6513 S ARLINGTON AVE 90043
Certificate Information: 6513 S ARLINGTON AVE 90043
- Application / Permit
- 22010-10000-00259
- Plan Check / Job No.
- B22LA00856
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New RADCO Approved Factory Built Housing Unit over a raised floor foundation per LADBS ADU Standard Plan ADU29. Factory Built Housing per RAD-31-1030. ADU
- Permit Issued
- Issued on 4/5/2022
- Issuing Office
- Current Status
- CofO Issued on 3/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/26/2022 | JOE VO |
| Corrections Issued | 1/27/2022 | JOE VO |
| Applicant returned to address corrections | 2/10/2022 | JOE VO |
| Plan Check Approved | 3/29/2022 | JOE VO |
| Issued | 4/5/2022 | APPLICANT |
| CofO in Progress | 3/6/2023 | ALIZAH MAYAGOITIA |
| Permit Finaled | 3/9/2023 | DEROLD HAUFF |
| CofO Issued | 3/9/2023 | DEROLD HAUFF |
| Permit Finaled | 3/9/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/27/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 1/27/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2022 | JEANIE LAM |
| Sewer availability | Cleared | 2/1/2022 | JEANIE LAM |
| Construction near power lines | Cleared | 3/21/2022 | RIDWAN HARDY |
Contact Information
| Contractor | United Dwelling Construction Inc; Lic. No.: 1066382-B | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/8/2022 | Approved | ENRIQUE MIRELES |
| Sewer | 7/8/2022 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 7/8/2022 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 7/11/2022 | Approved | ENRIQUE MIRELES |
| Sewer | 7/11/2022 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 7/11/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 7/25/2022 | Conditional Approval | HORACE FULTZ |
| Green Building Rough | 7/25/2022 | Not Ready for Inspection | HORACE FULTZ |
| Verify Sprinkler Sign Off | 7/25/2022 | Approved | HORACE FULTZ |
| HVAC-Rough | 8/12/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 10/27/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 10/27/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 10/27/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 10/27/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 10/27/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 10/27/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 10/27/2022 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 10/27/2022 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Service/Power Release | 10/27/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 10/27/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 11/14/2022 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Final | 11/14/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 11/14/2022 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 11/14/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 12/12/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 12/12/2022 | Approved | ENRIQUE MIRELES |
| Final | 12/12/2022 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 12/12/2022 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 12/12/2022 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 12/12/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 12/12/2022 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 12/12/2022 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 12/12/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 3/2/2023 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 3/2/2023 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 3/2/2023 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 3/2/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 3/3/2023 | OK to Issue CofO | ALIZAH MAYAGOITIA |