2841 1/2 E GUIRADO ST 90023
Certificate Information: 2841 1/2 E GUIRADO ST 90023
- Application / Permit
- 22010-10000-00444
- Plan Check / Job No.
- B22LA01689
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW TWO STORY ADU AT REAR OF LOT. REC ROOM AND INCIDENTAL TORAGE AT FIRST FLOOR AND ADU ON SECOND FLOOR. ADU:770SF
- Permit Issued
- Issued on 7/15/2022
- Issuing Office
- Current Status
- Issued on 7/15/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/11/2022 | JOE VO |
| Corrections Issued | 2/12/2022 | JOE VO |
| Quality Review Completed | 2/14/2022 | LIPING TENG |
| Plan Check Approved | 5/25/2022 | JOE VO |
| Issued | 7/15/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/3/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 3/7/2022 | JEANETTE VONG |
| Grading Pre-Inspection | Cleared | 3/9/2022 | KIRK LINKLATER |
| Clean Up Green Up | Cleared | 3/10/2022 | DANIEL CORONADO |
| Low Impact Development | Cleared | 5/9/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 5/11/2022 | JEANETTE VONG |
Contact Information
| Architect | Kadribegovic,, Nerin; Lic. No.: C32104 | 1240 BROOKMERE RD PASADENA, CA 91105 |
| Architect | Kadribegovic,, Nerin; Lic. No.: NA32104 | , |
| Contractor | Jmp Builders Inc; Lic. No.: 745040-B | , |
| Engineer | Garza,, Omar Leonel; Lic. No.: NA5593 | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 8/16/2022 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 8/16/2022 | Approved | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 9/16/2022 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 9/16/2022 | Approved | FREDDIE RIVERA |
| METHANE-Barrier | 9/16/2022 | Approved | FREDDIE RIVERA |
| METHANE-Subgrade | 9/16/2022 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2022 | Partial Approval | BRENDAN MORELLI |
| ELECTRICAL-Rough | 4/3/2023 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 4/3/2023 | Corrections Issued | FREDDIE RIVERA |
| Wood Frame | 4/3/2023 | Partial Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2023 | Partial Approval | FREDDIE RIVERA |
| HVAC-Rough | 6/12/2023 | Corrections Issued | FREDDIE RIVERA |
| Wood Frame | 6/16/2023 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 6/21/2023 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Rough | 6/21/2023 | Partial Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 6/21/2023 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 7/26/2023 | Approved | FREDDIE RIVERA |
| Green Building Rough | 7/26/2023 | Approved | FREDDIE RIVERA |
| METHANE-Rough | 7/26/2023 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 7/26/2023 | Approved | FREDDIE RIVERA |
| Insulation | 8/11/2023 | Approved | JOSH MEISTER |
| Drywall Nailing | 8/24/2023 | Approved | RONNIE MINDANAO |
| Shower Pan | 10/3/2023 | Corrections Issued | FREDDIE RIVERA |
| Shower Pan | 10/6/2023 | Approved | FREDDIE RIVERA |
| Sewer | 3/11/2024 | Approved | FREDDIE RIVERA |
| Underground Mechanical | 3/11/2024 | Partial Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 3/26/2024 | Approved | JUSTIN HAWLEY |
| Pre-Inspection | 3/26/2024 | Approved | JUSTIN HAWLEY |
| Service/Power Release | 4/23/2024 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Final | 5/31/2024 | Corrections Issued | FREDDIE RIVERA |
| Final | 5/31/2024 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 5/31/2024 | Approved | FREDDIE RIVERA |
| HVAC-Final | 5/31/2024 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Final | 5/31/2024 | Corrections Issued | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 5/31/2024 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 5/31/2024 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 5/31/2024 | Approved | FREDDIE RIVERA |
| Final | 7/3/2024 | Corrections Issued | FREDDIE RIVERA |
| Service/Power Release | 7/3/2024 | Approved | FREDDIE RIVERA |