235-235 1/2 W 50TH ST 90037
Certificate Information: 235-235 1/2 W 50TH ST 90037
- Application / Permit
- 22010-10000-00385
- Plan Check / Job No.
- B22LA01356
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY DUPLEX WITH ATTACHED 1-CAR GARAGE AT FRONT AND 2-CAR GARAGE AT REAR.
- Permit Issued
- Issued on 5/6/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/3/2022 | ERIC WONG |
| Corrections Issued | 2/5/2022 | ERIC WONG |
| Quality Review Completed | 2/9/2022 | PETER KIM |
| Building Plans Picked Up | 2/16/2022 | APPLICANT |
| Applicant returned to address corrections | 4/27/2022 | ERIC WONG |
| Plan Check Approved | 4/29/2022 | ERIC WONG |
| Issued | 5/6/2022 | APPLICANT |
| CofO in Progress | 1/6/2023 | ALEJANDRO DE ARTOLA |
| CofO Issued | 1/13/2023 | DEROLD HAUFF |
| Permit Finaled | 1/13/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/25/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 2/25/2022 | CHRISTOPHER ROCHA |
| Low Impact Development | Cleared | 3/3/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 3/9/2022 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 4/8/2022 | GILBERT URREA |
| Green Code | Cleared | 4/27/2022 | ERIC WONG |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/1/2022 | Approved | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 6/1/2022 | Approved | JOAQUIN GREENOUGH |
| Deputy Reinf. Concrete | 6/3/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 6/29/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Sewer | 6/29/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Underground Mechanical | 6/29/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Wood Frame | 6/29/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Underground Mechanical | 6/30/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Sewer | 7/1/2022 | Approved | JOAQUIN GREENOUGH |
| Underground Mechanical | 7/1/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Insulation | 7/5/2022 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 7/6/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2022 | Approved | HORACE FULTZ |
| Deputy Wood Construction | 8/17/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2022 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 8/19/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 8/19/2022 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 8/23/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 8/23/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 8/23/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| MERV13>=Rough | 8/23/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 8/23/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 8/31/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 8/31/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 8/31/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| MERV13>=Rough | 8/31/2022 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 8/31/2022 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 9/15/2022 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 9/15/2022 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 9/15/2022 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 9/21/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 9/21/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 10/6/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/11/2022 | Approved | SHAVONNE ESPINOZA |
| Interior/Exterior Lathing | 10/12/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/21/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/30/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/30/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 12/30/2022 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 12/30/2022 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 12/30/2022 | Approved | ALEJANDRO DE ARTOLA |
| MERV13>=Final | 12/30/2022 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 12/30/2022 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 12/30/2022 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 12/30/2022 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 12/30/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 1/5/2023 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Service/Power Release | 1/5/2023 | Approved | ALEJANDRO DE ARTOLA |