8250 N SEPULVEDA BLVD 91402

Certificate Information: 8250 N SEPULVEDA BLVD 91402

Application / Permit
22010-10000-00330
Plan Check / Job No.
B22LA01141
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(9) Gasoline Station
Work Description
NEW FUEL CANOPY. 2 OF 6
Permit Issued
Issued on 1/12/2024
Issuing Office
Metro
Current Status
CofO Issued on 3/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2022 APPLICANT
Assigned to Plan Check Engineer 2/3/2022 TSE MING HUANG
Plans on Hold 2/7/2022 ALBERT SERVIN
Green Plans Picked Up 2/10/2022 APPLICANT
Hold Released 2/13/2022 ALBERT SERVIN
Corrections Issued 2/14/2022 ALBERT SERVIN
Quality Review Completed 2/16/2022 KEN GILL
Building Plans Picked Up 2/24/2022 APPLICANT
Applicant returned to address corrections 3/9/2022 ALBERT SERVIN
Disabled Access Plans Picked Up 3/17/2022 APPLICANT
Applicant returned to address corrections 10/24/2022 ALBERT SERVIN
Applicant returned to address corrections 11/1/2022 ALBERT SERVIN
Applicant returned to address corrections 11/4/2022 ALBERT SERVIN
Applicant returned to address corrections 12/2/2022 ALBERT SERVIN
Applicant returned to address corrections 5/19/2023 ALBERT SERVIN
Plan Check Approved 5/19/2023 ALBERT SERVIN
Plan Check Approved 5/19/2023 TSE MING HUANG
Issued 1/12/2024 APPLICANT
CofO in Progress 3/7/2025 DANNY RODRIGUEZ
Permit Finaled 3/20/2025 RICKEY JACKSON
CofO Issued 3/20/2025 RICKEY JACKSON
Permit Finaled 3/20/2025 RICKEY JACKSON

Permit Application Clearance Information

Green Code Cleared 10/27/2022 AARON COSTA
DAS Clearance Cleared 11/30/2022 ALBERT SERVIN
"Q" conditions Cleared 12/9/2022 DANIEL CORONADO
Comm Cor/Mini-Mall Cleared 12/9/2022 DANIEL CORONADO
Comm Cor/Mini-Mall Cleared 12/9/2022 DANIEL CORONADO
Comm Cor/Mini-Mall Cleared 12/9/2022 DANIEL CORONADO
Hydrant and Access approval Cleared 12/17/2022 KURT CORRAL
Driveway location Cleared 1/4/2023 MIGUEL CRISOSTOMO
Eng Process Fee Ord 176,300 Cleared 1/5/2023 MEGAN GODINEZ
Sewer availability Cleared 1/5/2023 MEGAN GODINEZ
Highway dedication Cleared 4/25/2023 MEGAN GODINEZ
Permit Cleared 4/25/2023 MEGAN GODINEZ
Low Impact Development Cleared 5/4/2023 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/9/2023 MEGAN GODINEZ

Contact Information

Architect Mendoza,, Harvey Anthony; Lic. No.: C25312 737 NORTH NORA AVENUE      WEST COVINA, CA 91790
Contractor Corona Alvaro Construction Company Inc; Lic. No.: 797455-B 615 E ALLEN AVE      SAN DIMAS, CA 91773
Engineer Ibrahim,, Ibrahim Foud; Lic. No.: C86724 10300 ARROW RTE APT 12-03      RANCHO CUCAMONGA, CA 91730
Engineer Jiang,, Clarence Tzu-Wei; Lic. No.: GE2477 PO BOX 1891      WEST COVINA, CA 91793
Engineer Tiwari,, Vilas; Lic. No.: S3438 895 SANTA MARIA CIRCLE      DUARTE, CA 91010

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 5/8/2024 Partial Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/9/2024 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 5/9/2024 Partial Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 6/5/2024 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 6/6/2024 Conditional Approval KENNETH ROBERTS
Deputy Reinf. Masonry 6/7/2024 Conditional Approval JOHN KITCKO
Deputy Reinf. Masonry 6/10/2024 Conditional Approval ROBERT DAVIS
Deputy Reinf. Masonry 6/11/2024 Partial Approval JOHN KITCKO
Deputy Reinf. Masonry 6/12/2024 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 6/14/2024 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/15/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 8/20/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 8/21/2024 Approved DANNY RODRIGUEZ
Structural Steel Frame 9/6/2024 Corrections Issued DANNY RODRIGUEZ
Structural Steel Frame 10/10/2024 Approved DANNY RODRIGUEZ
Final 2/28/2025 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 2/28/2025 Approved DANNY RODRIGUEZ
Green Building Final 2/28/2025 Approved DANNY RODRIGUEZ
Green Building Rough 2/28/2025 Approved DANNY RODRIGUEZ
Reinforced Masonry Frame 2/28/2025 Partial Approval DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 2/28/2025 SGSOV No Gas DANNY RODRIGUEZ
Smoke Detectors 2/28/2025 Approved DANNY RODRIGUEZ
Verify Sprinkler Sign Off 2/28/2025 Approved DANNY RODRIGUEZ
Final 3/4/2025 Partial Inspection DANNY RODRIGUEZ
Final 3/6/2025 OK to Issue CofO DANNY RODRIGUEZ
Reinforced Masonry Frame 3/6/2025 Approved DANNY RODRIGUEZ