3701 S NORTON AVE 90018

Certificate Information: 3701 S NORTON AVE 90018

Application / Permit
22010-10000-00425
Plan Check / Job No.
B22LA01551
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED MASTER BEDROOM AND BATHROOM ADDITION TO REAR OF (E) SFD. INCLUDES REAR BEDROOM, DINING AND KITCHEN REMODEL.
Permit Issued
Issued on 3/10/2022
Issuing Office
Current Status
CofO Issued on 1/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2022 APPLICANT
Assigned to Plan Check Engineer 2/8/2022 LAWRENCE QUIRANTE
Corrections Issued 2/8/2022 LAWRENCE QUIRANTE
Plan Check Approved 3/9/2022 SHANGQIN XIE
Issued 3/10/2022 APPLICANT
Building Plans Picked Up 3/11/2022 APPLICANT
CofO in Progress 12/16/2022 ANTHONY EGSON
No Progress 1/20/2023 ANTHONY EGSON
CofO in Progress 1/20/2023 ANTHONY EGSON
Permit Finaled 1/24/2023 RONALD MYRICK
CofO Issued 1/24/2023 RONALD MYRICK
Permit Finaled 1/24/2023 RONALD MYRICK

Permit Application Clearance Information

Sewer availability Cleared 2/9/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 2/11/2022 TREVOR QUAN
Low Impact Development Cleared 3/3/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 3/7/2022 TREVOR QUAN

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/1/2022 No Access for Inspection ANTHONY EGSON
Footing/Foundation/Slab 4/15/2022 Approved ANTHONY EGSON
BUILDING-Rough-Frame 5/16/2022 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 5/16/2022 Approved ANTHONY EGSON
Green Building Rough 5/16/2022 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 5/16/2022 Corrections Issued ANTHONY EGSON
Insulation 5/18/2022 Approved ANTHONY EGSON
PLUMBING-Rough 5/18/2022 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 5/19/2022 Approved ANTHONY EGSON
ELECTRICAL-Rough 6/16/2022 Corrections Issued HORACE FULTZ
HVAC-Rough 6/16/2022 Approved HORACE FULTZ
PLUMBING-Rough 6/16/2022 Approved HORACE FULTZ
BUILDING-Rough-Frame 6/30/2022 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 6/30/2022 Approved ANTHONY EGSON
Green Building Rough 6/30/2022 Not Ready for Inspection ANTHONY EGSON
Interior/Exterior Lathing 6/30/2022 Approved ANTHONY EGSON
BUILDING-Rough-Frame 7/11/2022 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 7/11/2022 Approved ANTHONY EGSON
Green Building Rough 7/11/2022 Not Ready for Inspection ANTHONY EGSON
Interior/Exterior Lathing 7/11/2022 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 7/15/2022 Partial Approval ANTHONY EGSON
Green Building Rough 7/15/2022 Approved ANTHONY EGSON
Insulation 7/15/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 7/15/2022 Approved ANTHONY EGSON
Drywall Nailing 7/21/2022 Approved ANTHONY EGSON
BUILDING-Rough-Frame 10/25/2022 Approved ANTHONY EGSON
ELECTRICAL-Final 10/25/2022 Corrections Issued ANTHONY EGSON
Final 10/25/2022 Not Ready for Inspection ANTHONY EGSON
Green Building Final 10/25/2022 Corrections Issued ANTHONY EGSON
HVAC-Final 10/25/2022 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Final 10/25/2022 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 10/25/2022 SGSOV Not Ready ANTHONY EGSON
Smoke Detectors 10/25/2022 Approved ANTHONY EGSON
ELECTRICAL-Final 11/18/2022 No Access for Inspection ANTHONY EGSON
HVAC-Final 11/18/2022 Corrections Issued ANTHONY EGSON
PLUMBING-Final 11/18/2022 Corrections Issued ANTHONY EGSON
ELECTRICAL-Final 11/30/2022 Corrections Issued ANTHONY EGSON
Final 11/30/2022 Not Ready for Inspection ANTHONY EGSON
Green Building Final 11/30/2022 Approved ANTHONY EGSON
HVAC-Final 11/30/2022 Corrections Issued ANTHONY EGSON
PLUMBING-Final 11/30/2022 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 11/30/2022 SGSOV Approved ANTHONY EGSON
ELECTRICAL-Final 12/12/2022 Corrections Issued ANTHONY EGSON
HVAC-Final 12/12/2022 Approved ANTHONY EGSON
ELECTRICAL-Final 12/15/2022 Approved ANTHONY EGSON
Final 12/15/2022 OK to Issue CofO ANTHONY EGSON
HVAC-Final 12/15/2022 Approved ANTHONY EGSON
Final 1/19/2023 OK to Issue CofO ANTHONY EGSON
Service/Power Release 1/20/2023 Approved ANTHONY EGSON