2016 1/4-1/2 E 2ND ST 90033
Certificate Information: 2016 1/4-1/2 E 2ND ST 90033
- Application / Permit
- 22010-10000-00313
- Plan Check / Job No.
- B22LA01074
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN* 2 (N) ACCESSORY DWELLING UNITS PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g) W/ROOF DECK The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
- Permit Issued
- Issued on 7/26/2022
- Issuing Office
- Current Status
- CofO Issued on 6/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/3/2022 | LAMAR DAVIS |
| Corrections Issued | 2/7/2022 | LAMAR DAVIS |
| Quality Review Completed | 2/13/2022 | HERNAN ARREOLA |
| Applicant returned to address corrections | 4/21/2022 | LAMAR DAVIS |
| Applicant returned to address corrections | 5/4/2022 | LAMAR DAVIS |
| Plan Check Approved | 7/25/2022 | LAMAR DAVIS |
| Issued | 7/26/2022 | APPLICANT |
| CofO in Progress | 5/11/2023 | FREDDIE RIVERA |
| Permit Finaled | 6/3/2023 | DEROLD HAUFF |
| CofO Issued | 6/3/2023 | DEROLD HAUFF |
| Permit Finaled | 6/3/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/16/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 2/18/2022 | CELINA MORENO |
| Sewer availability | Cleared | 2/18/2022 | CELINA MORENO |
| Clean Up Green Up | Cleared | 2/22/2022 | RUBEN VASQUEZ |
| ZA Case | Cleared | 2/22/2022 | RUBEN VASQUEZ |
| GPI Written Notices | Cleared | 4/21/2022 | KIRK LINKLATER |
| Grading Pre-Inspection | Cleared | 4/21/2022 | KIRK LINKLATER |
| Roof/Waste drainage to street | Cleared | 6/28/2022 | THAN WIN |
Contact Information
| Contractor | A T A Construction Inc; Lic. No.: 1044074-B | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/8/2022 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 9/8/2022 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 9/8/2022 | Off-Hour Fees Due | |
| METHANE-Barrier | 9/8/2022 | Approved | FREDDIE RIVERA |
| METHANE-Barrier | 9/8/2022 | Off-Hour Fees Due | |
| METHANE-Subgrade | 9/8/2022 | Approved | FREDDIE RIVERA |
| METHANE-Subgrade | 9/8/2022 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 9/9/2022 | Partial Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2022 | Conditional Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 9/20/2022 | Approved | FREDDIE RIVERA |
| Insulation | 9/21/2022 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Sewer | 9/23/2022 | Approved | ALIZAH MAYAGOITIA |
| Deputy Wood Construction | 9/28/2022 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2022 | Approved | FREDDIE RIVERA |
| Wood Frame | 10/4/2022 | Partial Approval | RUBEN SALAS |
| ELECTRICAL-Rough | 10/27/2022 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 10/27/2022 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 10/27/2022 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 10/27/2022 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 11/7/2022 | Corrections Issued | FREDDIE RIVERA |
| Green Building Rough | 11/7/2022 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 11/7/2022 | Approved | FREDDIE RIVERA |
| MERV13>=Rough | 11/7/2022 | Approved | FREDDIE RIVERA |
| METHANE-Rough | 11/7/2022 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 11/7/2022 | Approved | FREDDIE RIVERA |
| Insulation | 11/15/2022 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 11/23/2022 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 3/17/2023 | Approved | FREDDIE RIVERA |
| Gas Test | 3/17/2023 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 3/17/2023 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 3/17/2023 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 4/12/2023 | Approved | FREDDIE RIVERA |
| Final | 4/12/2023 | Partial Inspection | FREDDIE RIVERA |
| Green Building Final | 4/12/2023 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Final | 4/12/2023 | Approved | FREDDIE RIVERA |
| MERV13>=Final | 4/12/2023 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 4/12/2023 | Partial Inspection | FREDDIE RIVERA |
| Service/Power Release | 4/12/2023 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 4/12/2023 | Approved | FREDDIE RIVERA |
| Final | 5/4/2023 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 5/4/2023 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 5/4/2023 | Approved | FREDDIE RIVERA |
| Service/Power Release | 5/4/2023 | Approved | FREDDIE RIVERA |
| Final | 5/11/2023 | OK to Issue CofO | FREDDIE RIVERA |