17549-17551 W BLYTHE ST 91325

Certificate Information: 17549-17551 W BLYTHE ST 91325

Application / Permit
22010-10000-00384
Plan Check / Job No.
B22LA01354
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 1-STORY ADDITION with attached A.D.U. TO EXISTING ONE STORY SINGLE FAMILY DEWLLING AT REAR OF LOT. Attached ADU per Ordinance, LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 10/14/2022
Issuing Office
Valley
Current Status
CofO Issued on 10/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/26/2022 APPLICANT
Assigned to Plan Check Engineer 2/3/2022 LAWRENCE QUIRANTE
Corrections Issued 2/4/2022 LAWRENCE QUIRANTE
Applicant returned to address corrections 2/26/2022 AUNG SOE
Building Plans Picked Up 3/3/2022 APPLICANT
Plan Check Approved 7/29/2022 MINA HABILI
Issued 10/14/2022 APPLICANT
CofO in Progress 10/10/2023 DAVID ANDERSON
Permit Finaled 10/23/2023 RUBEN SALAS
CofO Issued 10/23/2023 RUBEN SALAS
Permit Finaled 10/23/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/22/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 2/25/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 2/25/2022 DAGOVERTO GUERRERO
Miscellaneous Cleared 5/31/2022 DALIA MOKAYED
Low Impact Development Cleared 6/10/2022 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 6/10/2022 DAGOVERTO GUERRERO
Construction near power lines Cleared 7/27/2022 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Arakelyan,, Aram; Lic. No.: C82796 145 S GLENOAKS BI 328      BURBANK, CA 91502

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/18/2022 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 12/6/2022 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 12/29/2022 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 2/7/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 2/7/2023 Corrections Issued RAUL OLAGI
HVAC-Rough 2/7/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 2/7/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 3/3/2023 Corrections Issued RAUL OLAGI
HVAC-Rough 3/3/2023 Corrections Issued RAUL OLAGI
Deputy Drilled-In Anchors 4/6/2023 Conditional Approval RAUL OLAGI
ELECTRICAL-Rough 4/13/2023 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/13/2023 Approved RAUL OLAGI
HVAC-Rough 4/13/2023 Approved RAUL OLAGI
Special/Order Compliance 4/13/2023 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 4/27/2023 Corrections Issued RAUL OLAGI
Insulation 4/27/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 4/27/2023 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 5/5/2023 Approved RAUL OLAGI
Drywall Nailing 5/5/2023 Approved RAUL OLAGI
Green Building Rough 5/5/2023 Approved RAUL OLAGI
PLUMBING-Rough 5/5/2023 Approved RAUL OLAGI
Shower Pan 5/31/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 6/5/2023 Approved RAUL OLAGI
Final 9/8/2023 Corrections Issued MISAEL ESPARZA
Green Building Final 9/8/2023 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/8/2023 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 9/8/2023 Corrections Issued MISAEL ESPARZA
Final 10/6/2023 OK to Issue CofO DAVID ANDERSON
Green Building Final 10/6/2023 Approved DAVID ANDERSON
Smoke Detectors 10/6/2023 Approved DAVID ANDERSON