756 W 169TH ST 90247

Certificate Information: 756 W 169TH ST 90247

Application / Permit
22010-10000-00451
Plan Check / Job No.
B22LA01716
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* NEW 1-STORY DETACHED ADU PER LAMC 12.22A.33(c)-(d).
Permit Issued
Issued on 9/27/2023
Issuing Office
Current Status
CofO Issued on 4/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/7/2022 APPLICANT
Assigned to Plan Check Engineer 2/15/2022 VIVIAN LAO
Corrections Issued 2/17/2022 VIVIAN LAO
Applicant returned to address corrections 12/12/2022 VIVIAN LAO
Applicant returned to address corrections 2/7/2023 SUNMIN LEE
Applicant returned to address corrections 6/29/2023 SUNMIN LEE
Applicant returned to address corrections 8/25/2023 KEVIN MORALES
Plan Check Approved 9/19/2023 KEVIN MORALES
Issued 9/27/2023 APPLICANT
CofO in Progress 4/9/2025 BEN MOLSTAD
Permit Finaled 4/10/2025 ANSON MAGLASANG
CofO Issued 4/10/2025 ANSON MAGLASANG
Permit Finaled 4/10/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 3/31/2022 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 3/31/2022 ERIK BEASLEY
Low Impact Development Cleared 11/22/2022 ROGELIO CORTES
Sewer availability Cleared 11/23/2022 ANA SORIANO
Roof/Waste drainage to street Cleared 12/12/2022 ANA SORIANO
Miscellaneous Cleared 12/13/2022 ANA SORIANO
Watercourse Cleared 2/13/2023 ANA SORIANO

Contact Information

Contractor The Adu Guys Com Inc; Lic. No.: 1071442-B       ,
Contractor The Adu Guys.Com Inc; Lic. No.: 1071442-B       ,
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/17/2023 Not Ready for Inspection JAMES CHAVEZ
Footing/Foundation/Slab 10/20/2023 Approved JAMES CHAVEZ
Reinforced Masonry Frame 10/31/2023 Partial Approval JAMES CHAVEZ
Masonry Wall/Backfill 11/17/2023 Partial Approval JAMES CHAVEZ
Sewer 11/22/2023 Approved JOHN KLARIN
Deputy Drilled-In Anchors 11/27/2023 Conditional Approval JAMES CHAVEZ
Excavation/Setback/Form/Re-Bar 11/27/2023 Corrections Issued JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 12/8/2023 Corrections Issued JAMES CHAVEZ
Rough-Elec/Plmb/HVAC 1/26/2024 Not Ready for Inspection JAMES CHAVEZ
BUILDING-Rough-Frame 1/31/2024 Conditional Approval JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 1/31/2024 Approved JAMES CHAVEZ
Gas Test 1/31/2024 Approved JAMES CHAVEZ
Green Building Rough 1/31/2024 Approved JAMES CHAVEZ
Rough-Elec/Plmb/HVAC 1/31/2024 Approved JAMES CHAVEZ
Sewer 1/31/2024 Approved JAMES CHAVEZ
Underground Mechanical 1/31/2024 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 2/7/2024 Approved JAMES CHAVEZ
Insulation 2/7/2024 Approved JAMES CHAVEZ
Interior/Exterior Lathing 2/7/2024 Partial Approval JAMES CHAVEZ
Drywall Nailing 2/12/2024 Approved JAMES CHAVEZ
Interior/Exterior Lathing 2/12/2024 Approved JAMES CHAVEZ
Shower Pan 2/12/2024 Approved JAMES CHAVEZ
Service/Power Release 6/10/2024 Approved JAMES CHAVEZ
Final 2/10/2025 Corrections Issued BEN MOLSTAD
Green Building Final 2/10/2025 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Final 2/10/2025 Corrections Issued BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 2/10/2025 SGSOV Not Ready BEN MOLSTAD
Smoke Detectors 2/10/2025 Corrections Issued BEN MOLSTAD
Final 3/27/2025 Corrections Issued BEN MOLSTAD
Green Building Final 3/27/2025 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Final 3/27/2025 Corrections Issued BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 3/27/2025 SGSOV Not Ready BEN MOLSTAD
Smoke Detectors 3/27/2025 Approved BEN MOLSTAD
ELECTRICAL-Final 4/7/2025 Approved BEN MOLSTAD
Final 4/7/2025 OK to Issue CofO BEN MOLSTAD
Green Building Final 4/7/2025 Approved BEN MOLSTAD
HVAC-Final 4/7/2025 Approved BEN MOLSTAD
PLUMBING-Final 4/7/2025 Approved BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 4/7/2025 SGSOV Approved BEN MOLSTAD