3150 W LACLEDE AVE 90039
Certificate Information: 3150 W LACLEDE AVE 90039
- Application / Permit
- 22010-10000-00543
- Plan Check / Job No.
- B22LA01992
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* NEW DETACHED (20' X 30') ADU (ZC: 543 SF) PER LAMC 12.22.A.33(c)-(d). SOLAR DEFERRED. SOLAR TO BE INSTALLED TO MEET KW PER TITLE 24 PRIOR TO C OF O
- Permit Issued
- Issued on 7/11/2022
- Issuing Office
- Current Status
- CofO Issued on 12/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/15/2022 | VIVIAN LAO |
| Corrections Issued | 2/16/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 3/16/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 3/17/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 5/27/2022 | VIVIAN LAO |
| Plan Check Approved | 7/7/2022 | VIVIAN LAO |
| Issued | 7/11/2022 | APPLICANT |
| CofO in Progress | 12/4/2024 | THOMAS LOGRASSO |
| Permit Finaled | 12/7/2024 | DEROLD HAUFF |
| CofO Issued | 12/7/2024 | DEROLD HAUFF |
| Permit Finaled | 12/7/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| "Q" conditions | Cleared | 4/19/2022 | RYAN LY |
| ZI | Cleared | 4/19/2022 | RYAN LY |
| Address approval | Cleared | 4/20/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 4/25/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 4/25/2022 | STEVE MELGAR |
| Low Impact Development | Cleared | 6/29/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 7/5/2022 | CINDY QI |
Contact Information
| Contractor | Cbkme Inc; Lic. No.: 755006-B | , |
| Engineer | Mirhosseini,, Maj; Lic. No.: C60576 | 6255 E 6TH ST LONG BEACH, CA 90803 |
| Engineer | Mirhosseini,, Maj; Lic. No.: NA60576 | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/6/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Underground Mechanical | 9/6/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 9/12/2022 | Partial Approval | AMY COLIN |
| Footing/Foundation/Slab | 9/19/2022 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 10/27/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 10/27/2022 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 1/5/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 1/5/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 1/5/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 1/5/2023 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 1/5/2023 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 1/5/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 1/18/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 3/20/2023 | No Access for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/27/2023 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 4/27/2023 | Partial Approval | SCOTT FINNILA |
| Underground Mechanical | 4/27/2023 | Partial Approval | SCOTT FINNILA |
| Pre-Inspection | 5/10/2023 | Corrections Issued | SCOTT FINNILA |
| Underground Mechanical | 5/10/2023 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 6/16/2023 | Corrections Issued | JEFFREY MEAD |
| Interior/Exterior Lathing | 6/16/2023 | Partial Inspection | JEFFREY MEAD |
| ELECTRICAL-Rough | 7/20/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 7/26/2023 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 8/7/2023 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/14/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 8/14/2023 | Approved | HAMIK HARTOUNIAN |
| Insulation | 9/15/2023 | Approved | JOSH MEISTER |
| BUILDING-Rough-Frame | 10/5/2023 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 12/21/2023 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 12/21/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Final | 4/10/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Gas Test | 4/10/2024 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 4/10/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 4/10/2024 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Service/Power Release | 4/10/2024 | Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 4/10/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 5/9/2024 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 5/9/2024 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 5/9/2024 | SGSOV Approved | THOMAS LOGRASSO |
| Service/Power Release | 5/9/2024 | Approved | THOMAS LOGRASSO |
| Smoke Detectors | 5/9/2024 | Approved | THOMAS LOGRASSO |
| Final | 9/12/2024 | Corrections Issued | THOMAS LOGRASSO |
| Final | 11/15/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 11/27/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 12/3/2024 | OK to Issue CofO | THOMAS LOGRASSO |
| Service/Power Release | 12/3/2024 | Approved | THOMAS LOGRASSO |