826-828 E 88TH PL 90002
Certificate Information: 826-828 E 88TH PL 90002
- Application / Permit
- 22010-10000-00375
- Plan Check / Job No.
- B22LA01317
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2 STORY DUPLEX WITH ATTACHED 1 CAR GARAGE AT FRONT AND 2 CAR GARAGE AT REAR.
- Permit Issued
- Issued on 7/19/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/3/2022 | CRYSTEL MAALOUF |
| Corrections Issued | 2/8/2022 | CRYSTEL MAALOUF |
| Quality Review Completed | 2/9/2022 | SAI KHUM |
| Building Plans Picked Up | 2/14/2022 | APPLICANT |
| Plan Check Approved | 4/20/2022 | CRYSTEL MAALOUF |
| Issued | 7/19/2022 | APPLICANT |
| CofO in Progress | 1/6/2023 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 1/13/2023 | DEROLD HAUFF |
| CofO Issued | 1/13/2023 | DEROLD HAUFF |
| Permit Finaled | 1/13/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/2/2022 | CHRISTOPHER ROCHA |
| Permit | Cleared | 3/2/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 3/3/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 3/18/2022 | CHRISTOPHER ROCHA |
| Low Impact Development | Cleared | 3/23/2022 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 3/24/2022 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 4/5/2022 | LAURINDA MEADE |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/12/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 9/2/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Sewer | 9/2/2022 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 9/2/2022 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 9/7/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2022 | Conditional Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/19/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 10/19/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/20/2022 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 10/20/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/25/2022 | Approved | LILIANA PORTILLO |
| Green Building Rough | 10/25/2022 | Approved | LILIANA PORTILLO |
| Insulation | 10/25/2022 | Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 10/25/2022 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 11/2/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 11/2/2022 | Partial Approval | LILIANA PORTILLO |
| Interior/Exterior Lathing | 11/15/2022 | No Access for Inspection | LILIANA PORTILLO |
| Interior/Exterior Lathing | 11/28/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 12/28/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/28/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 12/28/2022 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 12/28/2022 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 12/28/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 12/28/2022 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 12/28/2022 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 12/28/2022 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 12/28/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/30/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 12/30/2022 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 12/30/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 1/5/2023 | OK to Issue CofO | ALEJANDRO DE ARTOLA |