25214 S FRAMPTON AVE 1-2 90710
Certificate Information: 25214 S FRAMPTON AVE 1-2 90710
- Application / Permit
- 22010-10000-00497
- Plan Check / Job No.
- B22LA01828
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED A.D.U. AND GARAGE (UNIT A)
- Permit Issued
- Issued on 6/1/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | ERIC WONG |
| Corrections Issued | 2/19/2022 | ERIC WONG |
| Quality Review Completed | 2/28/2022 | PETER KIM |
| Building Plans Picked Up | 3/8/2022 | APPLICANT |
| Plan Check Approved | 2/9/2023 | ERIC WONG |
| Issued | 6/1/2023 | APPLICANT |
| CofO in Progress | 1/8/2025 | EUGENE CASSIDY |
| Permit Finaled | 1/8/2025 | ANSON MAGLASANG |
| CofO Issued | 1/8/2025 | ANSON MAGLASANG |
| Permit Finaled | 1/8/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 3/29/2022 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2022 | JOSE HERNANDEZ |
| "Q" conditions | Cleared | 6/28/2022 | MAYELA VILLA |
| Frnt yard landscape/Water mgmt | Cleared | 6/28/2022 | MAYELA VILLA |
| Opn space landscape/Water mgmt | Cleared | 6/28/2022 | MAYELA VILLA |
| Sewer availability | Cleared | 7/22/2022 | JOSE HERNANDEZ |
| Hydrant and Access approval | Cleared | 9/8/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 1/26/2023 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 1/31/2023 | ANA SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
| Geologist | Feucht,, Alex Thomas; Lic. No.: GEO4433 | 2443 EAGLE HARBOR DRIVE HENDERSON, NV 890527136 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Methane Barrier | 7/19/2023 | Partial Approval | EUGENE CASSIDY |
| METHANE-Barrier | 7/19/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Final | 7/19/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 7/19/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Subgrade | 7/19/2023 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 7/19/2023 | Partial Approval | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 7/31/2023 | Corrections Issued | EUGENE CASSIDY |
| METHANE-Final | 7/31/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 7/31/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Structural Steel Frame | 7/31/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 8/11/2023 | Corrections Issued | EUGENE CASSIDY |
| Structural Steel Frame | 8/11/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 9/12/2023 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 9/12/2023 | Approved | EUGENE CASSIDY |
| METHANE-Barrier | 9/12/2023 | Approved | EUGENE CASSIDY |
| Structural Steel Frame | 9/12/2023 | Partial Approval | EUGENE CASSIDY |
| Sewer | 9/26/2023 | Partial Approval | JOHN KLARIN |
| Special/Order Compliance | 9/26/2023 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2023 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2023 | Approved | JAMES CHAVEZ |
| Wood Frame | 11/16/2023 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Rough | 1/11/2024 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 1/11/2024 | Approved | EUGENE CASSIDY |
| METHANE-Final | 1/11/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 1/11/2024 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 1/11/2024 | Corrections Issued | EUGENE CASSIDY |
| Underground Mechanical | 1/11/2024 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 1/29/2024 | Approved | EUGENE CASSIDY |
| Insulation | 3/21/2024 | Conditional Approval | EUGENE CASSIDY |
| Interior/Exterior Lathing | 3/21/2024 | Approved | EUGENE CASSIDY |
| Shower Pan | 3/21/2024 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 4/1/2024 | Approved | EUGENE CASSIDY |
| Gas Test | 11/5/2024 | Approved | EUGENE CASSIDY |
| Green Building Final | 11/5/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Final | 11/5/2024 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Final | 11/5/2024 | Approved | EUGENE CASSIDY |
| Verify Rec and Parks Fee Memo | 11/5/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 12/24/2024 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 12/24/2024 | Approved | EUGENE CASSIDY |
| Final | 12/24/2024 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 12/24/2024 | Approved | EUGENE CASSIDY |
| Green Building Rough | 12/24/2024 | Approved | EUGENE CASSIDY |
| HVAC-Final | 12/24/2024 | Approved | EUGENE CASSIDY |
| METHANE-Final | 12/24/2024 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 12/24/2024 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 12/24/2024 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 12/24/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 12/24/2024 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 12/24/2024 | Approved | EUGENE CASSIDY |
| Final | 1/7/2025 | OK to Issue CofO | EUGENE CASSIDY |
| Service/Power Release | 1/7/2025 | Approved | EUGENE CASSIDY |