22560 W LASSEN ST 91311

Certificate Information: 22560 W LASSEN ST 91311

Application / Permit
22010-10000-00494
Plan Check / Job No.
B22LA01826
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
FOR PROPOSED NEW DETACHED ADU AT THE REAR OF PROPERTY, WITH ROOF DECK. 1-STORY 3 BED AND 2 BATH, 1 ADA BATH. TOTAL PROPOSED RFA (800 S.F.). MAX HEIGHT 15'-6" NON-SPRINKLERED.
Permit Issued
Issued on 7/12/2022
Issuing Office
Metro
Current Status
CofO Issued on 7/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2022 APPLICANT
Assigned to Plan Check Engineer 3/3/2022 JAD BASMA
Corrections Issued 3/11/2022 JAD BASMA
Quality Review Completed 3/18/2022 KEN GILL
Building Plans Picked Up 4/8/2022 APPLICANT
Applicant returned to address corrections 7/8/2022 JAD BASMA
Plan Check Approved 7/12/2022 JAD BASMA
Issued 7/12/2022 APPLICANT
CofO in Progress 6/18/2025 CHRIS CHRISTENSEN
Permit Finaled 7/1/2025 JOHN JANSON
CofO Issued 7/1/2025 JOHN JANSON
Permit Finaled 7/1/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/14/2022 CARLOS AGUILERA
Address approval Cleared 3/14/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 3/14/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 3/14/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 3/14/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 3/14/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 3/14/2022 CARLOS AGUILERA
Watercourse Cleared 3/15/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/16/2022 CARLOS AGUILERA
Sewer availability Cleared 3/16/2022 CARLOS AGUILERA
Low Impact Development Cleared 5/18/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 5/19/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 5/20/2022 GILBERT URREA
GPI Written Notices Cleared 7/8/2022 JAD BASMA
Permit Cleared 7/11/2022 CINDY QI

Contact Information

Contractor Owner-Builder       ,
Engineer Mlb, Engineering; Lic. No.: C76761 7918 FOOTHILL BLVD      SUNLAND, CA 91040

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/11/2023 Partial Inspection KRISTEN CAUSEY
Pre-Inspection 7/3/2023 Approved CHRIS CHRISTENSEN
Underground Mechanical 11/1/2023 Partial Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 11/7/2023 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 11/28/2023 Conditional Approval CHRIS CHRISTENSEN
Special/Order Compliance 11/28/2023 Corrections Issued CHRIS CHRISTENSEN
BUILDING-Rough-Frame 12/14/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Rough 12/14/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 12/14/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Wood Frame 12/14/2023 Partial Approval CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 1/8/2024 Not Ready for Inspection CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 1/18/2024 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 1/23/2024 Conditional Approval CHRIS CHRISTENSEN
Green Building Rough 1/23/2024 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 1/23/2024 Partial Approval CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 1/23/2024 Approved CHRIS CHRISTENSEN
Wood Frame 1/23/2024 Approved CHRIS CHRISTENSEN
Insulation 1/29/2024 Conditional Approval CHRIS CHRISTENSEN
Special/Order Compliance 3/1/2024 Corrections Issued CHRIS CHRISTENSEN
Underground Mechanical 3/1/2024 Approved CHRIS CHRISTENSEN
Drywall Nailing 3/20/2024 Approved CHRIS CHRISTENSEN
Shower Pan 3/20/2024 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 4/10/2024 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/18/2024 Not Ready for Inspection CHRIS CHRISTENSEN
Final 10/18/2024 Not Ready for Inspection CHRIS CHRISTENSEN
Footing/Foundation/Slab 10/18/2024 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 10/18/2024 Not Ready for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 10/18/2024 SGSOV Not Ready CHRIS CHRISTENSEN
Service/Power Release 10/18/2024 Not Ready for Inspection CHRIS CHRISTENSEN
Smoke Detectors 10/18/2024 Not Ready for Inspection CHRIS CHRISTENSEN
Wood Frame 1/10/2025 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 6/3/2025 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 6/3/2025 Approved CHRIS CHRISTENSEN
Final 6/3/2025 Corrections Issued CHRIS CHRISTENSEN
Footing/Foundation/Slab 6/3/2025 Approved CHRIS CHRISTENSEN
Green Building Final 6/3/2025 Approved CHRIS CHRISTENSEN
HVAC-Final 6/3/2025 Approved CHRIS CHRISTENSEN
PLUMBING-Final 6/3/2025 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 6/3/2025 SGSOV Not Ready CHRIS CHRISTENSEN
Service/Power Release 6/3/2025 Not Ready for Inspection CHRIS CHRISTENSEN
Smoke Detectors 6/3/2025 Approved CHRIS CHRISTENSEN
Final 6/12/2025 Conditional Approval CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 6/12/2025 SGSOV Approved CHRIS CHRISTENSEN
Service/Power Release 6/12/2025 Approved CHRIS CHRISTENSEN
Final 6/17/2025 OK to Issue CofO CHRIS CHRISTENSEN