1919 N SEIGNEUR AVE 90032

Certificate Information: 1919 N SEIGNEUR AVE 90032

Application / Permit
22010-10000-00560
Plan Check / Job No.
B22LA02094
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 2 story single family dwelling with attached 2-car garage on a hillside lot with slope greater than 33-1/3 percent.
Permit Issued
Issued on 2/26/2024
Issuing Office
Metro
Current Status
CofO Issued on 10/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/7/2022 APPLICANT
Assigned to Plan Check Engineer 3/3/2022 KESETE HAREGOT
Corrections Issued 3/5/2022 KESETE HAREGOT
Quality Review Completed 3/8/2022 FARUK SEZER
Building Plans Picked Up 3/10/2022 APPLICANT
Applicant returned to address corrections 10/12/2023 KESETE HAREGOT
Applicant returned to address corrections 12/7/2023 KESETE HAREGOT
Plan Check Approved 1/23/2024 KESETE HAREGOT
Issued 2/26/2024 APPLICANT
CofO in Progress 10/27/2025 LILIANA PORTILLO
Permit Finaled 10/27/2025 DEROLD HAUFF
CofO Issued 10/27/2025 DEROLD HAUFF
Permit Finaled 10/27/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/31/2022 JEANIE LAM
BHO/Hillside ordinance Cleared 3/31/2022 JEANIE LAM
BHO/Hillside ordinance Cleared 3/31/2022 JEANIE LAM
BHO/Hillside ordinance Cleared 3/31/2022 JEANIE LAM
BHO/Hillside ordinance Cleared 3/31/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 4/3/2022 JEANIE LAM
Sewer availability Cleared 4/3/2022 JEANIE LAM
Miscellaneous Cleared 4/14/2022 ALBERT TAM
Permit Cleared 4/19/2022 JEANIE LAM
BHO/Hillside ordinance Cleared 4/22/2022 THAN WIN
Trees in Parkway Cleared 5/4/2022 ADALBERTO VERA
Disturb/Remove Protected Trees Cleared 5/26/2022 ADALBERTO VERA
Hydrant and Access approval Cleared 7/5/2022 RUEL COLE
"D" conditions Cleared 8/17/2022 SPENCER WEJROWSKI
"Q" conditions Cleared 8/17/2022 SPENCER WEJROWSKI
Low Impact Development Cleared 11/10/2022 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 11/14/2022 JEANIE LAM
Work Adjacent to Public Way Cleared 7/6/2023 JOSE RODRIGUEZ
GPI Written Notices Cleared 10/12/2023 KESETE HAREGOT
Grading Pre-Inspection Cleared 10/12/2023 KESETE HAREGOT
Green Code Cleared 10/12/2023 KESETE HAREGOT

Contact Information

Architect Kivotos,, Juan M; Lic. No.: C26491 1323 N NIAGARA STREET      BURBANK, CA 91505
Contractor Ramtin & Associates Llc; Lic. No.: 1102854-B 13900 MARQUESAS WAY   APT-5104    MARINA DEL REY, CA 90292
Engineer Mirfakhraie,, Ramtin; Lic. No.: C80437 32679 SEAGATE DR 203      RANCHO PALOS VERDES, CA 90275
Engineer Price,, Mark Erin; Lic. No.: L7764 18700 WELLHAVEN STREET      CANYON COUNTRY, CA 91351
Engineer Sayah,, Daniel H; Lic. No.: S6000 15233 VENTURA BLVD 1130      SHERMAN OAKS, CA 91403
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 7/22/2024 Conditional Approval LILIANA PORTILLO
Piling/Pier/Caisson 7/23/2024 Partial Approval LILIANA PORTILLO
Deputy Reinf. Concrete 7/26/2024 Approved OSVALDO PARAMO
Piling/Pier/Caisson 7/26/2024 Approved OSVALDO PARAMO
Deputy Reinf. Concrete 7/29/2024 Conditional Approval CRAIG VAUGHAN
Underground Mechanical 8/12/2024 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 8/19/2024 Corrections Issued LILIANA PORTILLO
Deputy Reinf. Concrete 8/20/2024 Conditional Approval LILIANA PORTILLO
Footing/Foundation/Slab 8/27/2024 Partial Approval LILIANA PORTILLO
Deputy Shotcrete 8/28/2024 Conditional Approval LILIANA PORTILLO
Footing/Foundation/Slab 9/26/2024 Partial Approval BRENDAN MORELLI
Deputy Reinf. Concrete 9/27/2024 Conditional Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 10/3/2024 Partial Approval JOHN QUINTANILLA
Deputy Reinf. Concrete 10/22/2024 Conditional Approval LILIANA PORTILLO
Footing/Foundation/Slab 10/23/2024 Partial Approval LILIANA PORTILLO
Deputy Reinf. Concrete 10/24/2024 No Access for Inspection LILIANA PORTILLO
Deputy Reinf. Concrete 10/31/2024 Approved LILIANA PORTILLO
Footing/Foundation/Slab 10/31/2024 Partial Approval LILIANA PORTILLO
Deputy Reinf. Concrete 11/1/2024 Conditional Approval LILIANA PORTILLO
PLUMBING-Rough 12/4/2024 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 12/9/2024 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 1/17/2025 Partial Approval LILIANA PORTILLO
Deputy Wood Construction 2/6/2025 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 2/10/2025 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 2/28/2025 Approved LILIANA PORTILLO
HVAC-Rough 2/28/2025 Approved LILIANA PORTILLO
PLUMBING-Rough 2/28/2025 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 3/14/2025 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 3/14/2025 Conditional Approval LILIANA PORTILLO
Verify Sprinkler Sign Off 3/14/2025 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 4/15/2025 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 4/15/2025 Approved LILIANA PORTILLO
Interior/Exterior Lathing 4/15/2025 Partial Approval LILIANA PORTILLO
BUILDING-Rough-Frame 4/22/2025 Approved ANTHONY RAMOS
Green Building Rough 4/22/2025 Approved ANTHONY RAMOS
Insulation 4/22/2025 Corrections Issued ANTHONY RAMOS
Drywall Nailing 5/19/2025 Approved LILIANA PORTILLO
Insulation 5/19/2025 Approved LILIANA PORTILLO
Shower Pan 6/6/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 6/17/2025 Approved BRENDAN MORELLI
Service/Power Release 8/5/2025 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 8/12/2025 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Final 8/20/2025 Approved LILIANA PORTILLO
Service/Power Release 8/26/2025 Approved LILIANA PORTILLO
Final 10/17/2025 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 10/17/2025 Approved LILIANA PORTILLO
Green Building Final 10/17/2025 Not Ready for Inspection LILIANA PORTILLO
HVAC-Final 10/17/2025 Corrections Issued LILIANA PORTILLO
PLUMBING-Final 10/17/2025 Approved LILIANA PORTILLO
Reinforced Concrete Frame 10/17/2025 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 10/17/2025 SGSOV Not Required LILIANA PORTILLO
Smoke Detectors 10/17/2025 Approved LILIANA PORTILLO
Final 10/23/2025 OK to Issue CofO LILIANA PORTILLO
Green Building Final 10/23/2025 Approved LILIANA PORTILLO
HVAC-Final 10/23/2025 Approved LILIANA PORTILLO