11427 S CLOVIS AVE 90059
Certificate Information: 11427 S CLOVIS AVE 90059
- Application / Permit
- 22010-10000-00303
- Plan Check / Job No.
- B22LA00991
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (E) GARAGE WITH AN ADDITION TO BE CONVERTED TO A DETACHED ADU PER ORDINANCE (1-STORY)
- Permit Issued
- Issued on 5/11/2022
- Issuing Office
- Current Status
- CofO Issued on 2/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2022 | CARLOS MONTES |
| Corrections Issued | 1/27/2022 | CARLOS MONTES |
| Applicant returned to address corrections | 3/23/2022 | CARLOS MONTES |
| Plan Check Approved | 5/2/2022 | CARLOS MONTES |
| Issued | 5/11/2022 | APPLICANT |
| CofO in Progress | 2/2/2024 | JOHN KLARIN |
| Permit Finaled | 2/13/2024 | ANSON MAGLASANG |
| CofO Issued | 2/13/2024 | ANSON MAGLASANG |
| Permit Finaled | 2/13/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 3/14/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 3/16/2022 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 3/31/2022 | AMAAN MALIK |
| Community Plan Implem. Overlay | Cleared | 4/26/2022 | HELEN JADALI |
Contact Information
| Contractor | Next Generation Builders; Lic. No.: 1069728-B | 1858 ECHO PARK AVE LOS ANGELES, CA 90026 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Wood Construction | 8/24/2023 | Conditional Approval | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 8/25/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Rough | 8/25/2023 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2023 | Partial Approval | JAMES CHAVEZ |
| Gas Test | 8/25/2023 | Approved | JAMES CHAVEZ |
| HVAC-Rough | 8/25/2023 | Approved | JAMES CHAVEZ |
| MERV13>=Rough | 8/25/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Rough | 8/25/2023 | Approved | JAMES CHAVEZ |
| Special/Order Compliance | 8/25/2023 | Corrections Issued | JAMES CHAVEZ |
| Wood Frame | 8/25/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 9/6/2023 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 9/6/2023 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2023 | Approved | JOHN KLARIN |
| Green Building Rough | 9/6/2023 | Approved | JOHN KLARIN |
| Insulation | 9/12/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 9/12/2023 | Approved | JOHN KLARIN |
| Drywall Nailing | 9/18/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 9/29/2023 | Approved | JOHN KLARIN |
| Final | 12/28/2023 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 12/28/2023 | Approved | JOHN KLARIN |
| Green Building Final | 12/28/2023 | Corrections Issued | JOHN KLARIN |
| MERV13>=Final | 12/28/2023 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 12/28/2023 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 12/28/2023 | Approved | JOHN KLARIN |
| Final | 1/25/2024 | Corrections Issued | JAMES CHAVEZ |
| Service/Power Release | 1/25/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Final | 1/31/2024 | Approved | JOHN KLARIN |
| Final | 1/31/2024 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 1/31/2024 | Approved | JOHN KLARIN |
| HVAC-Final | 1/31/2024 | Approved | JOHN KLARIN |
| PLUMBING-Final | 1/31/2024 | Approved | JOHN KLARIN |
| Final | 2/2/2024 | OK to Issue CofO | JOHN KLARIN |
| Service/Power Release | 2/5/2024 | Approved | JOHN KLARIN |