1514 W 211TH ST 90501
Certificate Information: 1514 W 211TH ST 90501
- Application / Permit
- 22010-10000-00446
- Plan Check / Job No.
- B22LA01693
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 2-STORY ADU and attached garage : Plancheck per LAMC 12.22 A.33 (c) and (d)
- Permit Issued
- Issued on 2/27/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | SUNMIN LEE |
| Corrections Issued | 3/4/2022 | SUNMIN LEE |
| Quality Review Completed | 3/16/2022 | KEN GILL |
| Building Plans Picked Up | 3/18/2022 | APPLICANT |
| Plan Check Approved | 1/20/2023 | SUNMIN LEE |
| Issued | 2/27/2023 | APPLICANT |
| CofO in Progress | 6/12/2024 | EUGENE CASSIDY |
| Permit Finaled | 7/10/2024 | ANSON MAGLASANG |
| CofO Issued | 7/10/2024 | ANSON MAGLASANG |
| Permit Finaled | 7/10/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 8/1/2022 | ERIK BEASLEY |
| Permit | Cleared | 8/1/2022 | ERIK BEASLEY |
| Low Impact Development | Cleared | 9/9/2022 | SARAH YOUSSEF |
| Hydrant and Access approval | Cleared | 9/18/2022 | JOHN CONNEALLY |
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2022 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 10/31/2022 | ERIK BEASLEY |
| Trees in Parkway | Cleared | 11/3/2022 | ADALBERTO VERA |
| Sewer availability | Cleared | 11/7/2022 | ERIK BEASLEY |
Contact Information
| Contractor | Modern Muse Construction Inc; Lic. No.: 1077027-B | 12352 CORVETTE STREET GARDEN GROVE, CA 92841 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/3/2023 | Corrections Issued | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 4/12/2023 | Corrections Issued | EUGENE CASSIDY |
| Grounding or Bonding | 4/12/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 4/14/2023 | Approved | EUGENE CASSIDY |
| Grounding or Bonding | 4/14/2023 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/25/2023 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 4/25/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 4/25/2023 | Partial Inspection | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 4/25/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2023 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2023 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 5/24/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Service/Power Release | 5/24/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Sewer | 5/24/2023 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 5/24/2023 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2023 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 6/28/2023 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2023 | Conditional Approval | JAMES CHAVEZ |
| HVAC-Rough | 6/28/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Rough | 6/28/2023 | Approved | JAMES CHAVEZ |
| Wood Frame | 6/28/2023 | Approved | JAMES CHAVEZ |
| Insulation | 7/10/2023 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 7/14/2023 | Approved | EUGENE CASSIDY |
| Green Building Rough | 7/14/2023 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 7/14/2023 | Partial Approval | EUGENE CASSIDY |
| Shower Pan | 7/14/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Interior/Exterior Lathing | 8/2/2023 | Approved | EUGENE CASSIDY |
| Shower Pan | 8/2/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 11/13/2023 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 5/22/2024 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 5/22/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 5/22/2024 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 5/22/2024 | Approved | EUGENE CASSIDY |
| Green Building Final | 5/22/2024 | Approved | EUGENE CASSIDY |
| HVAC-Final | 5/22/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Final | 5/22/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 5/22/2024 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 5/22/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 5/22/2024 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 5/22/2024 | Approved | EUGENE CASSIDY |
| Final | 6/7/2024 | OK to Issue CofO | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 6/7/2024 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 6/7/2024 | Not Required | EUGENE CASSIDY |