2016 1/4-1/2 E 2ND ST 90033

Certificate Information: 2016 1/4-1/2 E 2ND ST 90033

Application / Permit
22010-10000-00313
Plan Check / Job No.
B22LA01074
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePLAN* 2 (N) ACCESSORY DWELLING UNITS PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g) W/ROOF DECK The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
Permit Issued
Issued on 7/26/2022
Issuing Office
Current Status
CofO Issued on 6/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/21/2022 APPLICANT
Assigned to Plan Check Engineer 2/3/2022 LAMAR DAVIS
Corrections Issued 2/7/2022 LAMAR DAVIS
Quality Review Completed 2/13/2022 HERNAN ARREOLA
Applicant returned to address corrections 4/21/2022 LAMAR DAVIS
Applicant returned to address corrections 5/4/2022 LAMAR DAVIS
Plan Check Approved 7/25/2022 LAMAR DAVIS
Issued 7/26/2022 APPLICANT
CofO in Progress 5/11/2023 FREDDIE RIVERA
Permit Finaled 6/3/2023 DEROLD HAUFF
CofO Issued 6/3/2023 DEROLD HAUFF
Permit Finaled 6/3/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/16/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 2/18/2022 CELINA MORENO
Sewer availability Cleared 2/18/2022 CELINA MORENO
Clean Up Green Up Cleared 2/22/2022 RUBEN VASQUEZ
ZA Case Cleared 2/22/2022 RUBEN VASQUEZ
GPI Written Notices Cleared 4/21/2022 KIRK LINKLATER
Grading Pre-Inspection Cleared 4/21/2022 KIRK LINKLATER
Roof/Waste drainage to street Cleared 6/28/2022 THAN WIN

Contact Information

Contractor A T A Construction Inc; Lic. No.: 1044074-B       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/8/2022 Approved FREDDIE RIVERA
Footing/Foundation/Slab 9/8/2022 Approved FREDDIE RIVERA
Footing/Foundation/Slab 9/8/2022 Off-Hour Fees Due
METHANE-Barrier 9/8/2022 Approved FREDDIE RIVERA
METHANE-Barrier 9/8/2022 Off-Hour Fees Due
METHANE-Subgrade 9/8/2022 Approved FREDDIE RIVERA
METHANE-Subgrade 9/8/2022 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 9/9/2022 Partial Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 9/20/2022 Conditional Approval FREDDIE RIVERA
PLUMBING-Rough 9/20/2022 Approved FREDDIE RIVERA
Insulation 9/21/2022 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 9/23/2022 Partial Approval ALIZAH MAYAGOITIA
Sewer 9/23/2022 Approved ALIZAH MAYAGOITIA
Deputy Wood Construction 9/28/2022 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 9/28/2022 Approved FREDDIE RIVERA
Wood Frame 10/4/2022 Partial Approval RUBEN SALAS
ELECTRICAL-Rough 10/27/2022 Approved FREDDIE RIVERA
HVAC-Rough 10/27/2022 Approved FREDDIE RIVERA
Interior/Exterior Lathing 10/27/2022 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 10/27/2022 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 11/7/2022 Corrections Issued FREDDIE RIVERA
Green Building Rough 11/7/2022 Approved FREDDIE RIVERA
Interior/Exterior Lathing 11/7/2022 Approved FREDDIE RIVERA
MERV13>=Rough 11/7/2022 Approved FREDDIE RIVERA
METHANE-Rough 11/7/2022 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 11/7/2022 Approved FREDDIE RIVERA
Insulation 11/15/2022 Approved FREDDIE RIVERA
Drywall Nailing 11/23/2022 Approved JEFFREY MEAD
ELECTRICAL-Final 3/17/2023 Approved FREDDIE RIVERA
Gas Test 3/17/2023 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 3/17/2023 SGSOV Approved FREDDIE RIVERA
Service/Power Release 3/17/2023 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 4/12/2023 Approved FREDDIE RIVERA
Final 4/12/2023 Partial Inspection FREDDIE RIVERA
Green Building Final 4/12/2023 Partial Inspection FREDDIE RIVERA
HVAC-Final 4/12/2023 Approved FREDDIE RIVERA
MERV13>=Final 4/12/2023 Approved FREDDIE RIVERA
PLUMBING-Final 4/12/2023 Partial Inspection FREDDIE RIVERA
Service/Power Release 4/12/2023 Partial Inspection FREDDIE RIVERA
Smoke Detectors 4/12/2023 Approved FREDDIE RIVERA
Final 5/4/2023 Corrections Issued FREDDIE RIVERA
Green Building Final 5/4/2023 Approved FREDDIE RIVERA
PLUMBING-Final 5/4/2023 Approved FREDDIE RIVERA
Service/Power Release 5/4/2023 Approved FREDDIE RIVERA
Final 5/11/2023 OK to Issue CofO FREDDIE RIVERA