667 S MCCADDEN PL 90005
Certificate Information: 667 S MCCADDEN PL 90005
- Application / Permit
- 22010-10000-00401
- Plan Check / Job No.
- B22LA01435
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan Addition and conversion to ADU from Garage
- Permit Issued
- Issued on 5/22/2023
- Issuing Office
- Current Status
- CofO Issued on 10/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/31/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/1/2022 | ARSALAN SHABESTARI |
| Corrections Issued | 2/1/2022 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 6/23/2022 | ARSALAN SHABESTARI |
| Plan Check Approved | 10/26/2022 | ARSALAN SHABESTARI |
| Issued | 5/22/2023 | APPLICANT |
| CofO in Progress | 8/27/2024 | RONNIE MINDANAO |
| Permit Finaled | 10/2/2024 | RUBEN SALAS |
| CofO Issued | 10/2/2024 | RUBEN SALAS |
| Permit Finaled | 10/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/23/2022 | JEANIE LAM |
| CPC | Cleared | 3/23/2022 | ARSALAN SHABESTARI |
| CPC | Cleared | 3/23/2022 | ARSALAN SHABESTARI |
| Miscellaneous | Cleared | 3/23/2022 | ARSALAN SHABESTARI |
| Miscellaneous | Cleared | 3/23/2022 | ARSALAN SHABESTARI |
| Roof/Waste drainage to street | Cleared | 3/23/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/12/2022 | JEANIE LAM |
| Sewer availability | Cleared | 4/12/2022 | JEANIE LAM |
| Specific Plan | Cleared | 4/18/2022 | ADRINEH MELKONIAN |
| Construction near power lines | Cleared | 9/7/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/7/2022 | RIDWAN HARDY |
| HPOZ | Cleared | 10/17/2022 | DEEPEAKA DHALIWAL |
Contact Information
| Architect | Song,, Byung K; Lic. No.: NA25500 | , |
| Contractor | Yoo Sung Kun; Lic. No.: 1001698-B | , |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/31/2023 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 7/25/2023 | Partial Approval | SCOTT FINNILA |
| Sewer | 7/25/2023 | Approved | SCOTT FINNILA |
| Deputy Drilled-In Anchors | 7/28/2023 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 8/3/2023 | Corrections Issued | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 8/8/2023 | Approved | ALIZAH MAYAGOITIA |
| Wood Frame | 10/19/2023 | Corrections Issued | RICHARD DOCKUS |
| Deputy Drilled-In Anchors | 11/14/2023 | Partial Approval | SCOTT FINNILA |
| Wood Frame | 11/17/2023 | Corrections Issued | RICHARD DOCKUS |
| Deputy Drilled-In Anchors | 11/28/2023 | Conditional Approval | RICHARD DOCKUS |
| Deputy Steel/Welding | 11/28/2023 | Conditional Approval | RICHARD DOCKUS |
| ELECTRICAL-Rough | 12/19/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 12/19/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Wood Frame | 12/19/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 12/21/2023 | Corrections Issued | JEFFREY MEAD |
| Wood Frame | 12/21/2023 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Rough | 12/29/2023 | Approved | RICHARD DOCKUS |
| Wood Frame | 12/29/2023 | Partial Approval | RICHARD DOCKUS |
| Interior/Exterior Lathing | 1/4/2024 | Partial Approval | RICHARD DOCKUS |
| PLUMBING-Rough | 1/16/2024 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 1/31/2024 | Approved | RICHARD DOCKUS |
| Wood Frame | 2/7/2024 | Approved | AMIR NAZARIAN |
| Insulation | 2/12/2024 | Corrections Issued | RICHARD DOCKUS |
| Insulation | 2/15/2024 | Approved | AMIR NAZARIAN |
| Drywall Nailing | 2/22/2024 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 6/14/2024 | SGSOV Not Ready | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 6/20/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 6/20/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 6/20/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Final | 6/20/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 6/20/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Barrier | 6/20/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Final | 6/20/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Rough | 6/20/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 6/20/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 6/20/2024 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 6/20/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 7/11/2024 | Approved | RONNIE MINDANAO |
| Final | 7/11/2024 | Corrections Issued | RONNIE MINDANAO |
| Footing/Foundation/Slab | 7/11/2024 | Approved | RONNIE MINDANAO |
| Green Building Final | 7/11/2024 | Approved | RONNIE MINDANAO |
| Green Building Rough | 7/11/2024 | Approved | RONNIE MINDANAO |
| METHANE-Barrier | 7/11/2024 | Approved | RONNIE MINDANAO |
| METHANE-Final | 7/11/2024 | Approved | RONNIE MINDANAO |
| METHANE-Rough | 7/11/2024 | Approved | RONNIE MINDANAO |
| METHANE-Subgrade | 7/11/2024 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 7/11/2024 | SGSOV Not Ready | RONNIE MINDANAO |
| Smoke Detectors | 7/11/2024 | Approved | RONNIE MINDANAO |
| Final | 7/24/2024 | Corrections Issued | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 7/24/2024 | SGSOV Not Ready | RONNIE MINDANAO |
| Final | 8/6/2024 | Corrections Issued | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 8/6/2024 | SGSOV No Gas | RONNIE MINDANAO |
| ELECTRICAL-Final | 8/26/2024 | Approved | RONNIE MINDANAO |
| Final | 8/26/2024 | OK to Issue CofO | RONNIE MINDANAO |
| HVAC-Final | 8/26/2024 | Approved | RONNIE MINDANAO |
| PLUMBING-Final | 8/26/2024 | Approved | RONNIE MINDANAO |