10150 S GRAPE ST 90002

Certificate Information: 10150 S GRAPE ST 90002

Application / Permit
22010-10000-00297
Plan Check / Job No.
B22LA00955
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 4 STORY TYPE V-A, 57 UNITS APARTMENT BUILDING (BLDG B)
Permit Issued
Issued on 6/23/2023
Issuing Office
Metro
Current Status
CofO Issued on 7/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/9/2022 APPLICANT
Assigned to Plan Check Engineer 2/18/2022 GARO TELMI
Corrections Issued 3/4/2022 GARO TELMI
Quality Review Completed 3/8/2022 KEN GILL
Building Plans Picked Up 3/10/2022 APPLICANT
Applicant returned to address corrections 4/4/2022 GARO TELMI
Applicant returned to address corrections 5/3/2022 GARO TELMI
Applicant returned to address corrections 6/14/2022 GARO TELMI
Applicant returned to address corrections 7/14/2022 GARO TELMI
Applicant returned to address corrections 8/25/2022 GARO TELMI
Applicant returned to address corrections 1/24/2023 GARO TELMI
Applicant returned to address corrections 2/9/2023 GARO TELMI
Applicant returned to address corrections 3/15/2023 GARO TELMI
Applicant returned to address corrections 4/27/2023 GARO TELMI
Applicant returned to address corrections 5/25/2023 GARO TELMI
Plan Check Approved 5/30/2023 GARO TELMI
Issued 6/23/2023 APPLICANT
TCO Issued (Expire Date: 11-12-2025) 5/16/2025 ADAM BURGESS
CofO in Progress 7/8/2025 JAMES POWERS
CofO Issued 7/8/2025 ERNESTO CORRAL
Permit Finaled 7/8/2025 ERNESTO CORRAL

Permit Application Clearance Information

Trees in Parkway Cleared 5/13/2022 ADALBERTO VERA
Hydrant and Access approval Cleared 5/15/2022 JOHN CONNEALLY
Address approval Cleared 5/24/2022 CINDY QI
Highway dedication Cleared 5/24/2022 CINDY QI
Permit Cleared 5/24/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 6/21/2022 CINDY QI
Building over 36-ft Cleared 8/26/2022 CALOSHA APPROVED
Fire Marshal Fire Life Safety Cleared 2/10/2023 PEJMAN NOORI
Frnt yard landscape/Water mgmt Cleared 2/21/2023 JASON CHAN
Opn space landscape/Water mgmt Cleared 2/21/2023 JASON CHAN
Green Code Cleared 2/22/2023 AARON COSTA
Sewer availability Cleared 3/24/2023 CHRISTOPHER ROCHA
Low Impact Development Cleared 5/2/2023 ORVAL HERNANDEZ-MARCI
DAS Clearance Cleared 5/3/2023 GARO TELMI
Public Housing Cleared 5/3/2023 JOEL LAUNCHBAUGH
Work Adjacent to Public Way Cleared 5/4/2023 LARRY LEE
Drainage to Storm Drain Cleared 5/16/2023 LINDA MARGARET
Roof/Waste drainage to street Cleared 5/16/2023 LINDA MARGARET
Specific Plan Cleared 5/16/2023 DAISY BENICIA
CPC Cleared 5/17/2023 JASON CHAN
Miscellaneous Cleared 5/17/2023 JASON CHAN
Miscellaneous Cleared 5/17/2023 JASON CHAN
Prkng lot landscape/Water mgmt Cleared 5/17/2023 JASON CHAN
Site Plan review Cleared 5/17/2023 JASON CHAN
Tract Map conditions Cleared 5/17/2023 JASON CHAN
ZA Case Cleared 5/17/2023 JASON CHAN

Contact Information

Architect Barar,, Ali; Lic. No.: C25584 624 SOUTH ORANGE GROVE BLVD.      PASADENA, CA 91105
Contractor Walton Construction Inc; Lic. No.: 1034491-B 358 E FOOTHILL BLVD STE 100      SAN DIMAS, CA 91773
Engineer Abantao,, Marlo Christoph Macaraeg; Lic. No.: C93225 230 W 47TH ST      LONG BEACH, CA 90805
Engineer Adams,, Jelisa; Lic. No.: GE3092 26632 EL TOBOSO      MISSION VIEJO, CA 92691
Engineer Braley,, J Edward; Lic. No.: L8446 163 TECHNOLOGY DRIVE   SUITE 100    IRVINE, CA 92618
Engineer Choi,, David; Lic. No.: S4784 1327 LOMA AVENUE      LONG BEACH, CA 90804

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/26/2023 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 12/29/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/12/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/13/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/14/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/15/2024 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 2/15/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/16/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/20/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/15/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/22/2024 Partial Approval JAMES POWERS
Insulation 4/2/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/3/2024 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/8/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 4/12/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/19/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/2/2024 Partial Approval JAMES POWERS
Insulation 6/10/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/20/2024 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/21/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 6/21/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/24/2024 Partial Approval JAMES POWERS
Insulation 7/2/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/9/2024 Partial Approval JAMES POWERS
Insulation 7/11/2024 Partial Approval JAMES POWERS
Insulation 7/25/2024 Partial Approval JAMES POWERS
Insulation 8/14/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 8/14/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 8/16/2024 Partial Approval JAMES POWERS
Insulation 8/19/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 8/19/2024 Partial Approval JAMES POWERS
Insulation 8/22/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 8/26/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 8/26/2024 Partial Approval JAMES POWERS
Drywall Nailing 8/28/2024 Partial Approval JAMES POWERS
Insulation 9/4/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/6/2024 Partial Approval JAMES POWERS
Drywall Nailing 9/11/2024 Partial Approval JAMES POWERS
Drywall Nailing 9/19/2024 Partial Approval JAMES POWERS
Drywall Nailing 9/26/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 9/26/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 10/2/2024 Partial Approval JAMES POWERS
Drywall Nailing 10/4/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 10/11/2024 Partial Approval RAMAZANALI ALMASI
Interior/Exterior Lathing 10/21/2024 Partial Approval JAMES POWERS
Special/Order Compliance 12/10/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 12/30/2024 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 2/11/2025 Partial Approval JAMES POWERS
Final 3/14/2025 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 3/14/2025 Approved JAMES POWERS
Green Building Final 3/14/2025 Approved JAMES POWERS
Green Building Rough 3/14/2025 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 3/14/2025 SGSOV Not Ready JAMES POWERS
Smoke Detectors 3/14/2025 Approved JAMES POWERS
Verify Sprinkler Sign Off 3/14/2025 Not Ready for Inspection JAMES POWERS
Wood Frame 3/14/2025 Partial Approval JAMES POWERS
Pre-Inspection 4/1/2025 Partial Approval JAMES POWERS
Special/Order Compliance 4/1/2025 Partial Approval JAMES POWERS
Final 4/3/2025 OK for TCO JAMES POWERS
SGSOV-Seismic Gas S/O Valve 4/3/2025 SGSOV Approved JAMES POWERS
Verify Sprinkler Sign Off 4/3/2025 Approved JAMES POWERS
Wood Frame 4/3/2025 Approved JAMES POWERS
Final 4/22/2025 OK for TCO JAMES POWERS
Final 5/12/2025 Not Ready for Inspection LARRY ARNICK
Final 5/14/2025 Partial Inspection LARRY ARNICK
Pre-Inspection 5/15/2025 Partial Inspection LARRY ARNICK
Order to Comply 5/16/2025 Not Required LARRY ARNICK
Special/Order Compliance 5/16/2025 Partial Inspection LARRY ARNICK
Final 7/2/2025 Not Ready for Inspection JAMES POWERS
Deputy Steel/Welding 7/8/2025 Partial Approval JAMES POWERS
Deputy Wood Construction 7/8/2025 Partial Approval JAMES POWERS
Final 7/8/2025 OK to Issue CofO JAMES POWERS