Pre-Inspection
|
3/11/2024
|
Approved
|
EDWIN GREGORYONA
|
|
Piling/Pier/Caisson
|
4/10/2024
|
Partial Approval
|
NICK DANERI
|
|
Deputy Steel/Welding
|
4/30/2024
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Steel/Welding
|
5/1/2024
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
5/15/2024
|
Partial Approval
|
JACOB MYERS
|
|
Deputy Steel/Welding
|
6/5/2024
|
Conditional Approval
|
NICK DANERI
|
|
METHANE-Barrier
|
6/17/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
METHANE-Subgrade
|
6/17/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
6/20/2024
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
6/20/2024
|
Partial Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
6/25/2024
|
Partial Inspection
|
NICK DANERI
|
|
METHANE-Rough
|
7/2/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
METHANE-Subgrade
|
7/2/2024
|
Partial Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
7/12/2024
|
Partial Approval
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
7/12/2024
|
Partial Approval
|
NICK DANERI
|
|
METHANE-Barrier
|
7/12/2024
|
Partial Inspection
|
NICK DANERI
|
|
METHANE-Subgrade
|
7/12/2024
|
Partial Inspection
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
7/18/2024
|
Partial Approval
|
JEROME BLACKWOOD
|
|
Footing/Foundation/Slab
|
7/18/2024
|
Partial Approval
|
JEROME BLACKWOOD
|
|
METHANE-Barrier
|
7/18/2024
|
Partial Inspection
|
JEROME BLACKWOOD
|
|
METHANE-Subgrade
|
7/18/2024
|
Partial Inspection
|
JEROME BLACKWOOD
|
|
Deputy Methane Barrier
|
7/25/2024
|
Conditional Approval
|
NICK DANERI
|
|
METHANE-Barrier
|
7/25/2024
|
Partial Inspection
|
NICK DANERI
|
|
Deputy Methane Barrier
|
7/29/2024
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Methane Barrier
|
8/8/2024
|
Conditional Approval
|
NICK DANERI
|
|
METHANE-Barrier
|
8/8/2024
|
Partial Approval
|
NICK DANERI
|
|
Deputy Methane Barrier
|
8/12/2024
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Methane Barrier
|
8/13/2024
|
Conditional Approval
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
8/13/2024
|
Partial Approval
|
NICK DANERI
|
|
METHANE-Subgrade
|
8/13/2024
|
Partial Approval
|
NICK DANERI
|
|
Deputy Methane Barrier
|
8/14/2024
|
Conditional Approval
|
NICK DANERI
|
|
METHANE-Rough
|
8/28/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Masonry Wall/Backfill
|
8/28/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
9/5/2024
|
Partial Approval
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
9/5/2024
|
Partial Inspection
|
NICK DANERI
|
|
METHANE-Barrier
|
9/5/2024
|
Partial Approval
|
NICK DANERI
|
|
METHANE-Subgrade
|
9/5/2024
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Shotcrete
|
9/11/2024
|
Conditional Approval
|
NICK DANERI
|
|
Masonry Wall/Backfill
|
9/11/2024
|
Partial Approval
|
NICK DANERI
|
|
Masonry Wall/Backfill
|
9/13/2024
|
Partial Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
9/17/2024
|
Partial Approval
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
9/25/2024
|
Partial Approval
|
NICK DANERI
|
|
METHANE-Barrier
|
9/25/2024
|
Conditional Approval
|
NICK DANERI
|
|
METHANE-Subgrade
|
9/25/2024
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Shotcrete
|
10/2/2024
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
10/2/2024
|
Partial Approval
|
NICK DANERI
|
|
Masonry Wall/Backfill
|
10/2/2024
|
Partial Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
10/7/2024
|
Partial Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
10/18/2024
|
Partial Approval
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
10/18/2024
|
Partial Approval
|
NICK DANERI
|
|
METHANE-Barrier
|
10/18/2024
|
Conditional Approval
|
NICK DANERI
|
|
METHANE-Subgrade
|
10/18/2024
|
Partial Approval
|
NICK DANERI
|
|
Masonry Wall/Backfill
|
10/18/2024
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
10/23/2024
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
10/23/2024
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
10/23/2024
|
Partial Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
10/30/2024
|
Partial Approval
|
LARRY ARNICK
|
|
Masonry Wall/Backfill
|
10/30/2024
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Masonry
|
11/6/2024
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
11/6/2024
|
Partial Approval
|
NICK DANERI
|
|
Masonry Wall/Backfill
|
11/6/2024
|
Partial Inspection
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
11/8/2024
|
Partial Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
11/15/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Masonry Wall/Backfill
|
11/15/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Masonry
|
11/19/2024
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
11/19/2024
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
11/22/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
11/22/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
11/26/2024
|
Partial Approval
|
NICK DANERI
|
|
Masonry Wall/Backfill
|
11/26/2024
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
12/4/2024
|
Conditional Approval
|
JEFFREY FULTON
|
|
Excavation/Setback/Form/Re-Bar
|
12/4/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Masonry Wall/Backfill
|
12/4/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Deputy Reinf. Concrete
|
12/6/2024
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
12/6/2024
|
Partial Approval
|
NICK DANERI
|
|
Masonry Wall/Backfill
|
12/6/2024
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
12/13/2024
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
12/13/2024
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
12/16/2024
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
12/16/2024
|
Partial Approval
|
NICK DANERI
|
|
Masonry Wall/Backfill
|
12/16/2024
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
12/20/2024
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
12/20/2024
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
12/20/2024
|
Partial Approval
|
NICK DANERI
|
|
Deputy Steel/Welding
|
1/2/2025
|
Conditional Approval
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
1/2/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Masonry Wall/Backfill
|
1/2/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
1/7/2025
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
1/7/2025
|
Partial Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
1/17/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
1/27/2025
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
1/27/2025
|
Partial Approval
|
NICK DANERI
|
|
Masonry Wall/Backfill
|
1/27/2025
|
Not Ready for Inspection
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
1/30/2025
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
1/30/2025
|
Partial Approval
|
NICK DANERI
|
|
Masonry Wall/Backfill
|
1/30/2025
|
Not Ready for Inspection
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
2/3/2025
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
2/3/2025
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
2/10/2025
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
2/10/2025
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
2/10/2025
|
Partial Approval
|
NICK DANERI
|
|
Masonry Wall/Backfill
|
2/10/2025
|
Partial Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
2/14/2025
|
Partial Approval
|
NICK DANERI
|
|
Masonry Wall/Backfill
|
2/14/2025
|
Partial Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
3/12/2025
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
3/17/2025
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
3/17/2025
|
Partial Approval
|
NICK DANERI
|
|
Wall Anchors
|
3/17/2025
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
3/24/2025
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
3/24/2025
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
3/27/2025
|
Partial Approval
|
NICK DANERI
|
|
Green Building Rough
|
3/27/2025
|
Not Ready for Inspection
|
NICK DANERI
|
|
Drywall Nailing
|
4/3/2025
|
Partial Approval
|
NICK DANERI
|
|
Green Building Rough
|
4/3/2025
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
4/11/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Green Building Rough
|
4/11/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/15/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
4/16/2025
|
Conditional Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/16/2025
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
4/21/2025
|
Partial Approval
|
NICK DANERI
|
|
Green Building Rough
|
4/21/2025
|
Not Ready for Inspection
|
NICK DANERI
|
|
Deputy Wood Construction
|
4/23/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
4/23/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/23/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Steel/Welding
|
4/25/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
4/25/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
4/25/2025
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
4/29/2025
|
Partial Approval
|
NICK DANERI
|
|
Green Building Rough
|
4/29/2025
|
Not Ready for Inspection
|
NICK DANERI
|
|
Insulation
|
4/29/2025
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
5/2/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
5/8/2025
|
Conditional Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/8/2025
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
5/13/2025
|
Partial Approval
|
NICK DANERI
|
|
Green Building Rough
|
5/13/2025
|
Not Ready for Inspection
|
NICK DANERI
|
|
Deputy Wood Construction
|
5/15/2025
|
Conditional Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/15/2025
|
Partial Approval
|
NICK DANERI
|
|
Light Gage Steel Frame
|
5/28/2025
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
5/30/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/30/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
6/3/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
6/3/2025
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
6/4/2025
|
No Result Entered
|
NICK DANERI
|
|
Deputy Wood Construction
|
6/5/2025
|
Conditional Approval
|
JOEY BUCHANAN
|
|
Deputy Wood Construction
|
6/6/2025
|
Conditional Approval
|
JOEY BUCHANAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/6/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Drywall Nailing
|
6/9/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Green Building Rough
|
6/9/2025
|
Approved
|
JOEY BUCHANAN
|
|
Deputy Steel/Welding
|
6/12/2025
|
Conditional Approval
|
JOEY BUCHANAN
|
|
Deputy Wood Construction
|
6/12/2025
|
Conditional Approval
|
JOEY BUCHANAN
|
|
Deputy Wood Construction
|
6/13/2025
|
Conditional Approval
|
JOEY BUCHANAN
|
|
Drywall Nailing
|
6/13/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Drywall Nailing
|
6/20/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/20/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
6/24/2025
|
Conditional Approval
|
JOEY BUCHANAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/24/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Deputy Wood Construction
|
6/25/2025
|
Conditional Approval
|
JOEY BUCHANAN
|
|
Deputy Wood Construction
|
6/26/2025
|
No Access for Inspection
|
JOEY BUCHANAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/26/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Deputy Wood Construction
|
6/27/2025
|
Conditional Approval
|
JOEY BUCHANAN
|
|
Drywall Nailing
|
7/2/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
7/8/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/8/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
7/8/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
7/10/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Insulation
|
7/10/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Insulation
|
7/15/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Insulation
|
7/18/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Deputy Steel/Welding
|
7/22/2025
|
Conditional Approval
|
JOEY BUCHANAN
|
|
Insulation
|
7/23/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Drywall Nailing
|
7/25/2025
|
Conditional Approval
|
JOEY BUCHANAN
|
|
Insulation
|
7/25/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Deputy Wood Construction
|
7/28/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/28/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Deputy Wood Construction
|
7/29/2025
|
Conditional Approval
|
JOEY BUCHANAN
|
|
Insulation
|
7/29/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Deputy Wood Construction
|
7/30/2025
|
Conditional Approval
|
JOEY BUCHANAN
|
|
Deputy Wood Construction
|
7/31/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Deputy Wood Construction
|
8/1/2025
|
Conditional Approval
|
JOEY BUCHANAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/6/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
8/8/2025
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/8/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
8/8/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
8/13/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/15/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
8/15/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
8/19/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/19/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
8/19/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
8/22/2025
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
8/22/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
8/26/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
8/26/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
8/29/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Wood Frame
|
8/29/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/2/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/5/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
9/8/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/8/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
9/11/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
9/15/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
9/17/2025
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/18/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/26/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
9/29/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Special/Order Compliance
|
10/2/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
10/3/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
10/9/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Order to Comply
|
10/15/2025
|
Not Required
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
10/20/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Light Gage Steel Frame
|
10/21/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
10/30/2025
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Insulation
|
11/4/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
11/5/2025
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
11/10/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
11/10/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
11/10/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
11/12/2025
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Interior/Exterior Lathing
|
11/12/2025
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Drywall Nailing
|
11/17/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Order to Comply
|
11/20/2025
|
Not Required
|
LARRY ARNICK
|
|
Insulation
|
11/25/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
12/2/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
Insulation
|
12/3/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
12/5/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
12/8/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
12/10/2025
|
Order to Comply Issued
|
LARRY ARNICK
|
|
Drywall Nailing
|
12/11/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
12/11/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
12/15/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
12/17/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
12/17/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
12/19/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
12/22/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
12/22/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
12/29/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
12/29/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
1/7/2026
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
1/9/2026
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Special/Order Compliance
|
1/9/2026
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Insulation
|
1/12/2026
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
1/14/2026
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
1/14/2026
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
1/16/2026
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
1/21/2026
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
1/29/2026
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
2/5/2026
|
Partial Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
2/10/2026
|
Partial Approval
|
RONALD JIMENEZ
|
|
Wood Frame
|
2/10/2026
|
Corrections Issued
|
RONALD JIMENEZ
|
|
Insulation
|
2/17/2026
|
Partial Approval
|
RONALD JIMENEZ
|
|
Insulation
|
2/19/2026
|
Partial Approval
|
RONALD JIMENEZ
|
|
Insulation
|
2/23/2026
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
3/2/2026
|
Partial Approval
|
RONALD JIMENEZ
|
|
Insulation
|
3/2/2026
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
3/6/2026
|
Partial Approval
|
JOEY BUCHANAN
|
|
Insulation
|
3/9/2026
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
3/12/2026
|
Partial Approval
|
RAFAEL CORTES
|
|
Insulation
|
3/25/2026
|
Partial Approval
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
3/31/2026
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
4/3/2026
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
4/6/2026
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
4/8/2026
|
Partial Approval
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
4/8/2026
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
4/15/2026
|
Partial Approval
|
RONALD JIMENEZ
|
|
Insulation
|
4/20/2026
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
4/22/2026
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
5/4/2026
|
Partial Approval
|
JOEY BUCHANAN
|
|
Drywall Nailing
|
5/12/2026
|
Partial Approval
|
JOEY BUCHANAN
|
|
Drywall Nailing
|
5/19/2026
|
Partial Approval
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
5/19/2026
|
Partial Approval
|
RONALD JIMENEZ
|
|
Interior/Exterior Lathing
|
5/20/2026
|
Partial Approval
|
JOEY BUCHANAN
|
|
Drywall Nailing
|
6/1/2026
|
Approved
|
JOEY BUCHANAN
|