEZ |
| Deputy Shotcrete | 5/1/2026 | No Result Entered | NICK DANERI |
| Deputy Shotcrete | 5/4/2026 | No Result Entered | NICK DANERI |
| Reinforced Masonry Frame | 5/7/2026 | Partial Approval | JAMES POWERS |
| Masonry Wall/Backfill | 5/14/2026 | Partial Approval | ALFREDO LOPEZ |
| Deputy Drilled-In Anchors | 5/15/2026 | Conditional Approval | RONALD JIMENEZ |
| Deputy Drilled-In Anchors | 5/18/2026 | No Result Entered | NICK DANERI |
| Deputy Drilled-In Anchors | 5/21/2026 | No Result Entered | NICK DANERI |
| Deputy Drilled-In Anchors | 5/22/2026 | No Result Entered | NICK DANERI |
| Light Gage Steel Frame | 5/27/2026 | Not Ready for Inspection | JOEY BUCHANAN |
| Structural Steel Frame | 5/27/2026 | Partial Approval | JOEY BUCHANAN |
| Deputy Steel/Welding | 5/28/2026 | No Result Entered | NICK DANERI |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2026 | Not Ready for Inspection | JOEY BUCHANAN |
| Light Gage Steel Frame | 6/3/2026 | Partial Approval | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 6/4/2026 | Partial Approval | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2026 | Partial Approval | JOEY BUCHANAN |
| Light Gage Steel Frame | 6/4/2026 | Not Ready for Inspection | JOEY BUCHANAN |