4440-4440 1/2 E TURQUOISE ST 90032
Certificate Information: 4440-4440 1/2 E TURQUOISE ST 90032
- Application / Permit
- 22010-10000-00440
- Plan Check / Job No.
- B22LA01664
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3-STORY DUPLEX WITH ATTACHED 4-CAR GARAGE (REAR BUILDING).
- Permit Issued
- Issued on 5/3/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/31/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2022 | VU NGUYEN |
| Corrections Issued | 2/15/2022 | VU NGUYEN |
| Quality Review Completed | 2/17/2022 | EUGENE BARBEAU |
| Building Plans Picked Up | 2/22/2022 | APPLICANT |
| Plan Check Approved | 5/3/2022 | VU NGUYEN |
| Issued | 5/3/2022 | APPLICANT |
| CofO in Progress | 3/1/2024 | OSVALDO PARAMO |
| Permit Finaled | 3/8/2024 | DEROLD HAUFF |
| CofO Issued | 3/8/2024 | DEROLD HAUFF |
| Permit Finaled | 3/8/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 3/23/2022 | VU NGUYEN |
| Address approval | Cleared | 3/25/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/25/2022 | TREVOR QUAN |
| Highway dedication | Cleared | 3/25/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 3/25/2022 | TREVOR QUAN |
| Low Impact Development | Cleared | 4/14/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 4/18/2022 | TREVOR QUAN |
| Frnt yard landscape/Water mgmt | Cleared | 4/27/2022 | DANIEL CORONADO |
| Hydrant and Access approval | Cleared | 4/27/2022 | KURT CORRAL |
| GPI Written Notices | Cleared | 5/3/2022 | VU NGUYEN |
| Grading Pre-Inspection | Cleared | 5/3/2022 | VU NGUYEN |
Contact Information
| Contractor | Builder Point Construction; Lic. No.: 1059885-B | 11445 PARAMOUNT BLVD SUITE H DOWNEY, CA 90241 |
| Engineer | Desai,, Anil T; Lic. No.: C24653 | 1530 VIA LOS COYOTES LA HABRA, CA 90631 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/6/2022 | Partial Inspection | OSVALDO PARAMO |
| Underground Mechanical | 9/12/2022 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 9/27/2022 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2022 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2022 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2023 | Partial Approval | OSVALDO PARAMO |
| HVAC-Rough | 2/7/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 2/8/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Rough | 2/22/2023 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 2/22/2023 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 2/22/2023 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Rough | 3/1/2023 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 3/3/2023 | Corrections Issued | OSVALDO PARAMO |
| Green Building Rough | 3/3/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 3/3/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 3/20/2023 | Approved | OSVALDO PARAMO |
| Green Building Rough | 3/20/2023 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 3/20/2023 | Approved | OSVALDO PARAMO |
| Insulation | 3/29/2023 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 3/29/2023 | Partial Approval | OSVALDO PARAMO |
| Drywall Nailing | 4/17/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 4/17/2023 | Partial Approval | BRENDAN MORELLI |
| Verify Rec and Parks Fee Memo | 8/10/2023 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Final | 8/23/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Final | 8/28/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| HVAC-Final | 8/28/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 10/12/2023 | Conditional Approval | OSVALDO PARAMO |
| Gas Test | 10/12/2023 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 10/12/2023 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 10/18/2023 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Final | 1/19/2024 | Approved | OSVALDO PARAMO |
| Service/Power Release | 1/19/2024 | Approved | OSVALDO PARAMO |
| HVAC-Final | 1/22/2024 | Approved | OSVALDO PARAMO |
| Final | 2/15/2024 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 2/15/2024 | Approved | OSVALDO PARAMO |
| Green Building Final | 2/15/2024 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 2/15/2024 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 2/15/2024 | Approved | OSVALDO PARAMO |
| Final | 2/20/2024 | OK to Issue CofO | OSVALDO PARAMO |