5130 W COLISEUM ST 90008

Certificate Information: 5130 W COLISEUM ST 90008

Application / Permit
22010-10000-00315
Plan Check / Job No.
B22LA01079
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Install a RADCO Approved Factory Built Housing Unit over a raised floor foundation per LADBS ADU Standard Plan ADU29. Factory Built Housing per RAD-31-1030. ADU Floor Area: 315.72 SF, Width: 11’-8”, Length: 27’-10”, Height: 13’-8 1/2”. RADCO Stamped FBH Plans
Permit Issued
Issued on 5/18/2022
Issuing Office
Current Status
CofO Issued on 4/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2022 APPLICANT
Assigned to Plan Check Engineer 1/28/2022 JOE VO
Corrections Issued 1/28/2022 JOE VO
Applicant returned to address corrections 3/6/2022 JOE VO
Plan Check Approved 5/13/2022 JOE VO
Issued 5/18/2022 APPLICANT
CofO in Progress 4/27/2023 ANTHONY EGSON
Permit Finaled 4/30/2023 DEROLD HAUFF
CofO Issued 4/30/2023 DEROLD HAUFF
Permit Finaled 4/30/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/2/2022 CHRISTOPHER ROCHA
Roof/Waste drainage to street Cleared 2/2/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 2/4/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 2/4/2022 CHRISTOPHER ROCHA
Grading Pre-Inspection Cleared 3/21/2022 KIRK LINKLATER
Hydrant and Access approval Cleared 5/6/2022 DWAYNE LAURENT

Contact Information

Contractor United Dwelling Construction Inc; Lic. No.: 1066382-B       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/11/2022 Approved ANTHONY EGSON
Footing/Foundation/Slab 8/11/2022 Approved ANTHONY EGSON
Sewer 8/22/2022 Corrections Issued ANTHONY EGSON
Underground Mechanical 8/22/2022 Approved ANTHONY EGSON
Sewer 8/26/2022 No Access for Inspection ANTHONY EGSON
Underground Mechanical 8/26/2022 No Access for Inspection ANTHONY EGSON
Sewer 8/31/2022 Approved ANTHONY EGSON
Underground Mechanical 8/31/2022 Approved ANTHONY EGSON
BUILDING-Rough-Frame 10/14/2022 Approved ANTHONY EGSON
Green Building Rough 10/14/2022 Approved ANTHONY EGSON
Verify Sprinkler Sign Off 10/14/2022 Approved ANTHONY EGSON
HVAC-Rough 10/31/2022 Approved ANTHONY EGSON
HVAC-Rough 11/23/2022 Approved ANTHONY EGSON
PLUMBING-Final 11/23/2022 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Final 2/10/2023 Corrections Issued STUART CHAPMAN
Final 2/10/2023 Not Ready for Inspection STUART CHAPMAN
Green Building Final 2/10/2023 Approved STUART CHAPMAN
HVAC-Final 2/10/2023 Approved STUART CHAPMAN
PLUMBING-Final 2/10/2023 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 2/10/2023 SGSOV Approved STUART CHAPMAN
Service/Power Release 2/10/2023 Not Ready for Inspection STUART CHAPMAN
Smoke Detectors 2/10/2023 Approved STUART CHAPMAN
ELECTRICAL-Final 4/19/2023 Approved ANTHONY EGSON
Final 4/19/2023 Corrections Issued ANTHONY EGSON
Service/Power Release 4/19/2023 Approved ANTHONY EGSON
Final 4/26/2023 OK to Issue CofO ANTHONY EGSON