12495 W PROMONTORY ROAD 90049
Certificate Information: 12495 W PROMONTORY ROAD 90049
- Application / Permit
- 22010-10000-00562
- Plan Check / Job No.
- B22LA02106
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW PATIO COVER FOR OUTDOOR KITCHEN/ BBQ AREA. 1 OF 3
- Permit Issued
- Issued on 8/25/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/22/2022 | CARLOS MONTES |
| Corrections Issued | 3/1/2022 | CARLOS MONTES |
| Quality Review Completed | 3/2/2022 | KEN GILL |
| Building Plans Picked Up | 3/4/2022 | APPLICANT |
| Applicant returned to address corrections | 4/27/2023 | CARLOS MONTES |
| Plan Check Approved | 6/30/2023 | CARLOS MONTES |
| Issued | 8/25/2023 | APPLICANT |
| CofO in Progress | 10/31/2024 | KEVIN SARGSYAN |
| Permit Finaled | 11/12/2024 | RICHARD STEINBACH |
| CofO Issued | 11/12/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/12/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| "Q" conditions | Cleared | 11/18/2022 | DALIA MOKAYED |
| Frnt yard landscape/Water mgmt | Cleared | 11/18/2022 | DALIA MOKAYED |
| Private street | Cleared | 11/18/2022 | DALIA MOKAYED |
| ZA Case | Cleared | 11/18/2022 | DALIA MOKAYED |
| ZA Case | Cleared | 11/18/2022 | DALIA MOKAYED |
| ZI | Cleared | 11/18/2022 | DALIA MOKAYED |
| BHO/Hillside ordinance | Cleared | 11/21/2022 | SAUL GARCIA |
| BHO/Hillside ordinance | Cleared | 11/21/2022 | SAUL GARCIA |
| BHO/Hillside ordinance | Cleared | 11/21/2022 | SAUL GARCIA |
| BHO/Hillside ordinance | Cleared | 11/21/2022 | SAUL GARCIA |
| BHO/Hillside ordinance | Cleared | 11/21/2022 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2022 | SAUL GARCIA |
| Highway dedication | Cleared | 11/28/2022 | JASON NG |
| Roof/Waste drainage to street | Cleared | 1/25/2023 | SAUL GARCIA |
| GPI Written Notices | Cleared | 1/26/2023 | CARLOS MONTES |
| Grading Pre-Inspection | Cleared | 1/26/2023 | CARLOS MONTES |
Contact Information
| Contractor | No Cap Construction Inc; Lic. No.: 1085630-B | 12814 VICTORY BLVD #184 NORTH HOLLYWOOD, CA 91606 |
| Engineer | Rybak,, Richard; Lic. No.: GE2131 | 20312 TAU PLACE CHATSWORTH, CA 91311 |
| Geologist | Haenschke,, Eirik Francis; Lic. No.: EG1597 | 9616 GIERSON AVE CHATSWORTH, CA 91311 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/16/2023 | Partial Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 4/19/2024 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 4/26/2024 | Partial Approval | KEVIN SARGSYAN |
| Deputy Shotcrete | 5/13/2024 | Conditional Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 5/17/2024 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 7/16/2024 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 7/16/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 7/26/2024 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/26/2024 | Approved | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 7/26/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 9/6/2024 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2024 | Approved | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 9/6/2024 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 9/13/2024 | Approved | KEVIN SARGSYAN |
| Final | 10/9/2024 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 10/9/2024 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 10/9/2024 | SGSOV Approved | KEVIN SARGSYAN |
| Structural Steel Frame | 10/9/2024 | Approved | KEVIN SARGSYAN |
| Final | 10/16/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Final | 10/30/2024 | OK to Issue CofO | KEVIN SARGSYAN |