1446 N MCDONALD AVE 90744

Certificate Information: 1446 N MCDONALD AVE 90744

Application / Permit
22010-10000-00489
Plan Check / Job No.
B22LA01771
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION OF NEW ADU TO DETACHED GARAGE. LID PLANS REQUIRED PRIOR TO C OF O.
Permit Issued
Issued on 8/24/2022
Issuing Office
Current Status
CofO Issued on 2/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/1/2022 APPLICANT
Assigned to Plan Check Engineer 2/11/2022 JOE VO
Corrections Issued 2/12/2022 JOE VO
Quality Review Completed 2/14/2022 LIPING TENG
Applicant returned to address corrections 4/28/2022 JOE VO
Plan Check Approved 6/7/2022 JOE VO
Issued 8/24/2022 APPLICANT
CofO in Progress 2/9/2024 EUGENE CASSIDY
Permit Finaled 2/9/2024 ANSON MAGLASANG
CofO Issued 2/9/2024 ANSON MAGLASANG
Permit Finaled 2/9/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 2/15/2022 ANA VILLA
Clean Up Green Up Cleared 2/23/2022 LOUIS ORTEGA
Eng Process Fee Ord 176,300 Cleared 5/11/2022 ANA VILLA
Sewer availability Cleared 5/11/2022 ANA VILLA
Roof/Waste drainage to street Cleared 8/16/2022 ANA VILLA

Contact Information

Contractor Dhs Ventures Inc; Lic. No.: 1047699-B       ,
Contractor La Ccs; Lic. No.: 1047699-B       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/29/2022 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 9/2/2022 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 9/12/2022 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 9/13/2022 No Access for Inspection EUGENE CASSIDY
METHANE-Barrier 9/13/2022 Not Ready for Inspection EUGENE CASSIDY
METHANE-Subgrade 9/13/2022 Corrections Issued EUGENE CASSIDY
Deputy Wood Construction 9/22/2022 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 9/22/2022 Partial Approval EUGENE CASSIDY
METHANE-Barrier 9/22/2022 Approved EUGENE CASSIDY
METHANE-Subgrade 9/22/2022 Corrections Issued EUGENE CASSIDY
Pre-Inspection 9/28/2022 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 10/4/2022 Approved EUGENE CASSIDY
METHANE-Subgrade 10/4/2022 Approved EUGENE CASSIDY
Deputy Drilled-In Anchors 11/17/2022 Partial Approval EUGENE CASSIDY
Wood Frame 11/18/2022 Partial Approval EUGENE CASSIDY
Deputy Wood Construction 11/22/2022 No Result Entered BOB GOBUTY
Floor/Roof Diaphrgm/Shear Wall 11/23/2022 Partial Approval EUGENE CASSIDY
Wood Frame 11/23/2022 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 12/13/2022 Not Ready for Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 12/13/2022 Approved EUGENE CASSIDY
Interior/Exterior Lathing 12/13/2022 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Final 12/13/2022 Not Ready for Inspection EUGENE CASSIDY
Wood Frame 12/13/2022 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 12/23/2022 Approved JAMES CHAVEZ
ELECTRICAL-Rough 12/23/2022 Off-Hour Fees Due
PLUMBING-Rough 12/23/2022 Approved JAMES CHAVEZ
PLUMBING-Rough 12/23/2022 Off-Hour Fees Due
Wood Frame 12/23/2022 Approved JAMES CHAVEZ
Wood Frame 12/23/2022 Off-Hour Fees Due
Rough-Elec/Plmb/HVAC 1/17/2023 Partial Approval EUGENE CASSIDY
Insulation 2/2/2023 Corrections Issued EUGENE CASSIDY
Insulation 2/7/2023 Partial Approval EUGENE CASSIDY
Drywall Nailing 4/11/2023 Corrections Issued EUGENE CASSIDY
Interior/Exterior Lathing 4/11/2023 Partial Approval EUGENE CASSIDY
Shower Pan 4/11/2023 Not Ready for Inspection EUGENE CASSIDY
Drywall Nailing 4/17/2023 Approved EUGENE CASSIDY
Shower Pan 4/17/2023 Approved EUGENE CASSIDY
Sewer 7/10/2023 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 7/17/2023 SGSOV Not Ready EUGENE CASSIDY
BUILDING-Rough-Frame 7/21/2023 Not Ready for Inspection EUGENE CASSIDY
Final 7/21/2023 Corrections Issued EUGENE CASSIDY
Green Building Final 7/21/2023 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 7/21/2023 Approved EUGENE CASSIDY
METHANE-Final 7/21/2023 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 7/21/2023 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 7/21/2023 SGSOV Not Ready EUGENE CASSIDY
Sewer 7/21/2023 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 7/21/2023 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 9/1/2023 Approved EUGENE CASSIDY
Final 9/1/2023 Corrections Issued EUGENE CASSIDY
Green Building Final 9/1/2023 Not Ready for Inspection EUGENE CASSIDY
METHANE-Final 9/1/2023 Approved EUGENE CASSIDY
METHANE-Rough 9/1/2023 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 9/1/2023 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 9/1/2023 Approved EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 9/27/2023 Corrections Issued EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 10/2/2023 Corrections Issued EUGENE CASSIDY
Deputy Drilled-In Anchors 10/3/2023 Partial Approval EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 10/4/2023 Approved EUGENE CASSIDY
PLUMBING-Final 11/6/2023 Not Ready for Inspection EUGENE CASSIDY
Final 11/30/2023 Corrections Issued EUGENE CASSIDY
Green Building Final 11/30/2023 Approved EUGENE CASSIDY
Final 12/15/2023 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Final 2/8/2024 Approved EUGENE CASSIDY
Final 2/8/2024 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 2/8/2024 Approved EUGENE CASSIDY
PLUMBING-Final 2/8/2024 Approved EUGENE CASSIDY