20455 W BIRMINGHAM WAY 91326
Certificate Information: 20455 W BIRMINGHAM WAY 91326
- Application / Permit
- 22010-10000-00428
- Plan Check / Job No.
- B22LA01595
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- (N) DETACEHD PATIO COVER
- Permit Issued
- Issued on 5/12/2022
- Issuing Office
- Metro
- Current Status
- CofO in Progress on 9/10/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | DANIEL YIP |
| Corrections Issued | 2/22/2022 | DANIEL YIP |
| Quality Review Completed | 2/24/2022 | KEN GILL |
| Building Plans Picked Up | 3/2/2022 | APPLICANT |
| Plan Check Approved | 5/9/2022 | DANIEL YIP |
| Issued | 5/12/2022 | APPLICANT |
| CofO in Progress | 2/16/2023 | DAVID SCANTLIN |
| No Progress | 9/10/2025 | HENRY KIM |
| CofO in Progress | 9/10/2025 | HENRY KIM |
Permit Application Clearance Information
| "T" removal | Cleared | 3/10/2022 | DANIEL CORONADO |
| Specific Plan | Cleared | 3/10/2022 | DANIEL CORONADO |
| ZA Case | Cleared | 3/10/2022 | DANIEL CORONADO |
| ZA Case | Cleared | 3/10/2022 | DANIEL CORONADO |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 4/4/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 4/4/2022 | CARLOS AGUILERA |
| GPI Written Notices | Cleared | 5/9/2022 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 5/9/2022 | DANIEL YIP |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Karapetian,, Arbi; Lic. No.: C79953 | 21520 BURBANK BLVD APT 219 WOODLAND HILLS, CA 91367 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/6/2022 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 2/13/2023 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 2/13/2023 | Approved | DAVID SCANTLIN |
| Final | 2/13/2023 | Corrections Issued | DAVID SCANTLIN |
| PLUMBING-Final | 2/13/2023 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 2/13/2023 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 2/15/2023 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 2/15/2023 | Approved | DAVID SCANTLIN |
| Final | 2/15/2023 | OK to Issue CofO | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 2/15/2023 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 2/15/2023 | Approved | DAVID SCANTLIN |
| Smoke Detectors | 2/15/2023 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 2/15/2023 | Approved | DAVID SCANTLIN |
| Special/Order Compliance | 4/24/2025 | Corrections Issued | DAVID SCANTLIN |