25112 S BELLE PORTE AVE 90710

Certificate Information: 25112 S BELLE PORTE AVE 90710

Application / Permit
22010-10000-00362
Plan Check / Job No.
B22LA01281
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. 2-story Accessory Dwelling Unit addition to existing 1-story detached garage per City Ordinance 12.22 A.33 (c)-(d).
Permit Issued
Issued on 1/8/2023
Issuing Office
Current Status
CofO Issued on 3/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/4/2022 APPLICANT
Assigned to Plan Check Engineer 3/3/2022 TU HUA
Corrections Issued 3/10/2022 TU HUA
Quality Review Completed 3/11/2022 SAI KHUM
Plan Check Approved 12/5/2022 TU HUA
Issued 1/8/2023 APPLICANT
CofO in Progress 3/12/2024 EUGENE CASSIDY
Permit Finaled 3/12/2024 ANSON MAGLASANG
CofO Issued 3/12/2024 ANSON MAGLASANG
Permit Finaled 3/12/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 3/14/2022 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 3/15/2022 JOSE HERNANDEZ
Sewer availability Cleared 3/30/2022 JOSE HERNANDEZ
Low Impact Development Cleared 7/27/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 8/10/2022 HUGO LOPEZ

Contact Information

Contractor Next Generation Builders; Lic. No.: 1069728-B       ,
Contractor Polymath Development Group Inc; Lic. No.: 1069728-B       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/1/2023 Approved EUGENE CASSIDY
Deputy Methane Barrier 2/22/2023 Partial Approval EUGENE CASSIDY
METHANE-Subgrade 3/20/2023 Partial Approval EUGENE CASSIDY
Deputy Methane Barrier 4/5/2023 Partial Approval EUGENE CASSIDY
Deputy Drilled-In Anchors 4/14/2023 Approved EUGENE CASSIDY
Footing/Foundation/Slab 4/14/2023 Corrections Issued EUGENE CASSIDY
METHANE-Barrier 4/14/2023 Approved EUGENE CASSIDY
METHANE-Subgrade 4/14/2023 Approved EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 4/21/2023 Approved EUGENE CASSIDY
Footing/Foundation/Slab 4/21/2023 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 5/5/2023 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 8/1/2023 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 8/11/2023 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 8/11/2023 Corrections Issued EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 8/11/2023 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 8/11/2023 Not Ready for Inspection EUGENE CASSIDY
HVAC-Rough 8/11/2023 Approved EUGENE CASSIDY
METHANE-Rough 8/11/2023 Approved EUGENE CASSIDY
PLUMBING-Rough 8/11/2023 Approved EUGENE CASSIDY
Deputy Wood Construction 8/16/2023 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 9/13/2023 Approved EUGENE CASSIDY
ELECTRICAL-Rough 9/13/2023 Approved EUGENE CASSIDY
Green Building Rough 9/13/2023 Approved EUGENE CASSIDY
Insulation 9/13/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 9/13/2023 Partial Approval EUGENE CASSIDY
Drywall Nailing 9/22/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 10/2/2023 Approved EUGENE CASSIDY
Shower Pan 10/2/2023 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 12/28/2023 SGSOV Not Ready EUGENE CASSIDY
ELECTRICAL-Final 2/27/2024 Not Ready for Inspection EUGENE CASSIDY
Final 2/27/2024 Corrections Issued EUGENE CASSIDY
Green Building Final 2/27/2024 Approved EUGENE CASSIDY
HVAC-Final 2/27/2024 Approved EUGENE CASSIDY
PLUMBING-Final 2/27/2024 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 2/27/2024 SGSOV Approved EUGENE CASSIDY
Service/Power Release 2/27/2024 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 2/27/2024 Approved EUGENE CASSIDY
ELECTRICAL-Final 3/11/2024 Approved EUGENE CASSIDY
Final 3/11/2024 OK to Issue CofO EUGENE CASSIDY