921 E 32ND ST 90011

Certificate Information: 921 E 32ND ST 90011

Application / Permit
22010-10000-00509
Plan Check / Job No.
B22LA01846
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
POPOSED ACCESSORY DEWLLING UNIT WITH 2-CAR GARAGE ***"COMPLY WITH DEPARTMENT ORDER effective date 08/31/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 9/13/2022
Issuing Office
Metro
Current Status
CofO Issued on 8/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/2/2022 APPLICANT
Assigned to Plan Check Engineer 2/17/2022 SINA KHOSRAVI
Corrections Issued 3/2/2022 SINA KHOSRAVI
Quality Review Completed 3/7/2022 CHARLES CHANG
Building Plans Picked Up 3/9/2022 APPLICANT
Applicant returned to address corrections 8/22/2022 SINA KHOSRAVI
Plan Check Approved 9/8/2022 SINA KHOSRAVI
Issued 9/13/2022 APPLICANT
CofO in Progress 7/28/2023 BRENDAN MORELLI
Permit Finaled 8/1/2023 DEROLD HAUFF
CofO Issued 8/1/2023 DEROLD HAUFF
Permit Finaled 8/1/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/15/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 6/17/2022 JEANIE LAM
Sewer availability Cleared 6/21/2022 JEANIE LAM
Hydrant and Access approval Cleared 7/19/2022 LAVEON RIDER
Low Impact Development Cleared 7/25/2022 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 7/27/2022 JEANIE LAM

Contact Information

Contractor Pacific Coast Builders; Lic. No.: 834794-B 9277OTTO ST      DOWNEY, CA 90240
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/18/2022 Not Ready for Inspection RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 10/19/2022 Approved RYAN SALAZAR
Underground Mechanical 10/19/2022 Approved RYAN SALAZAR
Footing/Foundation/Slab 10/25/2022 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/7/2022 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/15/2022 Approved BRENDAN MORELLI
HVAC-Rough 2/8/2023 Approved BRENDAN MORELLI
PLUMBING-Rough 2/8/2023 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 2/9/2023 Conditional Approval BRENDAN MORELLI
ELECTRICAL-Rough 2/9/2023 Approved BRENDAN MORELLI
Green Building Rough 2/9/2023 Not Ready for Inspection BRENDAN MORELLI
Verify Sprinkler Sign Off 2/9/2023 Approved BRENDAN MORELLI
Interior/Exterior Lathing 2/16/2023 Partial Approval BRENDAN MORELLI
Insulation 2/22/2023 Corrections Issued BRENDAN MORELLI
Insulation 3/3/2023 Approved ALIZAH MAYAGOITIA
Drywall Nailing 3/9/2023 Approved BRENDAN MORELLI
Green Building Rough 3/9/2023 Approved BRENDAN MORELLI
Interior/Exterior Lathing 4/3/2023 Approved BRENDAN MORELLI
Gas Test 4/20/2023 Approved BRENDAN MORELLI
Sewer 4/20/2023 Approved BRENDAN MORELLI
Underground Mechanical 4/20/2023 Approved BRENDAN MORELLI
Underground Mechanical 4/24/2023 Approved BRENDAN MORELLI
Gas Test 5/31/2023 Approved BRENDAN MORELLI
Verify Rec and Parks Fee Memo 5/31/2023 Approved BRENDAN MORELLI
HVAC-Final 7/19/2023 Corrections Issued BRENDAN MORELLI
PLUMBING-Final 7/19/2023 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 7/21/2023 Approved BRENDAN MORELLI
ELECTRICAL-Final 7/21/2023 Approved BRENDAN MORELLI
Final 7/21/2023 OK to Issue CofO BRENDAN MORELLI
Green Building Final 7/21/2023 Approved BRENDAN MORELLI
HVAC-Final 7/21/2023 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 7/21/2023 SGSOV Approved BRENDAN MORELLI
Service/Power Release 7/21/2023 Approved BRENDAN MORELLI
Smoke Detectors 7/21/2023 Approved BRENDAN MORELLI
Special/Order Compliance 7/25/2023 Approved BRENDAN MORELLI