5130 W COLISEUM ST 90008
Certificate Information: 5130 W COLISEUM ST 90008
- Application / Permit
- 22010-10000-00315
- Plan Check / Job No.
- B22LA01079
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Install a RADCO Approved Factory Built Housing Unit over a raised floor foundation per LADBS ADU Standard Plan ADU29. Factory Built Housing per RAD-31-1030. ADU Floor Area: 315.72 SF, Width: 11’-8”, Length: 27’-10”, Height: 13’-8 1/2”. RADCO Stamped FBH Plans
- Permit Issued
- Issued on 5/18/2022
- Issuing Office
- Current Status
- CofO Issued on 4/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2022 | JOE VO |
| Corrections Issued | 1/28/2022 | JOE VO |
| Applicant returned to address corrections | 3/6/2022 | JOE VO |
| Plan Check Approved | 5/13/2022 | JOE VO |
| Issued | 5/18/2022 | APPLICANT |
| CofO in Progress | 4/27/2023 | ANTHONY EGSON |
| Permit Finaled | 4/30/2023 | DEROLD HAUFF |
| CofO Issued | 4/30/2023 | DEROLD HAUFF |
| Permit Finaled | 4/30/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/2/2022 | CHRISTOPHER ROCHA |
| Roof/Waste drainage to street | Cleared | 2/2/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 2/4/2022 | CHRISTOPHER ROCHA |
| Grading Pre-Inspection | Cleared | 3/21/2022 | KIRK LINKLATER |
| Hydrant and Access approval | Cleared | 5/6/2022 | DWAYNE LAURENT |
Contact Information
| Contractor | United Dwelling Construction Inc; Lic. No.: 1066382-B | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/11/2022 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 8/11/2022 | Approved | ANTHONY EGSON |
| Sewer | 8/22/2022 | Corrections Issued | ANTHONY EGSON |
| Underground Mechanical | 8/22/2022 | Approved | ANTHONY EGSON |
| Sewer | 8/26/2022 | No Access for Inspection | ANTHONY EGSON |
| Underground Mechanical | 8/26/2022 | No Access for Inspection | ANTHONY EGSON |
| Sewer | 8/31/2022 | Approved | ANTHONY EGSON |
| Underground Mechanical | 8/31/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 10/14/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 10/14/2022 | Approved | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 10/14/2022 | Approved | ANTHONY EGSON |
| HVAC-Rough | 10/31/2022 | Approved | ANTHONY EGSON |
| HVAC-Rough | 11/23/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 11/23/2022 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 2/10/2023 | Corrections Issued | STUART CHAPMAN |
| Final | 2/10/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Green Building Final | 2/10/2023 | Approved | STUART CHAPMAN |
| HVAC-Final | 2/10/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 2/10/2023 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 2/10/2023 | SGSOV Approved | STUART CHAPMAN |
| Service/Power Release | 2/10/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Smoke Detectors | 2/10/2023 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 4/19/2023 | Approved | ANTHONY EGSON |
| Final | 4/19/2023 | Corrections Issued | ANTHONY EGSON |
| Service/Power Release | 4/19/2023 | Approved | ANTHONY EGSON |
| Final | 4/26/2023 | OK to Issue CofO | ANTHONY EGSON |