866-868 W 29TH PL 90731

Certificate Information: 866-868 W 29TH PL 90731

Application / Permit
22010-10000-00354
Plan Check / Job No.
B22LA01254
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2 NEW ATTACHED ACCESSORY DWELLING UNIT PER ORDINANCE
Permit Issued
Issued on 2/14/2024
Issuing Office
Metro
Current Status
Issued on 2/14/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/3/2022 APPLICANT
Assigned to Plan Check Engineer 2/10/2022 VU NGUYEN
Corrections Issued 2/15/2022 VU NGUYEN
Quality Review Completed 2/17/2022 EUGENE BARBEAU
Building Plans Picked Up 2/22/2022 APPLICANT
Plan Check Approved 12/4/2023 VU NGUYEN
Issued 2/14/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/14/2022 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 6/3/2022 ERIK BEASLEY
Sewer availability Cleared 6/3/2022 ERIK BEASLEY
Grading Pre-Inspection Cleared 9/12/2022 KIRK LINKLATER
Low Impact Development Cleared 2/14/2023 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 2/27/2023 ANA SORIANO
Coastal Zone Cleared 11/21/2023 DAVID URITA
Coastal Zone Cleared 11/21/2023 DAVID URITA
GPI Written Notices Cleared 12/4/2023 VU NGUYEN

Contact Information

Contractor Choe Craig; Lic. No.: 867838-B 3183 WILSHIRE BLVD   196 - E33    LOS ANGELES, CA 90010
Engineer Alexander,, Andy; Lic. No.: C84086 1615 GRAMERCY AVE      TORRANCE, CA 90501

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/25/2024 Partial Approval JAMES CHAVEZ
Special/Order Compliance 4/25/2024 Partial Inspection ANSON MAGLASANG
Footing/Foundation/Slab 6/7/2024 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 6/25/2024 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 7/1/2024 Approved ANSON MAGLASANG
BUILDING-Rough-Frame 9/16/2024 Not Ready for Inspection BEN MOLSTAD
Green Building Rough 9/16/2024 Not Ready for Inspection BEN MOLSTAD
Verify Sprinkler Sign Off 9/16/2024 Not Ready for Inspection BEN MOLSTAD
Deputy Wood Construction 9/18/2024 Conditional Approval ANSON MAGLASANG
ELECTRICAL-Rough 9/27/2024 Approved JOSEPH MCGARRY
PLUMBING-Rough 9/27/2024 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 10/3/2024 Approved JOSEPH MCGARRY
Green Building Rough 10/3/2024 Not Ready for Inspection JOSEPH MCGARRY
Verify Sprinkler Sign Off 10/3/2024 Approved JOSEPH MCGARRY
HVAC-Rough 10/25/2024 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 10/29/2024 Corrections Issued JOSEPH MCGARRY
Green Building Rough 10/29/2024 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 10/29/2024 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 11/14/2024 Approved JOSEPH MCGARRY
Insulation 11/14/2024 Corrections Issued JOSEPH MCGARRY
Drywall Nailing 11/26/2024 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 11/26/2024 Partial Approval JOSEPH MCGARRY
Green Building Final 12/6/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 12/6/2024 Approved EUGENE CASSIDY
Sewer 2/25/2025 Approved JOSEPH MCGARRY
ELECTRICAL-Final 4/3/2025 No Access for Inspection JOSEPH MCGARRY
HVAC-Final 4/3/2025 No Access for Inspection JOSEPH MCGARRY
PLUMBING-Final 4/3/2025 No Access for Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 5/6/2025 Approved JOSEPH MCGARRY