1919 N SEIGNEUR AVE 90032
Certificate Information: 1919 N SEIGNEUR AVE 90032
- Application / Permit
- 22010-10000-00560
- Plan Check / Job No.
- B22LA02094
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2 story single family dwelling with attached 2-car garage on a hillside lot with slope greater than 33-1/3 percent.
- Permit Issued
- Issued on 2/26/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | KESETE HAREGOT |
| Corrections Issued | 3/5/2022 | KESETE HAREGOT |
| Quality Review Completed | 3/8/2022 | FARUK SEZER |
| Building Plans Picked Up | 3/10/2022 | APPLICANT |
| Applicant returned to address corrections | 10/12/2023 | KESETE HAREGOT |
| Applicant returned to address corrections | 12/7/2023 | KESETE HAREGOT |
| Plan Check Approved | 1/23/2024 | KESETE HAREGOT |
| Issued | 2/26/2024 | APPLICANT |
| CofO in Progress | 10/27/2025 | LILIANA PORTILLO |
| Permit Finaled | 10/27/2025 | DEROLD HAUFF |
| CofO Issued | 10/27/2025 | DEROLD HAUFF |
| Permit Finaled | 10/27/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/31/2022 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 3/31/2022 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 3/31/2022 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 3/31/2022 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 3/31/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/3/2022 | JEANIE LAM |
| Sewer availability | Cleared | 4/3/2022 | JEANIE LAM |
| Miscellaneous | Cleared | 4/14/2022 | ALBERT TAM |
| Permit | Cleared | 4/19/2022 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 4/22/2022 | THAN WIN |
| Trees in Parkway | Cleared | 5/4/2022 | ADALBERTO VERA |
| Disturb/Remove Protected Trees | Cleared | 5/26/2022 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 7/5/2022 | RUEL COLE |
| "D" conditions | Cleared | 8/17/2022 | SPENCER WEJROWSKI |
| "Q" conditions | Cleared | 8/17/2022 | SPENCER WEJROWSKI |
| Low Impact Development | Cleared | 11/10/2022 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 11/14/2022 | JEANIE LAM |
| Work Adjacent to Public Way | Cleared | 7/6/2023 | JOSE RODRIGUEZ |
| GPI Written Notices | Cleared | 10/12/2023 | KESETE HAREGOT |
| Grading Pre-Inspection | Cleared | 10/12/2023 | KESETE HAREGOT |
| Green Code | Cleared | 10/12/2023 | KESETE HAREGOT |
Contact Information
| Architect | Kivotos,, Juan M; Lic. No.: C26491 | 1323 N NIAGARA STREET BURBANK, CA 91505 |
| Contractor | Ramtin & Associates Llc; Lic. No.: 1102854-B | 13900 MARQUESAS WAY APT-5104 MARINA DEL REY, CA 90292 |
| Engineer | Mirfakhraie,, Ramtin; Lic. No.: C80437 | 32679 SEAGATE DR 203 RANCHO PALOS VERDES, CA 90275 |
| Engineer | Price,, Mark Erin; Lic. No.: L7764 | 18700 WELLHAVEN STREET CANYON COUNTRY, CA 91351 |
| Engineer | Sayah,, Daniel H; Lic. No.: S6000 | 15233 VENTURA BLVD 1130 SHERMAN OAKS, CA 91403 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 7/22/2024 | Conditional Approval | LILIANA PORTILLO |
| Piling/Pier/Caisson | 7/23/2024 | Partial Approval | LILIANA PORTILLO |
| Deputy Reinf. Concrete | 7/26/2024 | Approved | OSVALDO PARAMO |
| Piling/Pier/Caisson | 7/26/2024 | Approved | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 7/29/2024 | Conditional Approval | CRAIG VAUGHAN |
| Underground Mechanical | 8/12/2024 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 8/19/2024 | Corrections Issued | LILIANA PORTILLO |
| Deputy Reinf. Concrete | 8/20/2024 | Conditional Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 8/27/2024 | Partial Approval | LILIANA PORTILLO |
| Deputy Shotcrete | 8/28/2024 | Conditional Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 9/26/2024 | Partial Approval | BRENDAN MORELLI |
| Deputy Reinf. Concrete | 9/27/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 10/3/2024 | Partial Approval | JOHN QUINTANILLA |
| Deputy Reinf. Concrete | 10/22/2024 | Conditional Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 10/23/2024 | Partial Approval | LILIANA PORTILLO |
| Deputy Reinf. Concrete | 10/24/2024 | No Access for Inspection | LILIANA PORTILLO |
| Deputy Reinf. Concrete | 10/31/2024 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 10/31/2024 | Partial Approval | LILIANA PORTILLO |
| Deputy Reinf. Concrete | 11/1/2024 | Conditional Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 12/4/2024 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2024 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2025 | Partial Approval | LILIANA PORTILLO |
| Deputy Wood Construction | 2/6/2025 | Conditional Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2025 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 2/28/2025 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 2/28/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 2/28/2025 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 3/14/2025 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2025 | Conditional Approval | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 3/14/2025 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 4/15/2025 | Conditional Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2025 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 4/15/2025 | Partial Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 4/22/2025 | Approved | ANTHONY RAMOS |
| Green Building Rough | 4/22/2025 | Approved | ANTHONY RAMOS |
| Insulation | 4/22/2025 | Corrections Issued | ANTHONY RAMOS |
| Drywall Nailing | 5/19/2025 | Approved | LILIANA PORTILLO |
| Insulation | 5/19/2025 | Approved | LILIANA PORTILLO |
| Shower Pan | 6/6/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 6/17/2025 | Approved | BRENDAN MORELLI |
| Service/Power Release | 8/5/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 8/12/2025 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Final | 8/20/2025 | Approved | LILIANA PORTILLO |
| Service/Power Release | 8/26/2025 | Approved | LILIANA PORTILLO |
| Final | 10/17/2025 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 10/17/2025 | Approved | LILIANA PORTILLO |
| Green Building Final | 10/17/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Final | 10/17/2025 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Final | 10/17/2025 | Approved | LILIANA PORTILLO |
| Reinforced Concrete Frame | 10/17/2025 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 10/17/2025 | SGSOV Not Required | LILIANA PORTILLO |
| Smoke Detectors | 10/17/2025 | Approved | LILIANA PORTILLO |
| Final | 10/23/2025 | OK to Issue CofO | LILIANA PORTILLO |
| Green Building Final | 10/23/2025 | Approved | LILIANA PORTILLO |
| HVAC-Final | 10/23/2025 | Approved | LILIANA PORTILLO |