1193 E 53RD ST 90011

Certificate Information: 1193 E 53RD ST 90011

Application / Permit
22010-10000-00431
Plan Check / Job No.
B22LA01636
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU AT REAR OF LOT, 1195 SQ FT PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 4/19/2023
Issuing Office
Metro
Current Status
CofO Issued on 9/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/2/2022 APPLICANT
Assigned to Plan Check Engineer 2/11/2022 DANIEL SANJUAN
Corrections Issued 2/11/2022 DANIEL SANJUAN
Applicant returned to address corrections 3/29/2022 JESSE JIMENEZ
Applicant returned to address corrections 7/25/2022 JOSEPH RAFOLS
Applicant returned to address corrections 8/11/2022 ZAW HAN
Applicant returned to address corrections 11/4/2022 MINA HABILI
Plan Check Approved 4/19/2023 DANIEL SMILEY
Issued 4/19/2023 APPLICANT
Permit Finaled 9/11/2025 DEROLD HAUFF
CofO Issued 9/11/2025 DEROLD HAUFF
Permit Finaled 9/11/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/25/2022 CINDY QI
Hydrant and Access approval Cleared 7/25/2022 GILBERT URREA
Eng Process Fee Ord 176,300 Cleared 8/8/2022 CINDY QI
Sewer availability Cleared 8/8/2022 CINDY QI
Low Impact Development Cleared 11/3/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 11/4/2022 CHRISTOPHER ROCHA
Construction near power lines Cleared 2/28/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/30/2023 Partial Approval BRENDAN MORELLI
PLUMBING-Rough 5/30/2023 Partial Approval BRENDAN MORELLI
Footing/Foundation/Slab 6/5/2023 Approved BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 7/19/2023 Corrections Issued BRENDAN MORELLI
Deputy Wood Construction 7/21/2023 Conditional Approval BRENDAN MORELLI
BUILDING-Rough-Frame 7/25/2023 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/25/2023 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 7/25/2023 Not Ready for Inspection ALEJANDRO DE ARTOLA
Pre-Inspection 7/25/2023 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/31/2023 Partial Approval ALEJANDRO DE ARTOLA
Sewer 9/12/2023 Approved ALEJANDRO DE ARTOLA
Pre-Inspection 9/18/2023 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 9/22/2023 Partial Approval ALEJANDRO DE ARTOLA
Rough-Elec/Plmb/HVAC 10/4/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 10/5/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 10/10/2023 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/30/2023 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 11/22/2023 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/22/2023 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/14/2023 Partial Approval ALEJANDRO DE ARTOLA
Insulation 2/26/2024 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 2/27/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 2/27/2024 Corrections Issued ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 2/27/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 4/3/2024 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/12/2024 Approved ALEJANDRO DE ARTOLA
Green Building Rough 4/12/2024 Approved ALEJANDRO DE ARTOLA
Rough-Elec/Plmb/HVAC 4/12/2024 Approved ALEJANDRO DE ARTOLA
Insulation 6/4/2024 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 7/10/2024 Approved ALEJANDRO DE ARTOLA
Service/Power Release 5/15/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 7/3/2025 Corrections Issued ENRIQUE MIRELES
Green Building Final 7/3/2025 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 7/3/2025 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 7/3/2025 Not Ready for Inspection ENRIQUE MIRELES
Smoke Detectors 7/3/2025 Approved ENRIQUE MIRELES
Final 8/14/2025 No Access for Inspection LUIS CASTRO
Service/Power Release 8/14/2025 No Access for Inspection LUIS CASTRO
Final 8/18/2025 Corrections Issued BARRY HACHE
Service/Power Release 8/18/2025 Not Ready for Inspection BARRY HACHE
Final 8/26/2025 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 8/26/2025 SGSOV Approved BARRY HACHE
Final 8/27/2025 Corrections Issued BARRY HACHE
Service/Power Release 8/27/2025 Not Ready for Inspection BARRY HACHE
Final 9/5/2025 Corrections Issued BARRY HACHE
Service/Power Release 9/5/2025 Not Ready for Inspection BARRY HACHE
Final 9/8/2025 Conditional Approval BARRY HACHE
Service/Power Release 9/8/2025 Approved BARRY HACHE