10110 S GRAPE ST 90002
Certificate Information: 10110 S GRAPE ST 90002
- Application / Permit
- 22010-10000-00296
- Plan Check / Job No.
- B22LA00955
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 4 STORY 33 UNITS TYPE V-A APARTMENT BUILDING (BLDG A)
- Permit Issued
- Issued on 6/23/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2022 | GARO TELMI |
| Corrections Issued | 3/4/2022 | GARO TELMI |
| Quality Review Completed | 3/8/2022 | KEN GILL |
| Building Plans Picked Up | 3/10/2022 | APPLICANT |
| Applicant returned to address corrections | 4/4/2022 | GARO TELMI |
| Applicant returned to address corrections | 5/3/2022 | GARO TELMI |
| Applicant returned to address corrections | 6/14/2022 | GARO TELMI |
| Applicant returned to address corrections | 7/14/2022 | GARO TELMI |
| Applicant returned to address corrections | 8/25/2022 | GARO TELMI |
| Applicant returned to address corrections | 1/24/2023 | GARO TELMI |
| Applicant returned to address corrections | 2/9/2023 | GARO TELMI |
| Applicant returned to address corrections | 3/15/2023 | GARO TELMI |
| Applicant returned to address corrections | 4/27/2023 | GARO TELMI |
| Applicant returned to address corrections | 5/25/2023 | GARO TELMI |
| Plan Check Approved | 5/30/2023 | GARO TELMI |
| Issued | 6/23/2023 | APPLICANT |
| TCO Issued (Expire Date: 11-12-2025) | 5/16/2025 | ADAM BURGESS |
| CofO in Progress | 7/8/2025 | JAMES POWERS |
| Permit Finaled | 7/8/2025 | ERNESTO CORRAL |
| CofO Issued | 7/8/2025 | ERNESTO CORRAL |
| Permit Finaled | 7/8/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 5/13/2022 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 5/15/2022 | JOHN CONNEALLY |
| Address approval | Cleared | 5/19/2022 | CINDY QI |
| Highway dedication | Cleared | 5/19/2022 | CINDY QI |
| Permit | Cleared | 5/19/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 6/21/2022 | CINDY QI |
| CPC | Cleared | 7/15/2022 | JASON CHAN |
| Miscellaneous | Cleared | 7/15/2022 | JASON CHAN |
| Miscellaneous | Cleared | 7/15/2022 | JASON CHAN |
| Tract Map conditions | Cleared | 7/15/2022 | JASON CHAN |
| ZA Case | Cleared | 7/15/2022 | JASON CHAN |
| Building over 36-ft | Cleared | 8/26/2022 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 8/26/2022 | CALOSHA APPROVED |
| Green Code | Cleared | 2/15/2023 | AARON COSTA |
| Frnt yard landscape/Water mgmt | Cleared | 2/21/2023 | JASON CHAN |
| Opn space landscape/Water mgmt | Cleared | 2/21/2023 | JASON CHAN |
| Fire Marshal Fire Life Safety | Cleared | 3/22/2023 | VIDAL GARCIA |
| Sewer availability | Cleared | 3/23/2023 | CHRISTOPHER ROCHA |
| Public Housing | Cleared | 5/1/2023 | JOEL LAUNCHBAUGH |
| Low Impact Development | Cleared | 5/2/2023 | ORVAL HERNANDEZ-MARCI |
| DAS Clearance | Cleared | 5/3/2023 | GARO TELMI |
| Work Adjacent to Public Way | Cleared | 5/4/2023 | LARRY LEE |
| Drainage to Storm Drain | Cleared | 5/16/2023 | LINDA MARGARET |
| Miscellaneous | Cleared | 5/16/2023 | DAISY BENICIA |
| Miscellaneous | Cleared | 5/16/2023 | DAISY BENICIA |
| Roof/Waste drainage to street | Cleared | 5/16/2023 | LINDA MARGARET |
| Specific Plan | Cleared | 5/16/2023 | DAISY BENICIA |
| Prkng lot landscape/Water mgmt | Cleared | 5/17/2023 | JASON CHAN |
| Site Plan review | Cleared | 5/17/2023 | JASON CHAN |
Contact Information
| Architect | Barar,, Ali; Lic. No.: C25584 | 624 SOUTH ORANGE GROVE BLVD. PASADENA, CA 91105 |
| Contractor | Walton Construction Inc; Lic. No.: 1034491-B | 358 E FOOTHILL BLVD STE 100 SAN DIMAS, CA 91773 |
| Engineer | Abantao,, Marlo Christoph Macaraeg; Lic. No.: C93225 | 230 W 47TH ST LONG BEACH, CA 90805 |
| Engineer | Adams,, Jelisa; Lic. No.: GE3092 | 26632 EL TOBOSO MISSION VIEJO, CA 92691 |
| Engineer | Braley,, J Edward; Lic. No.: L8446 | 163 TECHNOLOGY DRIVE SUITE 100 IRVINE, CA 92618 |
| Engineer | Choi,, David; Lic. No.: S4784 | 1327 LOMA AVENUE LONG BEACH, CA 90804 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/26/2023 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 12/29/2023 | Partial Approval | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 12/29/2023 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 1/19/2024 | Approved | JAMES POWERS |
| Deputy Reinf. Concrete | 1/23/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 1/25/2024 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 1/26/2024 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 1/29/2024 | Partial Approval | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 1/29/2024 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 1/30/2024 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 1/31/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Floor/Roof Diaphrgm/Shear Wall | 2/29/2024 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2024 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2024 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 3/27/2024 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 4/3/2024 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2024 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2024 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 5/3/2024 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 5/14/2024 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 5/30/2024 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2024 | Partial Approval | JAMES POWERS |
| Insulation | 6/6/2024 | Partial Approval | ALFREDO LOPEZ |
| Insulation | 6/20/2024 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 6/21/2024 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 7/9/2024 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2024 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 7/9/2024 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 7/17/2024 | Partial Approval | JAMES POWERS |
| Insulation | 7/25/2024 | Partial Approval | JAMES POWERS |
| Pre-Inspection | 7/25/2024 | Not Ready for Inspection | JAMES POWERS |
| Insulation | 7/30/2024 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 7/30/2024 | Not Ready for Inspection | JAMES POWERS |
| Insulation | 8/2/2024 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 8/6/2024 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 8/8/2024 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 8/13/2024 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 8/20/2024 | Partial Approval | JAMES POWERS |
| Interior/Exterior Lathing | 8/26/2024 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 8/28/2024 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 9/6/2024 | Partial Approval | JAMES POWERS |
| Interior/Exterior Lathing | 9/6/2024 | Not Ready for Inspection | JAMES POWERS |
| Interior/Exterior Lathing | 9/9/2024 | Partial Approval | JAMES POWERS |
| Interior/Exterior Lathing | 9/12/2024 | Approved | JAMES POWERS |
| Drywall Nailing | 10/4/2024 | Partial Approval | JAMES POWERS |
| Special/Order Compliance | 12/10/2024 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 12/30/2024 | Partial Approval | LARRY ARNICK |
| Deputy Reinf. Concrete | 2/3/2025 | Conditional Approval | LARRY ARNICK |
| Final | 3/14/2025 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 3/14/2025 | Approved | JAMES POWERS |
| Green Building Final | 3/14/2025 | Approved | JAMES POWERS |
| Green Building Rough | 3/14/2025 | Approved | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 3/14/2025 | SGSOV Not Ready | JAMES POWERS |
| Smoke Detectors | 3/14/2025 | Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 3/14/2025 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 3/14/2025 | Partial Approval | JAMES POWERS |
| Final | 4/22/2025 | OK for TCO | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 4/22/2025 | SGSOV No Gas | JAMES POWERS |
| Verify Sprinkler Sign Off | 4/22/2025 | Approved | JAMES POWERS |
| Wood Frame | 4/22/2025 | Approved | JAMES POWERS |
| Final | 5/12/2025 | Not Ready for Inspection | LARRY ARNICK |
| Final | 5/14/2025 | Partial Inspection | LARRY ARNICK |
| Pre-Inspection | 5/15/2025 | Partial Approval | LARRY ARNICK |
| Order to Comply | 5/16/2025 | Not Required | LARRY ARNICK |
| Special/Order Compliance | 5/16/2025 | Partial Approval | LARRY ARNICK |
| Final | 7/2/2025 | Not Ready for Inspection | JAMES POWERS |
| Deputy Reinf. Concrete | 7/8/2025 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 7/8/2025 | Partial Approval | JAMES POWERS |
| Final | 7/8/2025 | OK to Issue CofO | JAMES POWERS |