2811 E OREGON ST 90023
Certificate Information: 2811 E OREGON ST 90023
- Application / Permit
- 22010-10000-00565
- Plan Check / Job No.
- B22LA02130
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2 STORY SFD WITH 3 CAR GARAGE ON FIRST FLOOR. CUGU-PUBLICLY HABITABLE SPACE
- Permit Issued
- Issued on 10/24/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 3/17/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 3/25/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 4/22/2022 | MAHNAZ NOURHASHEMI |
| Building Plans Picked Up | 8/11/2022 | APPLICANT |
| Applicant returned to address corrections | 9/14/2022 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 10/20/2022 | MAHNAZ NOURHASHEMI |
| Issued | 10/24/2022 | APPLICANT |
| CofO in Progress | 3/4/2025 | FREDDIE RIVERA |
| Permit Finaled | 3/9/2025 | DEROLD HAUFF |
| CofO Issued | 3/9/2025 | DEROLD HAUFF |
| Permit Finaled | 3/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 4/27/2022 | MAYELA VILLA |
| Hydrant and Access approval | Cleared | 5/13/2022 | KURT CORRAL |
| Address approval | Cleared | 7/13/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2022 | CINDY QI |
| Sewer availability | Cleared | 7/18/2022 | CINDY QI |
| Low Impact Development | Cleared | 8/10/2022 | ROGELIO CORTES |
| GPI Written Notices | Cleared | 9/14/2022 | MAHNAZ NOURHASHEMI |
| Grading Pre-Inspection | Cleared | 9/14/2022 | MAHNAZ NOURHASHEMI |
| Roof/Waste drainage to street | Cleared | 10/6/2022 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Li,, Dacheng David; Lic. No.: C58075 | 1400 N KRAEMER BLVD #712 PLACENTIA, CA 92781 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/29/2022 | Partial Approval | RUBEN SALAS |
| Footing/Foundation/Slab | 1/25/2023 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 2/2/2023 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 2/27/2023 | Partial Inspection | FREDDIE RIVERA |
| Green Building Rough | 2/27/2023 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2023 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2023 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 3/28/2023 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Rough | 3/28/2023 | Approved | STUART CHAPMAN |
| Final | 3/28/2023 | Corrections Issued | STUART CHAPMAN |
| HVAC-Rough | 3/28/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 3/28/2023 | Corrections Issued | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 3/28/2023 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 4/7/2023 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 4/7/2023 | Partial Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 4/7/2023 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 6/22/2023 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 6/22/2023 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 6/22/2023 | Approved | FREDDIE RIVERA |
| Insulation | 6/29/2023 | Corrections Issued | FREDDIE RIVERA |
| Insulation | 7/6/2023 | No Access for Inspection | BRENDAN MORELLI |
| Insulation | 7/11/2023 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 8/3/2023 | Corrections Issued | FREDDIE RIVERA |
| Interior/Exterior Lathing | 8/3/2023 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 9/18/2023 | Partial Inspection | FREDDIE RIVERA |
| Drywall Nailing | 10/2/2023 | Approved | JEFFREY MEAD |
| Final | 10/31/2023 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 10/31/2023 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Final | 10/31/2023 | Corrections Issued | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 10/31/2023 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 10/31/2023 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 10/31/2023 | Approved | FREDDIE RIVERA |
| Final | 11/8/2024 | Partial Inspection | FREDDIE RIVERA |
| Green Building Final | 11/8/2024 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 11/8/2024 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 11/8/2024 | Partial Inspection | FREDDIE RIVERA |
| Final | 2/26/2025 | Partial Inspection | FREDDIE RIVERA |
| Green Building Final | 2/26/2025 | Partial Inspection | FREDDIE RIVERA |
| Service/Power Release | 2/26/2025 | Partial Inspection | FREDDIE RIVERA |
| Final | 2/28/2025 | OK to Issue CofO | FREDDIE RIVERA |
| Green Building Final | 2/28/2025 | Approved | FREDDIE RIVERA |
| Service/Power Release | 2/28/2025 | Approved | FREDDIE RIVERA |
| Special/Order Compliance | 3/4/2025 | Corrections Issued | FREDDIE RIVERA |